|
______________________________________
ConstructionRisk.com Report with Kent Holland
http://www.ConstructionRisk.com
Vol. 5, No. 4, May 03
______________________________________
========================================
Inside
This Issue:
*
Boilerplate Can Burn!
*
Accord and Satisfaction
Language on Endorsed Check Barred Contract Claim
*
Differing Site Conditions, Defective Specifications: One Coin,
Two Sides
======================================
ConstructionRisk.com
BOOK:
“Construction Law & Risk Management: Case Notes and Articles”
Now
in one well-indexed book, with 27 chapters, you can read the case
notes and articles that have been published in the ConstructionRisk.com
Report between 1999 and 2002.
It is
priced at about 1/3 of the cost of comparable books and newsletters This
book compiles and organizes case notes, articles and papers written by
well known and respected attorneys and professional consultants for
original publication in a number of newsletters published by a variety
of organizations including law firms, claim consultants, financial
services providers, accountants, design professionals and contractors.
The cases and articles that are included in this book were
selected based on their value for demonstrating risk management
principles to be considered and applied.
The intent is to give a sampling of issues and cases, providing
risk management ideas and information to serve as a useful resource for
the reader. 310 Pages. Chapters
include:
1.0
Americans with Disabilities Act
2.0
Conflicts of Interest
3.0
Contract Language – Terms and Conditions
4.0
Contractor Suits against Design Professionals
5.0
Copyright Ownership
6.0
Cost Issues
7.0
Damages
8.0
Design-Build
9.0
Differing Site Conditions & Other Changes
10.0
Dispute Resolution
11.0
Documentation
12.0
Economic Loss Doctrine – Bars Suit in absence of Contract
13.0 Environmental
14.0 Expert Witness
Evidence Required
15.0 Indemnification
16.0 Insurance
17.0 Limitation of
Liability
18.0 Scheduling
19.0 Site Safety Risk and Responsibility
20.0 Statute of
Limitations
21.0 Statute of Repose
22.0 Subrogation Waivers
23.0 Substantial
Completion
24.0 Surety
25.0 Suspension and
Debarment
26.0 Termination of
Contract
27.0
Warranties
For
More Information, go to this link: http://www.constructionrisk.com/constructionlawbook/index.htm
=======================================
___________
ARTICLE
# 1
___________
Boilerplate
Can Burn!
By:
Lawrence
Moss, Esq.
There are no “industry standard” construction form documents.
But the forms issued by the American Institute of Architects
(AIA) come close, being widely used.
One key provision to be considered is the issue of consequential
damages.
“Consequential damages” are damages, losses or injuries which do
not flow directly and immediately from the wrongful act of a party, but
rather from some consequence of that act, such as lost profits or damage
to reputation.
Some years ago, in the case of Perini Corp. v. Great Bay Hotel,
a
New Jersey
appellate court upheld a fourteen million dollar consequential damages
award against a general contractor for the owner’s lost profits
resulting from late completion – where the general contractor’s
total compensation was only $600,000!
In response to this and similar cases across the country, the AIA, at
the urging of contractors, included the mutual waiver of consequential
damage in the 1997 forms (see Paragraph 4.3.10) of the General
Conditions to the Contract for Construction, AIA Document A201 (1997);
there are analogous provisions in the current Owner/Architect agreement
forms.). By eliminating
consequential damages, the AIA intended that contractors and architects
be protected against damages awards which are grossly disproportionate
to the compensation received for their services.
Although the waiver is mutual, owners, contractors and architects
need to consider the potential impact of this provision.
For example, consider the development of a luxury condominium
project. The owner/developer
probably won’t see a dime of net income until the project is completed
and it starts unit closings. During
construction, however, the owner is incurring costs: interest and
financing fees; taxes, insurance and other carrying costs;
administrative costs, overhead and salary of sales and development
personnel. The owner’s
hope of making money is premised, in part, upon construction being
completed in time to get units closes and costs paid or eliminated
before those costs eat away any chance of profit – or worse.
If the contractor fails to complete by the promised completion date,
the owner will pay interest and carrying costs longer than planned.
Equity investors, who have a preferential return on capital, will
earn more money, leaving less bottom line for the developer.
Buyers might be able to terminate their contracts because of a
missed delivery date. Contractors
can be delayed, too. Drawings
may be incomplete and may need to be revised, resulting in extra delay
and expense.
To the extent that these damages are considered “consequential”
damages, and a party signed an unmodified AIA contract, that party
won’t recover a penny.
An alternative to deleting the waiver is to reconsider liquidated
damages. Liquidated damages
are amounts recoverable in a fixed amount upon occurrence of a defined
event. If liquidated damages clauses are drafted properly so as
not to be punitive, than after appropriate economic analysis, they are
usually enforceable by the courts.
