|
ConstructionRisk.com Report Ô
Vol. 1, No. 8 - November, 1999
In this issue:
_____________________________
Design-Build: Does It Guarantee Project Success?
By: Michael C. Loulakis, Esq.
The rapid increase in the use of design-build around the country is a
testament to the benefits of this project delivery system. Single point
responsibility for design and construction gives the owner an opportunity to
receive early commitments for total project cost and speedier project delivery
-- while at the same time lowering the potential for disputes and change orders.
It also makes design-build the system of choice when the success of the project
is dependent upon output, throughput and other performance guarantees.
But is design-build the best choice for every project? The most frequently
published case studies discuss success stories -- projects where the parties
understood what design-build does and does not deliver. This has lulled some
owners into thinking that design-build is a cure-all for anything that can go
wrong on a project. The reality is that owners who misuse the design-build
process, or don't understand the limitations of it, are likely to be seriously
disappointed.
When you understand the issues that can create problems in a design-build
relationship, you can better determine if this is the best system for your
project. Whether you are an owner or someone who provides services to owners,
make sure that the key factors driving the project can be best accomplished
through design-build and the procurement and contracting methodology for the
project. You should also remember that project success will not be determined
solely by what project delivery system you use, but by how the overall project
is managed and administered. Consider these thoughts.
Project Drivers
The design and construction of each project are controlled by a combination
of unique factors and drivers. Some of these drivers are project specific --
such as those affecting price, schedule and quality. Others are dictated by the
personality of the owner and how it wants to manage the project. Project
delivery systems are intended to establish a framework to help the owner achieve
these drivers, with some systems being better than others at meeting specific
drivers.
Consider, for example, an owner who wants to use design-build to accomplish
three goals: (1) get a value engineered design; (2) eliminate any claims; and
(3) obtain the lowest price possible. All of these goals are well-suited to the
design-build process. Add to the equation the owner's expectation that it will
control the design -- by using detailed, restrictive specifications developed by
it's A/E before the design-builder became involved. Can design-build be used in
this scenario? Certainly. Will the owner's objectives by met? Hardly.
The owner's need for control seriously jeopardizes each of the project
drivers. An owner stifles the ingenuity and creativity of the design-builder's
team when it requires the team to use its design ideas. As a result, the ability
of a design-builder to achieve meaningful value engineering or cost savings is
seriously impeded. Finally, the owner will likely be held responsible for any
faulty design elements, eliminating the single point of responsibility benefit
of design-build.
Many other examples show how misaligned project drivers can result in an
unsuccessful design-build project. A number involve owners who select
design-build for early project completion, yet insist on actions that delay the
process (such as starting construction after all design is completed). In short,
if you are an owner who (a) distrusts your service providers, (b) cannot make
decisions to keep pace with tight schedules, and (c) micro-manages by committee,
you should choose another delivery system.
Relationship of Procurement & Contracting Methodology
The design-build process merely establishes the roles and relationships among
the key members of the project team. Owners sometimes forget that in order for
specific project goals to be achieved, the delivery system must be compatible
with the owner's contracting methodology (e.g., lump sum, cost plus with GMP)
and procurement process (e.g., direct selection, competitive best value). If any
of these three elements are out of alignment, the owner's expectations are not
likely to be met.
If speedy project delivery is the major driver for selecting design-build,
the owner should seriously consider using a procurement strategy based on
qualifications and competitive negotiations -- with price competition, if any,
limited to fee and general conditions expenses. Owners interested in selecting
the design-builder on the basis of a fixed low price usually spend significant
time in the procurement process, eroding much of the time savings obtained in
the merging of design and construction.
Matching an owner's high quality expectations with its procurement and
contracting preferences can also be problematic. When a design-builder is
selected primarily on price, it may have little incentive to spend its money or
time to consider life cycle costing issues or to give the owner quality that
exceeds what is being specified. If quality is a significant driver,
qualifications of the design-build team should be part of the selection process,
as well as proposed life cycle costing approaches. Likewise, if the owner wants
more control over what is being designed -- which is particularly important in
projects with rigorous architectural standards (such as courthouses and luxury
hotels) -- it should consider selecting the design-builder on qualifications,
with a GMP set after the design has evolved and the owner feels comfortable with
what it is ultimately buying.
