|
ConstructionRisk.com Report Ô
Vol. 1, No.9 - December, 1999
In this issue:
· Delay Claims in
Construction Cases: Common Pitfalls
· Managing Conflicts of
Interest
________________________________
Delay Claims in Construction Cases: Common Pitfalls
By: Scott S. Aftuck, Esq.
Some of the most common disputes in construction cases relate to
delay. However, delay claims tend to be some of the least understood and
frequently confusing claims in the construction field. A clear
understanding of the basic elements necessary to prove delay claims is
invaluable in the processing of complex construction claims.
Much as it sounds, a delay claim on a construction project relates to
a period of time for which the project has been extended or word has not
been performed due to circumstances which were not anticipated when the
parties entered into the construction contract. The most common causes
of delay on a project include: differing site conditions; changes in
requirements or design; weather; unavailability of labor, material or
equipment; defective plans and specifications; and interference by the
owner. Such delays will often force a contractor to extend its schedule
to complete the work required under the contract, as well as to incur
additional costs in the performance of said work. Generally, these costs
may include: the costs of maintaining an idle work force and equipment;
unabsorbed office overhead; lost efficiencies; and general conditions.
However, in order to receive an extension of time for project
completion, or to recover additional costs, the contractor must meet a
number of prerequisites.
A delay must be excusable in order to be the basis for an extension
of time or additional compensation. Categories of excusable delay are
often determined in the contract and typically involve matters beyond
the control of the contractor. Examples of excusable delay include
design errors and omissions, owner initiated changes, unanticipated
weather, and acts of God. A non-excusable delay is a delay for which the
contractor has assumed the risk under the contract. Often, even if a
delay appears to be excusable, it will be the responsibility of the
contractor if it was foreseeable, but could have been prevented but for
the acts of the contractor. The same is true if the delay was caused by
the negligence of the contractor.
Delays may be further classified into compensable and non-compensable
delays. If a delay is compensable, the contractor is entitled to recover
compensation for the costs of the delay in addition to time extensions
to complete the project. Most contracts will include classes of delay
which are compensable. The general rule, however, is that if the delay
could have been avoided by due care of one of the parties, the party
which did not exercise such care is responsible for the additional
costs.
The contractor may also be liable for the negligent acts of its
subcontractors. If the negligent subcontractor is in the chain of
privity with the contractor, the contractor cannot recover delay damages
from the owner as those delays are the responsibility of the contractor.
However, if the subcontractor has a direct contractual relationship with
the owner of the project, the contractor may be able to recover damages
as it was not in a position to prevent the delay. Additionally, in order
to recover damages, a contractor must show a link between the delay and
the resultant damage. Simply stating that there was a delay is not
sufficient without showing a nexus between the delay and the damages.
Even if it is able to meet the foregoing criteria, a contractor will
not be entitled to recover if there is a concurrent delay affecting
completion of the project. A concurrent delay may be defined as a
second, independent delay occurring during the same time period as the
delay for which recovery is sought. If the party seeking increased
compensation is ultimately responsible for the concurrent delay, he may
not be able to recover any compensation for the initial delay.
Some courts, will allow the aggrieved party to attempt to apportion
the responsibility for delay, thus allowing compensation to the
contractor for the period of delay which was not its responsibility. See,
e.g., Raymond Constructors v. United States, 411 F.2d 1277 (Ct. Cl.
1969). However, apportionment of delay is often difficult due to
inadequate project documentation of the various delays. The best time in
which a contractor can apportion delay is while the project is ongoing.
Courts tend to find analyses made concurrent with the delays to be more
reliable then after the fact analyses.
A contractor can do a number of things to make it easier for it to
recover delay damages incurred on a project. The contractor should make
sure the construction contract clearly defines items which the
contractor will be able to recover. Additionally, each and every delay
should be well documented during the course of the project. Notice that
the delay is impacting the contractor should be given to the party with
which it is in privity. Finally, if there is any portion of delay for
which the contractor is responsible, it should seek to apportion the
overall delay between the items it is responsible for and those for
which it has no responsibility.
About the Author: Scott A. Aftuck is an attorney in the law
firm of Haese, LLC, 70 Franklin Street, 9th Floor, Boston, MA 02110;
Phone: (617) 428-0266. Copyright Ó 1999,
Haese, LLC. First published in the firm's Spring-Summer issue of their
Legal Notes: "Building on the Law." Reprinted here by
ConstructionRisk.com with permission. All rights reserved by Haese, LLC.
___________________________________
Managing Conflicts of Interest
By: Daniel J. Donohue, Esq.
A private company recently hired a consultant to get advice on
upgrading its technology and improving its customer service. The
consultant recommended that the company purchase additional systems to
improve customer satisfaction. The company was so pleased with the
consultant and its plan that it asked the consultant to a.) Submit a
competitive proposal to compete for a contract to add the systems it
recommended; and b.) Help the company evaluate the competing proposals,
including its own. Concerned about the obvious potential conflict of
interest, the consultant asks "Isnt that illegal?" This
months column explores the murky depths of such conflicts of interest
in order to provide an answer.
