|
ConstructionRisk.com Report
Vol. 2, No.4 - April 2000
In This Issue:
- Contractor Not Bound By
Architects Decision on Claim
- Cost of replacing defective
work excluded under Builders Risk Policy
- Defective Workmanship
Potentially Covered By Insurance
- Statute of Repose for
Construction Projects Time-Bars Claim that could also be Asserted as
Products Liability with Longer Statute of Limitations Period
============================================
About this Newsletter
This newsletter is published by e-mail once per month. Archived
issues (plus this current issue) are maintained on our website at
http://www.constructionrisk.com . The formatting on the website is
easier to read and print. Electronic newsletters provide prompt
information but, unfortunately, cannot be formatted into a professional
looking layout. At our website you will find an extensive library of
risk management materials, including articles indexed by subject matter.
It is organized as a construction risk management portal to make it easy
for you to find all kinds of valuable information on the web. And its
completely free offered as a public service by a lawyer with 20
years of legal experience as a construction lawyer and risk management
professional. Take a second to visit us at Error! Bookmark not
defined.
============================================
Submit an Article or a Website link
If you have an article you have written which you would like us to
consider adding to our library of articles, please send as an e-mail
with the article attached.
============================================
Contractor Not Bound By Architects Decision on Claim
Contracts between owners and contractors often state that the
contractor must submit any claim to the architect for final
determination. Most contracts state that this must be done as a
condition precedent to further review by a dispute resolution board or a
court. But some contracts purport to eliminate any right of the
contractor to appeal the architects decision or to file suit against
the owner after receiving an unfavorable decision by the architect. As a
result of such contracts, some A/Es have found themselves defendants in
actions brought by contractors alleging that the dispute process was
unfair and unenforceable because the A/E was biased against the
contractor due to the A/Es responsibility and allegiance to the
owner. I have always thought it inappropriate for an owner to attempt to
cut off a contractors rights in this manner and have advised A/Es
against allowing themselves to be put into this position because it
seems almost guaranteed to lead to problems.
In the case of Blount Excavating, Inc. v. Denso Manufacturing,
No. 03A01-9903-CV-00112 m 1999 Tenn. App. LEXIS 779, a contractor
successfully sued to get out from under the requirements of a contract
clause designating the architects decision as "final and binding
on the parties." The contractors underlying change order claim
was that it had to remove 200,000 square yards more of earth than
specified in the contract, due to inaccurate information provided by the
owners architect. The architect rejected the change order. The
contractor submitted a claim to the architect as required by its
contract and when the claim was denied, the contractor filed suit
against the owner. The owner filed a motion for summary judgment, asking
the court to dismiss the suit because the contract made the architects
decision final and precluded any further action by the contractor. The
court rejected that motion and allowed the contractors suit to go
forward. The owner then filed an "Application to Confirm
Arbitration Award." It argued that the architects final decision
was equivalent to an arbitration award and was, therefore enforceable by
the court. The court disagreed and rejected the owners motion.
In analyzing why it did not consider the architects decision to be
an "arbitration award" that could be confirmed by the court,
the court explained that the contract did not anywhere describe the
architect as an arbitrator. Whereas arbitration requires three parties
(a claimant, a defendant and a neutral), only two parties were involved
in this dispute resolution because the architect was the owners
agent. Thus, there was only the contract and the owner through its
agent, the architect. The court also alluded to the fact that the
architect would not be qualified in any event to be an arbitrator since
the contractors claim for entitlement was based on alleged inaccurate
site information by the architect. A party with an adverse interest in
the matter cannot qualify as an arbitrator.
Risk Management Note: Owners who attempt to deprive the
contractor of its day in court (arbitration or mediation) are, in the
opinion of this author, ill-advised. This leads to adversarial
relationships that hinder communication and good will on the project.
Architects and Engineers who sign contracts agreeing to make final (non-appealable)
decisions for owners are also ill-advised for the same reasons. In the
case discussed, the contractor sued the owner, but A/Es are just as
likely to be a target when the contractors rights and remedies have
been unfairly cut off by an onerous contract.
============================================
Cost of replacing defective work excluded under Builders Risk
Policy
A construction contractor (Laquilia Construction, Inc.) poured
concrete that failed to meet the specifications for minimum strength for
the floor slab of a high rise commercial building. The defective
concrete had to be ripped out and replaced. This replacement required
reinforcing the building while the rework was performed. It also
required various subcontractors to remove and later re-install their
work, including HVAC ductwork, electrical fixtures and plumbing.