Attributes of Successful Projects
Project success is not determined solely by the
choice of delivery systems. Professor Victor Sanvido recently conducted a study
on project delivery for the Construction Industry Institute. This study showed
that the best performing projects have the following attributes:
· Adequate to excellent ability of owner to make
decisions;
· Adequate to excellent scope definition,
· Excellent team communications
· Qualified contractor pool
· High ability to restrain the contractor pool
through prequalification and shortlisting
Likewise, the worst performing projects were characterized by:
· Contractors engaged late in the design process,
· Limited or no prior team experience,
· Onerous contract clauses,
· An owner lacking ability to make decisions,
· No prequalification of bidders
It is clear that if a design- build project has all of these
"worst-performing" features, it will probably be troubled.
What Should You Do?
If you are thinking about using design-build, what
should you do? A successful project owner will begin by carefully considering
whether its unique personality and goals can be addressed through design-build.
You may do this analytically -- by using a selection matrix process to compare
the attributes of available delivery systems to the project drivers and your
personality. If design-build scores well, then choose a procurement and
contracting plan that takes advantage of this system's strengths. Think through
what you realistically need to review, approve and control in the design and
construction. If your needs are too severe and restricting to the design-build
team, they may impact your long-term project goals.
Above all, don't delude yourself into believing that simply by calling your
project "design-build" you have a fail-safe mechanism for meeting all
your needs. You must carry the principles of design-build forward into your
procurement, contracting and management of the project.
About the Author: Michael C. Loulakis is a nationally respected
authority on design-build and an attorney in the firm of Wickwire Gavin, P.C. He
advises owners, contractors, design professionals, and sureties on construction
law issues. He may be contacted at Wickwire Gavin, P.C., 8100 Boone Blvd.,
Vienna, VA 22181; Phone (703) 790-8750 or by e-mail at mloulakis@wickwire.com.
Article copyright ã 1999, Wickwire, Gavin, P.C.
Originally published in the firm's Summer 1999 issue of "Legal
Foundations" newsletter. Reprinted by ConstructionRisk.com with permission.
_____________________________________________
The Catastrophe and Waiver of Subrogation
By: William T. Kacerovskis, Esq.
The project was proceeding well. Suddenly, one night the structure
inexplicably burns down. As usual, everyone says it was not their fault. Now
what?
If the construction contract contains a typical insurance clause, the owner's
property insurer pays the claim and the insurance proceeds can be used to fund
the cost of demolition and reconstruction.
(A) If the construction contract contains a waiver of subrogation clause,
then this is typically the end of the matter. The property insurer agreed to
insure against the risk and it must pay. Subrogation usually refers to the
situation where a property insurer who has paid the loss attempts to recoup its
loss from some party other than the owner (e.g. general contractor,
subcontractors' A/E's , etc.). Waiver of subrogation clauses typically prevents
the property insurer from pursuing such parties. Although the owner's property
insurer is ordinarily not mentioned in waiver of subrogation clauses, the
property insurer who pays a loss steps into the shoes of the owner. If the owner
has given up (i.e., waived) the right to pursue certain claims in the contracts,
the legal effect is that the property insurer is bound by that waiver.
A typical waiver of subrogation reads as follows: "The owner and
Contractor waive all rights against (1) each other and any of the
subcontractors, sub-subcontractors, agent and employees, each of the other,
[and] (2) the architect, architect's consultants, . . . for damage caused by
fire or other perils to the extent covered by property insurance obtained
pursuant to this contract.
(B) If the contracts do not contain express waiver of subrogation clauses,
then typically the property insurer will pursue claims (i.e., lawsuits) against
the contractor, subcontractors and/or the A/Es, contenting that their negligence
or other fault caused the fire or other catastrophe. Missouri law allows the
insurer to file suit in the name of the owner (a definite advantage if the case
is tried before a jury).
Limitations of Waiver of Subrogation Clauses
1. Typically, they apply "only to the extent
covered by property insurance" obtained pursuant to the contract. Thus, if
there is not coverage under the property insurance for any reason (exclusions,
etc.), the waiver of subrogation clause does not apply, and the owner is free to
pursue claims against anyone who allegedly caused or contributed to cause the
event.
