|
CPM
SCHEDULING CAN HELP IN RESOLUTION OF DISPUTES
Copyright,
Hill International, Inc., 2000
According,
to data compiled by the American Arbitration Association, the building
industry has witnessed an explosion of construction claims in recent
years. with an increase of more than 130 percent over the past decade.
Many of these disputes involved delays in the completion of a
construction project. As
Alternative Dispute Resolution (ADR) becomes an increasingly popular
method of resolving construction disputes without litigation, the trend
toward litigation may decelerate.
Detailed
reports and records always have been an essential factor in construction
claims litigation. Critical
Path Method (CPM) scheduling, a method of plotting. tracking and
controlling the numerous activities involved in construction, can be an
effective instrument for assessing the progress of a project or for
determining the impact of one delay on all subsequent activities.
During litigation. accurately created and updated CPM schedules
can provide an indisputable source of information when attempting to
resolve time-related disputes outside of the courtroom.
Before CPM scheduling can be fully constructive, however, it must
be used more effectively by all parties involved in the construction
process.
Although
CPM scheduling was introduced to the construction industry nearly 30
years ago, it is still not widely used.
Even when it is used, it is often underutilized, employed merely
as an aid for reporting and recording project progress.
In the mid-1960s, CPM scheduling was used selectively, due
largely to the inaccessibility of computer equipment.
The schedules were prepared by mainframe computers through a
costly, multi-tiered process that started with a cadre of planners who
first manually drew out the logic and input data onto data cards.
Some
errors had to be investigated, followed by the running and re-running of
the data to obtain a precise schedule.
Through
advances in personal computing, such difficulties have been diminished
and the cost and effort of producing an accurate, well detailed CPM have
dropped dramatically. With less expensive and more user-friendly options
now available, no firm need be without a CPM scheduling package.
For
greater effectiveness in ADR, a conscious effort must be made to use CPM
scheduling more often. The following steps can prove helpful in increasing a CPM's
effectiveness.
1.
Bring CPM Scheduling into the Mainstream of Project Management
By
establishing procedures including detailed scheduling specifications,
timely approval or disapproval, reality checks, strict reporting, and
updating requirements, CPM scheduling can become a central component of
a construction project.
Detailed
scheduling specifications. Recent
contract specifications now require the use of CPM techniques in project
scheduling. Though this is a promising development, CPM schedules often
still do not include the components that make them useful project tools.
For this reason, when requesting a deadline extension, one should
be required to provide not only a CPM schedule analysis, but also
particulars such as the number of activities in the CPM, the level of
detail, and resource loading requirements.
Once the project schedule has been set up in CPM form, it can be
used in the ADR process to analyze time-related disputes more
effectively. Examples of
these procedures are scheduling specifications currently used by the
U.S. Army Corps of Engineers, the Veterans Administration. and the Naval
Facilities Engineering Command.
Timely
approval or disapproval of CPM schedule.
To be most effective, the CPM schedule must be approved or
rejected within the first four to six weeks of the start of the project.
Otherwise, delays in the establishment and monitoring of the
project schedule against the original as-planned schedule may eventually
cause disputes between contractor and owner since each parry may be
using a different baseline to measure delays. In many instances, when
approval of the as planned schedule is delayed, the project has advanced
so far by the time a CPM schedule is approved that data on the CPM
schedule does not accurately reflect the realities of the project.
Because
a common baseline is so vital to the determination of project delays,
CPM approval must be a top priority at the start of every project.
In fact, timely approvals should be required by the contract.
When both parties are following a common baseline schedule,
time-related disputes that arise during the course of the project can be
clearly understood and are more likely to be resolved in the ADR
process.
Reporting
and updating of the CPM schedule. Once
prepared. the CPM schedule must be updated regularly through a
well-defined procedure established and agreed greed upon by both the
owner and the contractor. The
CPM update should be prepared with input from the project team and only
by those intimately familiar with the project.
During the updating process, the integrity of the CPM must not be
compromised by either unilateral changes in logic or changes in the
constraint dates. Reporting
must be consistent. and all updates must be carried out on the original
or agreed-upon base schedule.
To make
the CPM's logic and effects easier to follow after updates, both parties
must agree to all changes in logic, activities, or constraints before
the updating process starts. Most
importantly, the updated CPM must indicate both the percentage of an
activity that is complete and the remaining duration for that particular
activity. Providing one without the other can lead to confusion over
the actual status of the project.