The question addressed by the court was whether the Builders Risk
insurance policy issued by Travelers Insurance was required to cover the
costs incurred in the re-work as insured damages. The policy stated that
it insured against the risk of "physical loss or damage to the
property insured, except as excluded hereunder." The exclusions
stated that the policy would not pay for:
"1. (a) Any loss of use or occupancy or consequential loss of
any nature howsover caused, including penalties for non-completion or
delay in completion of or delay in completion of contract or
non-compliance with contract conditions;
(b) Cost of making good faulty or defective workmanship or material,
but this exclusion shall not apply to physical damage resulting from
such faulty or defective workmanship or material."
The contractor submitted a claim to Travelers for the "costs of
repairing the fifth floor slab under an approved correction plan."
Included in these costs was the cost of removing and replacing the slab,
shoring the full height of the building while the corrective work was
performed, and the cost of the other trade contractors having to
removing and reinstall their work. Travelers denied coverage on the
basis that the claim was excluded because it was for the "cost of
making good faulty or defective workmanship or material."
In suing Travelers for coverage, the plaintiff asserted that the
exception to the exclusion at part (b) above was applicable because the
defective installation of the concrete physically damaged the insured
property by being incorporated into the building and could only be
removed at cost. In reading the exception to the exclusion, the court
stated that "the exception to any exclusion should not be read so
broadly that the rule the exclusion clause is swallowed by the
exception
."
The court found that the plaintiffs claim "falls squarely
into the exclusion clause simply as a cost incurred to make good the
defective concrete. If, however, the fifth floor slab had collapsed and
damaged machinery, plumbing and electrical fixtures, or neighboring
property, those losses would qualify as "ensuring losses" that
are covered under the policy. The defective materials, themselves, would
still not be covered. But where there was no collapse and no actual
physical damage, the court found that "Laquilas claim for
coverage here is no more than an attempt to recover for excluded costs
of making good its faulty or defective workmanship." Pressing home
its point, the judge concluded: "Were I to accept the plaintiffs
interpretation, it would result in coverage for nearly every instance of
defective workmanship . . . whether or not there was any actual ensuring
loss or if such loss stemmed directly from a risk expressly and
unquestionably excluded by the policy. Such coverage would wrongfully
insulate contractors from liability when their negligent or shoddy
workmanship results in structural or other failings." Laquila
Construction, Inc. v. Pinnacle Concrete Corp. v. Travelers Indemnity
Company of Illinois, 66 F. Supp. 2d 543 (D.C. Ill. 1999).
==========================================
Defective Workmanship Potentially Covered By Insurance
An insurance dispute arose when the commercial general liability (CGL)
insurance company refused to defend a suit by a prime contractor against
an inspection firm (SLT, Inc.) that it had hired to inspect and approve
shop welds of pipe sections that were brought to the construction site
for installation. Large pipe sections were purchased by the contractor
from a fabricator (Progressive Fabricators, Inc.) located in St. Louis
for use at a hydroelectric plant in California. SLT was to inspect the
welds before the pipe sections were shipped by the fabricator to
California.
SLT tendered defense of the suit to its CGL carrier, Liberty Mutual
which declined to defend on the basis that the losses alleged in the
complaint were not covered "property damage" and, in any event
were excluded under the policys "impaired property"
exclusion. SLT settled its case with Esicorp (the successor to the
original prime contractor) for over $2 million. As part of this
settlement agreement, SLT agreed to give Esicorp $125,000 in cash plus
transfer to Esicorp its rights to file a lawsuit against Liberty Mutual
alleging bad faith breach of its contractual duties to defend and
indemnify.
In the trial court, Esicorp obtained a judgment against Liberty
Mutual. On appeal the appellate court affirmed the judgment and agreed
that Liberty Mutual had breached its duty to defend SLT in the
underlying suit. The policy promised to indemnify SLT for non-excluded
"property damage" caused by an "occurrence." The
policy defined property damage as "physical injury to tangible
property, including all resulting loss of use of that property."
Esicorps complaint had alleged that as a result of SLTs failure to
discover defective welds in the pipes, the pipes were brought to the
project and installed. When it was discovered during installation that
the welds were defective, the owner suspended further work and required
Esicorp to re-examine all the shop welds and repair rejectable defects.
In reviewing the responsibilities of Liberty Mutual, the appellate
court explained that an insurance company has two distinct duties. The
first is to defend the insured in any lawsuit seeking damages that would
be covered losses. The second duty is to indemnify the insured for
covered losses. The duty to defend is broader than the duty to
indemnify. If the complaint against the insured alleges facts that give
rise to a claim potentially within the policys coverage, the insurer
has a duty to defend. In the Liberty Mutual policy, coverage was to be
provided for property damage that was defined as "physical injury
to tangible property, including all resulting loss of use of that
property." The court concluded that "it was reasonably
apparent to a liability insurer from these allegations that
"property damage" to the pipe system, and perhaps to
surrounding project property and equipment, would likely result from
this type of on-site repair operation. Thus, while "most of the
damages alleged in Esicorps complaint appeared to be economic losses,
not covered property damage" the complaint included allegations
giving rise to a claim "potentially within the policies
coverage." The duty to defend was thereby triggered.
