|
ConstructionRisk.com
Report
Vol. 2, No.6 - June 2000
In This Issue:
* No Compensation owed to contractor who
performed extra work without written authorization
* Additional Insured Endorsement Limited
* CGL Policy does not cover contractors
defective work
* Liquidated damage assessment against contractor
=====================================
About this Newsletter
This newsletter is edited by J. Kent Holland, Jr., Esq., and
published by e-mail once per month. Archived issues (plus this current
issue) are maintained on our website at http://www.constructionrisk.com.
The formatting on the website is easier to read and print. Electronic
newsletters provide prompt information but, unfortunately, cannot be
formatted into a professional looking layout. At our website you will
find an extensive library of risk management materials, including
articles indexed by subject matter. It is organized as a construction
risk management portal to make it easy for you to find all kinds of
valuable information on the web. And its completely free offered
as a public service by J. Kent Holland, Jr., an attorney with 20 years
of legal experience as a construction lawyer and risk management
professional.
=====================================
Submit an Article or a Website link
If you have an article you have written which you would like us to
consider adding to our library of articles, or including in the
ConstructionRisk.com Report, please send us an e-mail with the article
attached.
=====================================
NO COMPENSATION OWED TO CONTRACTOR WHO PERFORMED
ADDITIONAL WORK WITHOUT WRITTEN AUTHORIZATION
It is surprising how many cases there are in which a consultant or
contractor performs additional services or work for an owner without
first adhering to notice and approval requirements of the contract.
Failure to obtain authorization for additional work from the owners
designated representative can, and often does, bar entitlement to be
paid for the extra work.
In the case of F. Garofalo Electric Co., Inc. v. New York
University, et al., 705 N.Y.S. 2d 327 (March 14, 2000), the
electrical contractor, Garofalo, alleged that it performed additional
work and furnished additional materials in reliance upon oral
representations by NYU and its construction manager, MDI, to pay for
such extra work. Plaintiffs complaint alleged breach of contract by
both NYU and MDI. It also alleged that MDI was negligent. The defendants
asked the court to grant motions of summary judgment against the
complaint. The appellate court agreed that the plaintiff could not
maintain a claim for negligence against MDI because New York did not
recognize a cause of action for economic loss caused by allegedly
negligent performance of contractual duties. Moreover, the court held
that the plaintiff was not a third party beneficiary of the contract
between NYU and MDI, and therefore had no rights under that contract to
sue MDI.
NYU argued that it was entitled to summary judgement because
plaintiff had failed to provide the contractually required
contemporaneous written notice and documentation of its claims for extra
work, and that they were therefore barred. In opposition to the motion,
plaintiff didnt argue that it complied with the contracts notice
requirements or obtained a signed contract modification. Instead, it
argued that NYU, through MDI, its agent, had abandoned, waived or
modified the requirements. Its basis for this argument was its assertion
that MDIs project manager orally instructed plaintiff to perform the
extra work and keep track of hours and materials, and said, "it
would be taken care of at the end of the job." "Further,
plaintiff pointed to the deposition testimony of MDIs vice president,
wherein he stated that MDI basically instructed plaintiff to proceed
with the work without the paperwork required by the contract. Lastly,
plaintiff maintained that its foreman and sub-foreman prepared Foremans
Daily Reports and submitted them to MDI on a daily or weekly basis and
that these reports were sufficient to meet the contract
requirements."
In rejecting all of these arguments by the plaintiff, the court
explained: "The contracts notice and documentation requirements
for extra work and delay damages are condition precedents to plaintiffs
recovery and the failure to strictly comply is deemed a waiver of such
claims. Plaintiff conceded . . . it did not strictly comply with the
contracts mandates. Therefore, plaintiff clearly waived its
claims." Even if MDI had, as alleged by the plaintiff, orally
instructed plaintiff to perform the extra work and modified the
contractual requirements, the court said this would not relieve the
contractor from meeting the requirements. According to the court,
"The record reveals that MDIs authority was clearly and
unambiguously limited by the express terms of both the contract and the
construction managers agreement and, as such, it lacked authority to
waive or modify the notice or documentation requirements in plaintiffs
contract."
__________________________________
Risk management Note: It is vitally important that parties to
contracts understand the principles explained in this case. When the
contract states it can only be modified in writing, it means what it
says. Courts enforce these provisions even in situations where the
results might appear to be "unfair" and the owner might appear
to receive a windfall by not having to pay for work. Although this case
dealt with a construction subcontractor, the same principles and law
apply equally to consulting contracts. If a consultant is asked by an
owner to perform services that it deems are "additional
services" beyond the scope of the "basic services" for
which it was to compensated, it must adhere to the requirements of the
contract to provide the owner with written notice that the services are
"additional." It will also have to meet any contractual
requirements mandating that the notice be given to a specified
representative of the owner for approval. Finally, it will have to
adhere to contractual requirements concerning the documentation of costs
associated with the additional services.
