|
ConstructionRisk.com ReportÔ
Vol. 1, No. 6 - September, 1999
In this issue:
______________________________
Inspection of subcontractor's Work Does Not Make Owner and Prime Contractor
Liable for Safety
Where a project owner had the contractual right to inspect the contractor's
work progress for the purpose of monitoring compliance with the plans and
specifications, a court held that this did not give the owner control over the
sight for the purpose of assuring safety.
The contract stated that the "City shall not supervise, direct, or have
control over, or be responsible for, Contractor's means, methods, techniques,
sequences or procedures of construction, or for the safety precautions and
programs incident thereto." An employee of a subcontractor was injured on
the job when a plank in a flying concrete form fell away from the concrete. That
individual sued both the prime contractor and the project owner, arguing that
their daily inspection of the work should have led them to detect and correct
the safety violations at the site.
According to the court, the inspection had been performed for the limited
purpose of determining compliance with plans and specifications and had nothing
to do with site safety. The work in question had been under supervision and
control of the subcontractor's project superintendent. As explained by the
court: "Liability attaches only when the owner or general contractor
retains control over the operative details of the hired work. In the absence of
direct management over the means and methods of the independent contractor's
work or the provision of the equipment which caused the injury, no legal duty is
created." Zamudio, v. City and County of San Francisco, 82 Cal. Rptr.
2d 664 (Cal. App. 1 Dist 1999).
________________________________
Miller Act Surety Requirements Amended
By: Edward G. Gallagher, Esq.
Since 1935, performance and payment bonds on federal construction projects
have been required by the Miller Act, 40 U.S.C. 270a, et. seq. Other than
increases in the contract value for which bonds are required, the Miller Act had
not been amended in any substantive aspect until August 17, 1999, when President
Clinton signed the Construction Industry Payment Protection Act of 1999.
The 1999 Act, which was the result of bargaining among many industry groups,
makes three changes to the current law. First, it raises the amount of the
payment bond to 100 % of the contract amount unless the contracting officer
finds that such a bond is unavailable. Prior law had a formula to set the
minimum amount of the payment bond at 4- - 5-% of the contract amount but with a
cap of $2.5 million. In actual practice, the government had not exercised its
authority to require more than this minimum, and for large projects $2.5 million
could be inadequate.
The Miller Act requires a claimant not in privity of contract with the prime
contractor furnishing the bond to give 90 days written notice by registered mail
to the prime that it is looking to the bond for payment. The courts consistently
held that any means that resulted in delivery was acceptable, and the registered
mail requirement came into play only if the contractor denied receipt of the
notice. With presumed knowledge of that interpretation of prior law, Congress
amended the statute to require a written, third party verification of receipt.
On could argue that the 1999 Act has changed the law, and regular mail will
no longer be sufficient even if receipt were admitted. On the other hand, the
clear intent of the amendment is to increase protection for subcontractors and
suppliers not to reduce it. When the issue reaches the courts, they will
probably hold that the current rule continues in force and any method of
delivery is sufficient if the contractor admits receipt.
The third change voids waivers of Miller Act rights unless made in writing
after the claimant commences work on the project. A waiver clause in a
subcontract is void unless the subcontract is signed after the subcontractor
started work.
An interesting question is whether this provision voids arbitration clauses
or provisions requiring that disputes be passed through to the government. That
was not the intent, and the legislative history explicitly states that
arbitration or other dispute resolution clauses are not voided. It also states,
however, that issues arising under the Miller Act (timeliness, notice, etc.) are
to be decided exclusively by the U.S. District Court. The claimant must sue the
surety on the bond within the one year limitations period, and the court will
then stay the suit pending resolution of the amount owed the subcontractor
through the arbitration. The surety's liability for that amount would still be
decided by the U.S. District Court.
About the Author: Edward G. Gallagher, is an attorney is the Virginia
office of the law firm of Wickwire Gavin, P.C.. His legal practice emphasizes
fidelity and surety law and construction contracts. He may be reached at 8750
Boone Blvd., Vienna, VA 22181; Phone (703) 790-8750 or by e-mail at egallagher@wickwire.com.
Copyright Ó 1999, Wickwire Gavin, P.C. Originally
published in the Fall 1999 issue of the firm's legal newsletter, "Legal
Foundations," and reprinted here at ConstructionRisk.com with permission.
