Contractor Required to Indemnify Negligent Party
Pursuant to the indemnity clause of its lease agreement with a
landowner (Washington Street Investments (WSI), the Goettl Air Conditioning Company
(Goettl) agreed to indemnify WSI for all damages caused in whole or in part by Goettl's
negligence. When one of Goettl's employees (Cunningham) fell through a skylight while on
the roof of the building, that employee recovered workers compensation and then sued WSI
for additional damages.
WSI demanded that Goettl defend it per the indemnity agreement but Goettl refused to do
so. WSI and Cunningham settled the case, and WSI assigned its indemnity rights to
Cunningham who then sued Goettl to recover the damages. At trial, the court granted
summary judgment to Cunningham, concluding that Goettl was required by the terms of what
it deemed to be a "general indemnity agreement" to indemnify WSI. This decision
was reversed by the first appellate court on the basis that the court believed that the
indemnity did not apply where the damages were caused by the indemnitee (WSI's) own
negligence. Specifically, the court found that WSI's failure to conduct site inspections
recommended by its engineer created a material question of fact as to whether WSI was
actively negligent. Presumably, the court believed that if WSI was actively negligent, the
indemnification requirement would not apply.
This decision was reversed by the Arizona Supreme Court which found that even if the
indemnitee had been actively negligent, the indemnity requirement still applied. The
indemnity provision in question reads as follows:
Lessor (WSI) shall not be liable to Lessee (Goettl] ... for any injury
... resulting from the condition of, or any defect in, the Premises. Lessee hereby agrees
to indemnify and hold Lessor harmless from and defend Lessor against any and all claims
... arising out of or in connection with ... any accident ... in or about Premises, when
such injury ... shall be caused in whole or in part by ... any act or negligence of
Lessee....
Because the indemnity clause did not specifically state what would result if the
indemnitee (WSI) was itself negligent, the court found it to be a "general
indemnity." As a general rule, an indemnitee under such an agreement is only entitled
to indemnitee from the consequences of other parties' negligence as well as its own
passive negligence, but is not entitled to indemnitee against its own active negligence.
But where there is clear and unequivocal language demonstrating that the indemnitee is be
indemnified despite its active negligence, the clause will be enforced as written.
In this case, the court found that the language was clear and unambiguous, and that
Goettl was, therefore, required to indemnify WSI (and now Cunningham) for the damages.
An interesting aspect of the case was that when Goettl refused to participate in the
defense, WSI settled the matter directly with Cunningham, without input or participation
from Goettl. Because Goettl had ample notice by WSI of these proceedings and
circumstances, the court ruled that the settlement was binding against Goettl. The rule is
that so long as the indemnitor (Goettl) had reasonable notice of the action and an
opportunity to assume or participate in the defense, the judgment against the indemnitee
is binding against the indemnitor. Cunningham v. Goettl Air Conditioning, Inc. No.
CV-97-0511-PR, 1999 Ariz. LEXIS 67, 1999 WL 312544 (Ariz. May 19, 1999).
Article Copyright ã 1999,
ConstructionRisk.com, LLC - Virginia
______________________________________
"No-Damage-for-Delay" Clause Unenforceable where
City Withheld Superior Knowledge about Site Conditions and Caused the Delay
A state court in California declined to enforce a "no-damage-for-delay"
clause that would have deprived a construction contractor of equitable adjustment for time
delays and expenses caused by the project owner, City of Los Angeles. The city had
superior knowledge concerning site conditions which it withheld from the bidders. The city
also impeded access to the site.
In its Invitation for Bids (IFB), the city advertised for bids for the rehabilitation
of the Venice Canals. This work included excavation of material on the bottom of the
canals and the disposal of that material. The city learned while the IFB was still pending
that the material on the floor of the canals was contaminated with pollutants and could
not be disposed of in unclassified landfills as previously anticipated. The city also
learned that work at part of the site would be prohibited by federal agencies during the
months of April through September due to nesting terns.
In response to what it learned about the site, the city issued a revision to the IFB
stating: "The construction stages may be interchanged to suit the requirements of any
permitting agency or as directed by the City." The bidders were not expressly advised
by the city, however, concerning the information that had become available to the city. In
the contract that was awarded to the low bidder, G. A. MacDonald Construction Co., Inc.,
the terms and conditions provided that the city would not be liable for any delay damages
other than for "unreasonable and unanticipated delays caused by the public
agency." This was an exception mandated by California Code, section 7102.
Work on the contractor's critical path was delayed for four months because after the
city issued the notice to proceed, the city was unable to obtain a disposal permit for the
excavated materials for another four months. When the contractor filed a delay claim, the
city asserted the "no-damage-delay" clause barred recovery. In deciding this
matter, the California Court of Appeal concluded that the contractor was entitled to
damages because the clause barring them was unenforceable pursuant to the exceptions
stated in the statute.
According to the court, the city withheld superior knowledge concerning the
contamination and site access. The inclusion in the addendum to the IFB to permit the city
the general right to "interchange" the construction stages was not sufficient to
give the bidders notice of the conditions or the impact that these conditions could have
on the schedule. Because the city had caused unreasonable, unanticipated delay, the damage
disclaimer was unenforceable. Howard Contracting, Inv. V. G.A. MacDonald Construction
Co., Inc. , 83 Cal. Rptr. 2d 590 (Cal. App. 2 Dist. 1999).
Article Copyright ã 1999,
ConstructionRisk.com, LLC - Virginia
_____________________
About This Newsletter
This newsletter is published monthly as an electronic magazine, or "e-zine."
It will be sent directly to email addresses of contractors, A/Es, attorneys, and risk
management and insurance professionals. Archived issues will be maintained on the World
Wide Web at ConstructionRisk.com.
Please visit us at our web site. This site has been created to help organize risk
management information and materials into one place for easy access and use.
If you do not want to receive this newsletter over the email, please send us a note at
Webmaster@ConstructionRisk.com stating that you want to be removed.
Disclaimer
This newsletter is distributed with the understanding that ConstructionRisk.com is not
engaged in the rendering of legal services. Further, the comments in this newsletter
are for general distribution and cannot apply to any single set of specific circumstances.
If you have a legal issue to which your believe this newsletter relates, we urge
you to consult your own legal counsel. Any content or opinions expressed by
the writers of this newsletter are set forth in their individual capacity and do not
necessarily reflect the opinion of any writer's employer and are not to be attributed to
any such employer.