Liquidated damages have been generally anathema to contractors.
Since the adoption by the AIA of the mutual waiver language,
however, more contractors are willing to negotiate a serious and
meaningful liquidated damage remedy -- especially if the alternative is
the deletion of the waiver of consequential damages clause, and the
possibility of uncapped liability for the contractor.
The moral of the story: If you are presented with an unmodified AIA
contract for signature, think twice, because the consequences of signing
an unmodified AIA contract could be significant.
ABOUT THE AUTHOR: Lawrence
Moss is an attorney with the law firm of D’Ancona & Pflaum LLC,
111 E. Wacker Drive, Suite 2800
,
Chicago
,
IL
60601
; Tel: (312) 602-2000. The
firm’s web site is: http://www.dancona.com.
=======================================
HILL INTERNATIONAL - Founded
in 1976, Hill is a worldwide construction consulting firm which provides
innovative approaches to both avoidance and resolution of construction
disputes. It also offers clients a full spectrum of project management
services, including a unique form of objective project management
oversight designed to better assure that capital projects are completed
on schedule and within budget. Hill is ranked in the top 15 largest
Construction Management Firms by ENR magazine. Visit http://www.hillintl.com
========================================
Montana
Dry Log and Lumber can
provide, sawmill direct wholesale truckload dimensional lumber(2x4, 2x6,
etc), commercial decking, 1x6
Aspen
panelings, large structural
appearance grade beams, and much more.
Call mark workman at 877-389-7748 or visit us at www.montanalogsandlumber.com.
for e-mail:
logcabin@3rivers.net
=======================================
____________
ARTICLE # 2
____________
Accord
and Satisfaction Language Barred Contract Claim
By: J. Kent
Holland, Jr., Esq.
Where a statement was conspicuously contained in a
letter transmitting a check for final payment to a contractor stating
that the check will constitute full satisfaction of a contractor claim,
a court held this to be an accord and satisfaction, barring the
contractor from claiming additional monies under its contract.
In Gelles & Sons General Contracting, Inc. v. Jeffrey
Stack, Inc. (No. 012319, Fairfax County, VA 2002),
the contractor (“Gelles”) had performed brick laying work,
and the its customer (“JSI”) took
issue with the amount and quality of the work and disputed the amount of
compensation due. The final
paragraph of its letter transmitting the check in question stated,
“JSI Paving and Construction stands by its final amounts as stated on
the latest correspondence.... Enclosed, please find a check ....
representing final payment of the contract.” Gelles cashed the check.
Then Gelles sued JSI for the balance that it deemed owed.
In response, JSI asked the court for summary judgment on the
basis of accord and satisfaction. The
court granted the summary judgment for several reasons.
Under the Virginia Code, section 8.3A-311, if a
person tenders a payment instrument to a claimant as full satisfaction
of the claim which was unliquidated or subject to a dispute, and the
claimant obtained payment of the instrument [i.e., cashed the check],
the following conditions apply. “b)
... the claim is discharged if the person against whom the claim is
asserted proves that the instrument or an accompanying written
communication contained a conspicuous statement to the effect that the
instrument was tendered as full satisfaction of the claim.”
“Conspicuous,” as defined in the Code, means a
term or clause that a reasonable person “ought to have noticed.”
There is no statutory requirement that the term or clause must be
displayed in a particular font or size type.
Gelles argued that the language was ambiguous and would not lead
a reasonable person to conclude that full satisfaction of the claim was
intended. The trail court
found that a reasonable person could not have considered the language of
the letters to be anything other than “a drop-dead letter that says,
‘This is it. This is what
we’re going to pay you.’” The
appellate agreed that “the entire course of conduct and communication
between these parties made clear that JSI offered the [amount] as the
final payment that it intended to make and that JSI considered that
amount to represent the proper accounting under the contract.”
Risk Management NOTE:
I have had the experience while litigating a contractor claim to
have a project owner successfully persuade a judge that through a
combination of a change order, payment authorization, and partial waiver
and lien release, the contractor had agreed to a total accord and
satisfaction of any and all claims related to any work related to the
change order. This
came as a surprise to the contractor who never intended by signing the
documents and cashing the check to waive its entitlement to the amount
that it alleged to remain contested.
Despite correspondence and documentation submitted to the owner
by the contractor prior to the “accord and satisfaction,”demanding
payment and seeking to preserve its rights, a court held that the
subsequent contractor claim for the outstanding balance could be barred.