When consultants and contractors run afoul of the contract
requirements, it is sometimes because the individuals running the job
are not adequately familiar with the contract terms. In other instances
it is because the parties have developed a comfortable relationship that
has led to informality and apparent waiver of contract requirements. As
explained by this court, however, the requirements are not actually
waived in the absence of a written modification to the contract. From my
experience, I dont think that project owners intentionally lull
consultants and contractors into performing services with the intent not
to pay for them. But what sometimes happens is that when the contractor
or consultant submit claims to the owner at the end of the project, the
owner retains counsel who determines that the parties did not adhere to
the notice and documentation requirements. In fulfilling their zealous
representation to the owner, they advise the owner that because these
requirements were not met, the claimants have legally waived their
right to be paid for the additional work. There are even reported court
cases in which the owner counter-claimed against the plaintiff and
recovered progress payments it had made on work that had been performed
with its knowledge but without written authorization of the designated
owners representative. When it comes to construction contracts, the
devils in the details.
=====================================
ADDITIONAL INSURED ENDORSEMENT LIMITED COVERAGE
Contractors are often required by contract to name the project owner
as an "additional insured" under a commercial general
liability (CGL) policy and this is routinely done. Subcontractors are
sometimes required to name both the general contractor and project owner
as additional insureds under their CGL policy. Design professionals, on
the other hand, rarely are able to provide additional insured status to
the owner under the professional liability policy. For a good
explanation of this distinction, see the Zurich Insurance
Architectural/Engineering Briefings at Vol.2, No.1 (February 1997),
http://www.zurichamerican.com/za/news/nwslttrs/archeng/2-97.htm
An additional insured endorsement can provide broad coverage to the
additional insured or it can carefully limit the coverage to only those
damages that arise from the named insureds acts and omissions. In American
Country Ins. Co. v. Cline, No. 1-98-2021, 1999 Ill. App. LEXIS
853, the court held that an additional insured endorsement effectively
limited the coverage to only those damages arising out of the insured
subcontractors own conduct and did not extend coverage to the owner
or general contractor for damages arising out of their own conduct. The
endorsement provided the following:
"The coverage afforded to the Additional
Insured is solely limited to liability specifically resulting from
the conduct of the Named Insured which may be imputed to the
Additional Insured. This endorsement provides no coverage to the
Additional Insured for liability arising out of the claimed
negligence of the Additional Insured, other than which may be
imputed to the Additional Insured by virtue of the conduct of the
Named Insured."
An employee of the electrical subcontract sued the project owner and
general contractor for their active negligence in causing an electrical
conduit pipe to fall on his ladder, resulting in his fall to the floor.
Both the owner and contractor gave the claim to the subcontractors
insurance company, American Country Insurance Company
("American"). American refused to defend the case since the
employee alleged active negligence of the owner and contractor, and the
endorsement limited coverage only to liability caused by the insured and
imputed to the additional insureds. The issue to be decided by the
appellate court was whether American correctly interpreted and applied
the language of the endorsement.
The court found that the coverage was not illusory and meaningless
even though the language of the endorsement strictly limited what would
be covered. This is because it would cover claims from the vicarious
liability of the owner and contractor arising out of actions of the
subcontractor. The narrow coverage seemed appropriate to the court,
particularly in view of the small price of $150.00 paid for the
endorsement. In addition, "this limitation on coverage recognizes
that businesses in the construction industry carry coverage for
liability arising out of their own work, and assumes that [Contractor]
would have its own general liability coverage. If an additional insured
seeks the same level of coverage that it already receives from its own
insurer, then insurers like plaintiff should receive a larger premium
payment." The court concluded that the terms of the endorsement
reflect the fact that the insurance company was only willing to provide
coverage of its own insureds actions.
Another issued determined by the court was whether the endorsement
violated public policy. Since the insurance company had filed the
endorsement with the state insurance commissioner of Illinois and it had
not been rejected by the Insurance Department, this was one indication
that the endorsement was not contrary to public policy. In addition to
this, the court found that the parties were sophisticated commercial
entities that negotiated their insurance policy and endorsement. This
bound the owner and contractor to their decision accepting the
endorsement.
Since the endorsement was enforceable as written, the court found
that the insurance company had no duty to defend the contractor and
owner in the suit by the subcontractors employee. That employees
suit alleged negligence only on the part of the contractor and owner,
and not the insured subcontractor. Thus there was no negligence of the
named insured imputed to the others. The claim, consequently, was not
covered by the endorsement.
=====================================
CGL POLICY DOES NOT COVER CONTRACTORS DEFECTIVE
WORK
To what extent may defective workmanship of a contractor be covered
under a commercial general liability (CGL) policy. Contractors have
occasionally argued successfully that property damage or personal injury
was imminent as a result of their defective work, and that the repair to
the work must be deemed to be insured damage. More often that not, these
kinds of claims are denied.