2. If the amount of the loss exceeds the amount of the property insurance
limits of coverage, then the owner is free to pursue claims for all losses which
exceed the amount of property insurance.
Implied Waiver of Subrogation Claims
Some courts outside of Missouri have held that when
the contract requires the owner to purchase property insurance, there is an
implied waiver of subrogation claims, even where the contract contains no
express waiver of subrogation clauses. Although the Missouri Courts have
repeatedly upheld express waiver of subrogation clauses in construction cases,
they have not yet directly addressed the issue of implied waiver of subrogation
in any construction cases. Implied waiver of subrogation has been found in
Missouri in landlord-tenant cases.
Why Waiver of Subrogation Clauses Are Valuable, Even For Owners
They can prevent the great delay in the completion
of the project which otherwise often ensues. The liability insurers for the
general contractor, subcontractors and A/E's frequently deny that their insureds
are liable for the catastrophe. Litigation or arbitration is frequently needed
to determine whose fault, if anyone's, caused the accident. This takes time. In
the meantime, the structure is not completed and the owner cannot begin to reap
the economic benefits of the construction.
About the Author: William Kacerovskis is with the law firm of
Brown and James, 705 Olive Street, Suite 1100, St. Louis, MO 63101; Phone (314)
421-3400. Article copyright ã 1999, Brown and
James, first published in the firm's Summer 1999 issue of their "Fault
Line" newsletter. Reprinted by ConstructionRisk.com with permission.
_______________________________
NEW PROJECT DELIVERY SELECTION GUIDE
RESTON, VIRGINIA A/E/C Training Technologies, LLC
has just released an innovative training and reference guide on project
delivery entitled Construction Project Delivery Systems: Evaluating
the Owners Alternatives. The author of this guide is Michael C.
Loulakis, a member of DBIAs Board of Directors and Chairman of the
Manual of Practice Task Committee. Mr. Loulakis is a nationally
recognized authority on design-build and played a major role in drafting
DBIAs family of contract documents.
The guide is presented on an interactive CD, using a
creative combination of narration and on-screen text and graphics. The
program also contains interactive questioning throughout each section to
test the knowledge of the viewer. All major delivery systems, including
design-build and construction management, are discussed in a practical
and comprehensive manner. Among the specific topics addressed are:
The historical evolution of project delivery.
The role that procurement and contracting methods
play in project success.
Strengths and weaknesses of each delivery system.
Contracting concerns for each player within the
delivery system.
Research studies showing what can be expected in
using a particular system.
Owners will particularly appreciate the programs
in-depth guidance on how to objectively select the best delivery system
for a specific project.
The program (US$395) can be obtained from A/E/C
Training Technologies (703-356-6637) or directly from the Design-Build
Institute of America (202-682-0110). To view a sample of the program,
visit A/E/Cs website at "www.aectraining.com."
________________________________
About This Newsletter
This newsletter is published monthly as an electronic magazine, or
"e-zine." It is sent directly to email addresses of contractors, A/Es,
attorneys, and risk management and insurance professionals. Archived issues are
maintained on the Web at www.ConstructionRisk.com. The formatting of
this newsletter is easier to read and to easier to print at the web site.
Electronic newsletters provide prompt information but cannot be formatted into a
professional looking layout.
Please visit us at our web site. This site has been created to help organize
risk management information and materials into one place for easy access and
use.
If you do not want to receive this newsletter over the email, please send us
a note at Webmaster@ConstructionRisk.com stating that you want to be removed.
Disclaimer
This newsletter is distributed with the understanding that
ConstructionRisk.com, LLC is not engaged in the rendering of legal services.
Further, the comments in this newsletter are for general distribution and cannot
apply to any single set of specific circumstances. If you have a
legal issue to which your believe this newsletter relates, we urge you to
consult your own legal counsel. Any content or opinions expressed by
the writers of this newsletter are set forth in their individual capacity and do
not necessarily reflect the opinion of any writer's employer and are not to be
attributed to any such employer.
Copyright ã 1999, ConstructionRisk.com, LLC

|