The lesson learned is that language asserting a release and
satisfaction must be taken most seriously, and, to assure that any right
to a claim for additional monies is preserved, appropriate communication
and action must be taken
ABOUT THE AUTHOR:
Mr. Holland is a construction lawyer with the law firm of
Wickwire Gavin, P.C. in Vienna, Virginia and is the director of risk
management services for the environmental and design professional
liability unit at Arch Insurance Company in New York, NY.
He may be reached at Kent@kentholland.com
or 703-623-1932.
____________
ARTICLE # 3
____________
Differing
Site Conditions, Defective Specifications: One Coin, Two Sides
By: Stephen J.
Densmore, Esq.
Unforeseen site conditions typically spawn two types of claims
based on two distinct but related theories: differing site conditions
(DSC) and defective specifications.
A contractor may attempt to circumvent the limitations on
recovery under a DSC provision by characterizing its claim as one for
breach of contract due to defective specifications.
In Comptrol Inc v.
United States
(Fed Cir. 2002) 294 F.3d 1357, a federal court recognized the close
relationship between these two theories and blocked the contractor’s
attempt to do an end-run around the recovery limits in the owner’s DSC
provision.
In Comptrol, the contractor claimed that
during bidding, the government withheld material information concerning
the presence of quicksand and the location of a subsurface pipeline.
Apparently unhappy with the recovery allowed by the DSC
provision, the contractor tried to argue that its claim should be
permitted as a claim for damages for breach of contract arising from
defective specifications. The
court rejected this argument and held that although DSC claims and
defective specifications claims are distinct in theory, “where the
alleged defect in the specification is the failure to disclose the
alleged differing site condition,” the two claims are “so
intertwined as to constitute a single claim” that is governed by the
DSC provision.”
Contract Drafting NOTE:
DSC provisions typically contain a number of clauses relating to
such things as notice, cost recovery, and continuous work that are
valuable protections for the owner.
In order to preserve these protections, an owner should try to
draft the DSC provision with language that limits the contractor’s
ability to circumvent the DSC provision by characterizing its claim as
one for “defective specifications.”
ABOUT THE AUTHOR:
Steve Densmore is an attorney with the law firm of Kane, Ballmer
and Berkman, 515 South Figueroa Street, Suite 1850, Los Angeles, CA
90071; Tel: (213) 617-0480. Email: sdensmore@kbblaw.com.
Website: http://www.kbblaw.com.
=====================================
ARCH INSURANCE GROUP
For information on design professional liability
and environmental liability insurance available from ARCH, contact
Richard Zarandona at 973-206-8025 (senior vice president), rzarandona@archinsurance.com;
Victoria Szot, P.E., J.D. (professional liability underwriter), at
973-206-8026, vszot@archinsurance.com;
Jim Boyes (environmental liability underwriter) at
973-206-8027, jboyes@archinsurance.com;
or Kent Holland (risk management) at 703-623-1932, kholland@archinsurance.com.
Underwriting is done out of the Arch Insurance Group office at
55 Madison Ave.
,
Morristown
,
NJ
,
07960
.
=====================================
ON-LINE RISK
MANAGEMENT COURSES BY KENT HOLLAND
Currently available risk management courses written by Kent Holland for
RedVector, (http://www.redvector.com/instructors/view_related_courses.asp?id=195)
include the following: Risk Management for the Design Professional;
Contract Guide for the Design Professional; Design Build Professional
Liability Risk Management and Insurance; Site Safety Risk and Liability;
Managing Communication, Documentation and Reports; Insurance for
Design-Build and Complex Projects; Construction Contract Law; Contract
Claims against Design Professionals; Insurance Coverage Disputes; and
Environmental Claims.
=====================================
ABOUT THIS NEWSLETTER & A DISCLAIMER
This newsletter Report is published and edited by J. Kent Holland, Jr.,
Esq., Director of Risk Management Services for the Environmental and Design Professional Liability Units of
Arch Insurance Group. The Report is independent of any insurance company, law firm, or other entity, and is distributed with the understanding that ConstructionRisk.com, LLC, and the editor and writers, are not hereby engaged in rendering legal services or the practice of law. Further, the content and comments in this newsletter are provided for educational purposes and for general distribution, and cannot apply to any single set of specific circumstances. If you have a legal issue to which you believe this newsletter relates, we urge you to consult your own legal counsel. ConstructionRisk.com, LLC, and its writers and editors, expressly disclaim any responsibility for damages arising from the use, application, or reliance upon the information contained herein.
=====================================
Copyright 2003, ConstructionRisk.com, LLC
Publisher & Editor: J. Kent Holland, Jr., Esq.
6505 Chesterfield Ave.
McLean, VA 22101
703-623-1932
Kent@ConstructionRisk.com
|