_______________________________
Environmental Consultants Are Sued for Cleanup Costs
An owner of a property adjacent to gasoline station that was contaminated by
leaking underground storage tanks sued professional consultants who had
investigated and removed contamination from the tanks, arguing that they had
failed to prevent contamination from the site migrating onto their property. One
legal theory by the plaintiff was the consultants were strictly liable under the
New York Navigation Law, as discharges of petroleum. Although the state statute
provides for an immunity defense for those who have responded to discharges of
petroleum for purposes of corrective action, the defendants failed to raise the
immunity defense during their trial. The appellate court held that the case
should not be dismissed on a summary judgment motion because there were triable
issues of fact raised by the plaintiff concerning the consultants'
responsibility under the state law and the various common law theories. Hilltop
Nyac Corp. V. TRMI Holdings, Inc., Nos. 98-07500, 98-07503 (N.Y. Ap. Div.,
2d Dept. Aug 30, 1999).
________________________________
Recovery of Attorneys Fees: Indemnity Obligation
As a general rule, attorneys fees that one party expends in litigation cannot
be recovered from another party in the absence of an express contractual
provision requiring it. But is there a different result when a defendant in a
case is required to pay damages to a plaintiff and that defendant is entitled to
recover in indemnity from a third party? Can he recover legal costs from the
third party which he was required to pay to the plaintiffs pursuant to a trial
court judgment in favor of the plaintiff?
In the case of Toufic Nassif v. Sunrise Homes, Inc. Coast Quality
Construction Company, 739 So. 2d 183, 1999 LA LEXIS 1705 (1999), the court
held that where the third party was required to indemnify the defendant in the
trial court action, that party was also required to indemnify the defendant for
the attorneys fees that the trial court awarded to the plaintiff. This case in
interesting in that it explains the principles of indemnification quite well.
The court explained that indemnity "in its most basic sense means
reimbursement, and may lie when one party discharges a liability which another
rightfully should have assumed. It is based on the principle that everyone is
responsible for his own wrongdoing, and if another person has been compelled to
pay a judgment which ought to have been paid by the wrongdoer, then the loss
should be shifted to the party whose negligence or tortious act caused the
loss."
A party that is not actually at fault but whose liability results from the
faults of others, may recover by way of indemnity from such others. This is so
even if there is not contractual requirement to do so. The duty arises at common
law. It is an imposed liability that is variously called "technical,
constructive, vicarious and derivative." Such indemnity has been allowed a
contractor from his subcontractor and/or supplier, so long as the exclusive
fault producing liability has been that of such subcontractor and/or supplier.
The basic principle behind indemnity from the party that is a fault is that
"no one ought to enrich himself at the expense of another."
In considering whether attorneys fees should be treated differently from
other damages, the court considered a situation where the jury returns a verdict
in favor of the contractor against a subcontractor for the full amount that had
been awarded against the contractor to the plaintiff homeowner in the original
trial. In such a situation, the contractor would not be entitled to recover the
attorneys fees it incurred in pursuing the third-party claim against the
subcontractor in the absence of express contractual language permitting the
recovery of attorneys fees by the prevailing party. On the other hand, the court
stated that the contractor would be entitled to recover from the subcontractor
the attorneys fees that the plaintiffs recovered from the contractor in the
original trial court action, since the contractor had been compelled to pay
those attorneys fees as part of the plaintiffs' "damages."
An action for indemnity is, therefore, deemed by the court to be a separate
substantive cause of action, independent of the underlying wrong, and is,
therefore, distinct from an action for attorneys fees. "In light of the
foregoing concepts, we conclude that the equitable principle of restitution
applies in an action for indemnity to allow a defendant who is only technically
or constructively liable for a plaintiff's loss to recover from the party
actually at fault the attorneys fees it was compelled to pay the plaintiff, even
in the absence of a statute or contract of indemnification."
___________________________________
About This Newsletter
This newsletter is published monthly as an electronic magazine, or "e-zine."
It is sent directly to email addresses of contractors, A/Es, attorneys, and risk
management and insurance professionals. Archived issues are maintained on the
World Wide Web at www.ConstructionRisk.com. The formatting of this newsletter is
easier to read and to easier to print at the web site. Electronic newsletters
provide prompt information but cannot be formatted into a professional looking
layout.
Please visit us at our web site. This site has been created to help organize
risk management information and materials into one place for easy access and
use.
If you do not want to receive this newsletter over the email, please send us
a note at Webmaster@ConstructionRisk.com stating that you want to be removed.
Disclaimer
This newsletter is distributed with the understanding that
ConstructionRisk.com, LLC is not engaged in the rendering of legal services.
Further, the comments in this newsletter are for general distribution and cannot
apply to any single set of specific circumstances. If you have a
legal issue to which your believe this newsletter relates, we urge you to
consult your own legal counsel. Any content or opinions expressed by
the writers of this newsletter are set forth in their individual capacity and do
not necessarily reflect the opinion of any writer's employer and are not to be
attributed to any such employer.
Copyright ã 1999, ConstructionRIsk.com, LLC

|