In Erie Insurance Property & Casualty Co. v. Pioneer Home
Improvement, Inc., No. 11278000 (W.Va. Dec 10, 1999), the
Supreme Court of West Virginia reviewed the question of whether
defective workmanship could be a covered loss under the policy. A
homeowner sued the insured general contractor for defective performance.
The general contractor tendered the claim to its insurance company to
defend. The insurer declined coverage on the basis there had been no
"occurrence" causing property damage. Second, it argued that
an exclusion to the policy negated any potential coverage. The policy
expressly excluded coverage for "that particular part of the any
property that must be restored, repaired or replaced because your work
was faulty."
In evaluating the language of the policy, the court explained that a
CGL policy does not insure against "damages in an action for breach
of contract and faulty workmanship on a project where the damages are
the cost of correcting the work itself." Instead, the policy is to
cover liability arising out of personal injury or property damage to
others caused by the insureds conduct. This is how the court
explained it:
"Pioneer [the contractor] purchased a CGL policy. These policies
do not insure the work or workmanship which the contractor or builder
performs. They are not performance bonds or builders risks policies.
CGL policies, instead, insure personal injury or property damage arising
out of the work. The completed operations hazard coverage applies
to collateral property damage or personal injury caused by an occurrence
arising out of your work that has been completed or abandoned."
=====================================
LIQUIDATED DAMAGE ASSESSMENT AGAINST CONTRACTOR
UPHELD
When the amount of damages is difficult to predict, a liquidated
damages clause will generally be upheld unless the court determines that
the clause was intended to be a penalty rather than liquidated damages.
In Safeco Credit v. U.S., 44 Fed.Cl. 406 (1999), a
contractor was assessed damages by the Department of Navy for late
completion of a contract. The contractor argued that the delays were
caused by 53 contract modifications by the Navy. The Navy granted time
extension change orders for the specific phase of the project that was
affected by each change order. It did not, however, specifically agree
to extend the start date or date of completion of any other phase of the
project that might arguably be affected by the delayed completion of the
first phases.
Contractor argued that if the Navy extended the time for completing
one phase, it must be assumed that the time for starting and completing
the next phase would likewise be granted a time extension. Moreover, the
contractor argued that the dollar amount of the liquidated damages was
punitive rather than reasonable, and did not follow the rules and
procedures of the Navys contract manual. In reviewing whether the
Navy had properly assessed liquidated damages and denied the contractors
claim for equitable adjustment for delay to the overall project, the
court stated that the contractor has the burden to establish that the
liquidated damages clause was intended to operate as a penalty. To prove
that, it is necessary to ask three things:
(1) Did the parties intend liquidated damages or a penalty?
The terms of the contract are the best evidence of the partys
intent.
(2) Was the amount of damages that would be caused by a breach
uncertain in amount or difficult to determine?
The more difficulty there would be in proving that a loss has
occurred or the amount of the loss in the event that it occurs, the
easier it is to show that the amount fixed as liquidated damages is
reasonable. The court evaluates this question based on the reasonable
expectations of the parties as of the date the contract was executed.
(3) Does the amount of damages bear a reasonable relationship to
actual damages that could be sustained in the event of a breach?
The amount is reasonable if it approximates the loss anticipated at
the time the contract is executed, even though it may not approximate
the actual loss.
In this case, the court found that the contractor failed to prove
that the liquidated damages clause operated as a penalty. The amounts
were based on the Navy Contract Manual, but to the extent that they
differed, the Navy had followed required Navy procedures to justify the
higher amounts set. On the issue of whether the project completion date
should have been extended due to the extensions on the individual
phases, the court found that the change orders were self contained and
that "the terms of the contract modifications at issue here make it
clear that a change in the completion date for one phase of the contract
does not lengthen the period of time in which a subsequent phase was to
be completed, unless expressly provided." No provision was made for
any cumulative impact. For these reasons, the court granted the Navys
motion for summary judgment against the contractor.
=====================================
DISCLAIMER
This newsletter is distributed with the understanding that
ConstructionRisk.com, LLC is not engaged in the rendering of legal
services. Further, the comments in this newsletter are for general
distribution and cannot apply to any single set of specific
circumstances. If you have a legal issue to which you believe this
newsletter relates, we urge you to consult your own legal counsel. Any
content or opinions expressed by the writers of this newsletter are set
forth in their individual capacity and do not necessarily reflect the
opinion of any writer's employer and are not to be attributed to any
such employer. ConstructionRisk.com expressly disclaims any
responsibility for damages arising from the use, application, or
reliance upon the information contained herein.
Copyright 2000, ConstructionRisk.com, LLC
Editor: J. Kent Holland, Jr. 703-827-4114

|