The case goes on from here to describe in greater detail the extent
of the insurance company duty, including whether it can be held liable
for more than the policy limit, and how to ascertain liability when the
underlying damages arise out of some combination of covered and
non-covered claims. Esicorp, Inc. v. Liberty Mutual Insurance Company,
193 F.3d 966 (8th Cir, 1999).
Risk Management Note: It is interesting how the decision of this
case contrasts with that of the court in Laquila Construction, Inc.
v. Pinnacle Concrete Corp. v. Travelers Indemnity Company of Illinois, discussed
above. Here the court concluded that allegations of potential property
damage resulting from defective inspection services of SLT could
potentially be covered under the CGL policy. In contrast, the court in Esicorp
found no potential coverage under a policy where repairs were conducted
before the defective materials could fail and thereby cause damage to
other property.
What is not explained in the courts analysis is how there could be
any potential coverage under a CGL policy for what appears to be
allegations of negligence by a professional services provider.
Generally, errors and omissions insurance that is afforded by
professional liability policies would be more appropriate to cover
negligent acts, errors and omissions in the performance of professional
services. Even where there are professional liability endorsements in
CGL policies, those policies will not provide coverage for purely
economic damages there must first be actual property damage or
bodily injury.
===========================================
Statute of Repose for Construction Activities Time-Bars Claim that
could also be Asserted as Products Liability with Longer Statute of
Limitations Period
A plaintiff filed suit for negligence as well as products liability
against a firm that designed, manufactured and installed precast
concrete products for a parking garage. The court dismissed the suit
because it was filed beyond the six years permitted under the states
statue of repose applicable to services on construction projects. The
plaintiff argued that the statute of repose was inapplicable because the
damages arose not out of construction services but out of products
liability. The statute of limitations for filing products liability
claims had not yet expired when the suit was filed because it permitted
suit to be filed up to two years after discovery of the defects. It
provided no absolute deadline but rather a moving date that depended
upon the date a plaintiff discovered the defect.
The statute of repose bars "all actions against any architect,
contractor, builder or builder vendor, engineer, or inspector performing
or furnishing the design, planning, supervision, inspection,
construction . . . of any improvement to real property
[filed] six
years after the substantial completion of the improvement . . ." In
rejecting the plaintiffs assertion that the manufacturer was not one
of the named entities to be protected by the statute of repose, the
court focused on the nature of the activity performed. Instead of
looking only at the label placed on the party performing the work, the
court stated it was necessary to "look to whether that individuals
actions fall within the statutes protected class of activities."
Since in this case, the defendant engaged in "design" and
"construction" it was entitled to protection under the statute
of repose. Two Denver Highlands Ltd. Partnership v. Stanley
Structures, Inc. No.98CA2177, 2000 Colo. App. LEXIS 16 (Jan 20,
2000).
Risk Management Note: A key used by courts in deciding if an item
is a service or a product is whether it is an off-the-shelf item that is
made by a party that has little or no on-site activity. If the party
that creates the product also installs it, the court is more likely to
find this to be construction work. On the other hand, if a party simply
supplies a product that someone purchases, takes to the site and then
installs it, the courts are more likely to be found to be a product and,
therefore, no protection is afforded by the statute of repose for
construction activities. Interestingly, mere size and cost of the item
is not necessarily determinative. In some instances, for example, huge
water tanks have been considered to be products if they are manufactured
off-site and later bolted down to a concrete pad on- site, because they
are considered mobile and the on-site installation was a minor part of
the total cost. Also, the more site-specific design and customization of
the item there has been, the more likely that the court will find this
be to construction activity protected by the statute of repose.
=============================================
Disclaimer
This newsletter is distributed with the understanding that
ConstructionRisk.com, LLC is not engaged in the rendering of legal
services. Further, the comments in this newsletter are for general
distribution and cannot apply to any single set of specific
circumstances. If you have a legal issue to which you believe this
newsletter relates, we urge you to consult your own legal counsel. Any
content or opinions expressed by the writers of this newsletter are set
forth in their individual capacity and do not necessarily reflect the
opinion of any writer's employer and are not to be attributed to any
such employer. ConstructionRisk.com expressly disclaims any
responsibility for damages arising from the use, application, or
reliance upon the information contained herein.
Copyright 2000, ConstructionRisk.com, LLC

|