Reporting
and updating the CPM provides concurrent data, so it is important that
such information is preserved in an easily utilized, retrievable form.
Generating this information electronically will make it more
accessible in the ADR stage
Reality
check of CPM schedule. Updating
the CPM improperly can cause discrepancies between the information on
the schedule and the actual construction progress.
Therefore. a validity or reality check of the CPM schedule can
help gauge the authenticity of what the schedule reflects.
This exercise also will make the CPM schedule a live document
performing its proper function, while making it a more effective tool in
the ADR process.
Improper
updating can be caused by a number of factors.
For example, if the CPM being used by the contractor has been
corrupted and its logic has been changed unilaterally, the report's
contents are an inaccurate representation of the project.
Therefore, the float posture for the activities is different from
the actual activity taking place on the project, and its Critical Path
is different. To avoid such
discrepancies, owners and contractors should schedule bimonthly meetings
to review and check the current CPM for validity.
2.
Shadow Schedule
A
shadow schedule is a replicated CPM schedule prepared by the owner to
match the contractor's CPM. Creating
a shadow schedule provides two advantages.
First. it ensures that the owner is fully aware of the dynamics
of the project. Second, the owner holds an independent check of the
contractor's respective update reports.
It
is important to remember that a shadow schedule is a living document,
not an archival record used only at the end of the project for claims
preparation. Owners must
discuss and verify the shadow schedule and subsequent updates with the
contractor on a regular basis so that as the project moves along, the
owner and the contractor have an equally thorough understanding of its
“pinch points.” Ideally,
all disagreements should be documented so effective steps can be taken
to resolve disputes. If
updated properly at the end of the project, shadow schedules also can be
used both as the project’s as-built schedule and as a tool to resolve
delay claims in ADR.
3.
CPM Training
Because
some of its most basic concepts are largely misunderstood, CPM
scheduling is often perceived as esoteric.
Training sessions are the best way to address this misperception
and ensure that all key project personnel are conversant with CPM
scheduling techniques.
Training
in the use of CPM scheduling is crucial.
A concerted effort must be made to educate project personnel and
make them conversant with the process.
Basic training courses can explain the fundamentals of CPM
scheduling, including:
·
Critical
Path
·
Float
·
Free
Float and Total Float
·
Early/Late
Start & Finish Dates
·
Forward
Pass Calculation and Backward Pass Calculations
·
Logic
·
Constraints
·
Activity
Durations
·
Percentage
Complete
·
Remaining
Durations
·
Resource
Allocation and Resource
·
Leveling
·
Work
Breakdown Structure
When
more project personnel are acquainted with the elements of CPM
scheduling, the chances are greater that an effective CPM schedule will
be available for use in the ADR process.
4.
Software Compatibility
As
CPM scheduling software becomes more widely used in the construction
industry, owners and contractors who work together must agree to use
compatible computer programs. There
have been instances on a few major projects where the owner's CPM
scheduling software was incompatible with the contractor's, leading to
discrepancies between the contractor's and owner's progress data.
In many instances. the float was incorrectly transferred and the
critical paths shown were vastly different.
This kind of inconsistency can lead to further confusion when
delays are evaluated in the ADR environment.
Making
the effort to compare software between owner and contractor at the start
of a project will obviously save a great deal of time and anguish if a
dispute arises during or after construction.
5.
Time Impact Analysis
Finally,
Time Impact Analysis developed using CPM techniques can play a key role
in ADR by demonstrating the effect of specific delays on the project.
It is most effective when it is developed using CPM scheduling
techniques. Pinpointing,
isolating, and quantifying the time impact caused by a specific delay
can help determine the time relationship to any other delays that may
have occurred or may be occurring at the same time.
The
use of Time Impact Analysis, in which fragments are used to simulate the
impact of a delay or a change, should be more extensively practiced.
Relatively simple and easily learned. techniques of this type of
analysis are key to type representing the respective positions of the
two parties and their impact. or lack of impact. on delays.
As
ADR is used more often to settle construction claims, the industry
should focus on the value of CPM scheduling.
Clearly. its implementation will be of great value in the attempt
to resolve time-related claims more effectively.
|