What is a conflict of interest? Conflicts of interest
arise in every type of business and we all deal with them every day. For
example, when you ask a restaurant owner to recommend something from the
menu, you know you are giving him a chance to push the slow-selling
highest-priced dish to benefit the restaurant at your expense. If the
owner does this, you probably will dine elsewhere in the future. Knowing
this, a smart owner will not steer you wrong. Of course, you can avoid
the conflict altogether by not asking for the owners advice. The
drawback is that you will miss the advice of the person who has the most
information about the restaurant.
Sometimes, people cannot even agree on the definition of a conflict
of interest. Most definitions focus on at least two ingredients: 1.) a
firms actual or potential financial interest in the outcome; and 2.)
the actual or potential effect on the ability of that person or firm to
render impartial advice. For example, those smartees at Harvard
University define conflicts of interest affecting procurement by the
University as follows: "[A]n individual is considered to have a
conflict of interest when the individual, or any of his Family or
Associates (i) has an existing or potential financial or other interest
which impairs or might appear to impair the individual's independence of
judgment in the discharge of responsibilities to the University, or (ii)
may receive a material, financial or other benefit from knowledge of
information confidential to the University." (On the World Wide Web
at
The Federal Government has a similar definition, but it also wants to
avoid giving one firm an undue competitive advantage over competing
firms. Federal Acquisition Regulation ("FAR") 9.501,
concerning conflicts affecting an organization, has the following
definition: "Organizational conflict of interest" means that
because of other activities or relationships with other persons, a
person is unable or potentially unable to render impartial assistance or
advice to the Government, or the person's objectivity in performing the
contract work is or might be otherwise impaired, or a person has an
unfair competitive advantage." (See
As these examples show, most of us recognize that a financial
interest in the outcome can affect the judgment of a person or firm, and
it is well to have a policy to deal with this type of situation.
Dealing with Conflicts of Interest.
Managing conflicts of interest requires integrity and trust in your
companys personnel and policy. While many types of policies are
possible, a good policy should at least include full disclosure and
efforts to neutralize the conflict.
The mere existence of a potential conflict of interest should not
automatically exclude a person or firm from participating in a
particular business opportunity. Competition and quality might be
impaired more by exclusion of a firm than by participation despite a
conflict of interest.
The goals of a conflict of interest policy should be to identify
potential conflicts of interest to senior management and to allow
management to be mindful of the issue in making its decisions. The
Harvard folks describe this situation this way: "If an individual
believes that he or she may have a conflict of interest, the individual
shall promptly and fully disclose the conflict to the Office of
the General Counsel and shall refrain from participating in any
way in the matter to which the conflict relates until the conflict
question has been resolved. In some cases, it may be determined that,
after full disclosure to those concerned, the University's interests are
best served by participation by the individual despite the
conflict." Similarly, the Federal Government requires the
Contracting Officer to identify actual and potential conflicts of
interest and to avoid, neutralize or mitigate the conflict. FAR
9.504(a). Mitigation efforts may include excluding a person or division
of a company from further involvement in a procurement, or waiving the
conflict where appropriate.
Thus, in our example, it was proper for the private company can allow
its consultant to bid on a contract for equipment it recommended. The
consultant did not get the work, though. It knew about more potential
problems than other competitors, and so its price was much too high!
About the Author: Daniel J. Donohue specializes in government
contracts and construction law. He is a shareholder in the Vienna,
Virginia office of Wickwire Gavin, P.C. (703) 790-8750. Copyright Ó
1999, ESI International. This article was first published in ESI
International's November issue of ESI Horizons. (For more information on
ESI see www.esi-intl.com)
__________________________________
About This Newsletter
This newsletter is published monthly as an electronic magazine, or
"e-zine." It is sent directly to email addresses of
contractors, A/Es, attorneys, and risk management and insurance
professionals. Archived issues are maintained on the World Wide Web at
www.ConstructionRisk.com. The formatting on the website is easier to
read and print. Electronic newsletters provide prompt information but,
unfortunately, cannot be formatted into a professional looking layout.
Please visit us at our web site and BOOKMARK US. This site has been
created to help organize risk management information and materials into
one place for easy access and use.
If you do not want to receive this newsletter over the email, please
send us a note at Webmaster@ConstructionRisk.com stating that you want
to be removed.
Disclaimer
This newsletter is distributed with the understanding that
ConstructionRisk.com, LLC is not engaged in the rendering of legal services.
Further, the comments in this newsletter are for general distribution and cannot
apply to any single set of specific circumstances. If you have a
legal issue to which your believe this newsletter relates, we urge you to
consult your own legal counsel. Any content or opinions expressed by
the writers of this newsletter are set forth in their individual capacity and do
not necessarily reflect the opinion of any writer's employer and are not to be
attributed to any such employer.
Copyright ã 1999, ConstructionRisk.com,
LLC

|