|
ConstructionRisk.com Report
http://www.ConstructionRisk.com
Vol. 7, No. 2, April 05
______________
Inside
This Issue:
• Contractors
May Now Bring Direct Action for Economic Losses Against Design
Professionals in
Pennsylvania
• Why Some Mediations Fail
• Pollution Exclusion
in D&O Policy Applied to
Exclude
Coverage for Alleged Business Torts
• Project Manager
Required by Fiduciary Duty to Owner to agree to Settlement with a
Supplier Contrary to its Own Interest.
======================================
Article # 1
Contractors
May Now Bring Direct Action for Economic Losses Against Design
Professionals in
Pennsylvania
By:
Andrew B. Cohn, Esq.
A very
recent Pennsylvania Supreme Court opinion (January 2005) has
significantly changed
Pennsylvania
law, allowing a general contractor to directly sue an architect in
negligence for additional construction costs caused by defective plans,
drawings, and specifications. Based
on this decision, contractors working on
Pennsylvania
projects may now bring direct actions against design professionals to
recover purely economic losses caused by errors and omissions in their
design documents.
In Bilt-Rite
Contractors, Inc. v. The Architectural Studio, a general contractor
on a public school project claimed that it incurred substantial
additional construction costs because the aluminum curtain wall, sloped
glazing, and metal support systems could not be installed and
constructed through the use of normal and reasonable construction means
and methods. The contractor
claimed the Project drawings and specifications were deficient and
caused the additional costs, which resulted from special construction
means and methods which the contractor was compelled to utilize.
The general
contractor sued the architect directly under the theory of “Negligent
Misrepresentation”, alleging that the architect’s specifications
were false and/or misleading. The
contractor had contracted with a
School District
, and therefore it did not have a
direct contract with the architect.
Moreover, its damages were purely economic
(i.e., it did not allege bodily injury or physical damage to property).
The trial court dismissed the contractor’s suit, and the
Pennsylvania Superior Court affirmed the decision, applying established
Pennsylvania
law which had previously held that a third party contractor could not
directly sue a design professional for negligence causing purely
economic losses. However,
the Pennsylvania Supreme Court reversed, holding in a decision of first
impression by the Supreme Court, that a contractor can sue a design
professional in negligence for purely economic losses resulting from
defective plans and specifications.
The Supreme
Court reasoned that contractors fall squarely within the class of
companies which reasonably rely on the representations of design
professionals in their design documents.
Applying Section 552 of the Restatement of Torts (2d), the Court
stated that it was reasonable for a design professional to expect that
contractors would rely on information supplied in project design
documents, and reasonably foreseeable that contractors could incur
economic losses if the design information was incorrect or erroneous.
These expectations, according to the Court, reflected modern
business realities which justified holding design professionals
responsible for economic harm caused to those who rely on this
information in project plans and specifications.
The
significance of this decision cannot be overstated.
In addition to their contractual responsibility to their clients,
Pennsylvania
design professionals will now be exposed to direct causes of action for
economic losses sustained by contractors who rely on defective plans and
specifications. Such
damages may exceed those sustained by a design professional’s clients
(e.g. project owners). On
the other hand, contractors (and most likely subcontractors) now have
the option, in addition to seeking change orders from owners under their
contracts, to bring a direct action against a design professional for
increased construction costs caused by design errors and omissions.
About
the Author: Mr. Cohn is
an attorney with the law firm of Kaplin Stewart Meloff Reiter &
Stein, PC,
350 Sentry Parkway
Building 640, Blue Bell, PA 19422; acohn@kaplaw.com;
610-260-6000.
__________
Article
# 2
__________
Why Some Mediations Fail
by Allan
H. Goodman
Mediation
is often used to resolve disputes arising during performance of
construction contracts. Mediation is the non-binding, cooperative
process in which parties to a dispute select a neutral third party, the
mediator, to help them resolve their differences. The goal of mediation
is a settlement agreement. While mediation is usually voluntary, many
courts mandate an attempt to settle cases by mediation before setting a
trial date. In a typical mediation, the mediator meets with all the
parties and their attorneys in a joint session and then conducts a
series of private, ex parte
caucuses. In these private caucuses, the mediator assesses the strengths
and weaknesses of the parties’ positions and helps them frame
settlement offers. The mediator may transmit settlement offers between
the parties or may have the parties meet together in settlement
discussions. A skilled mediator is able to help the parties overcome
impasses in negotiations and guide the parties to a settlement.
While
most mediations result in a settlement, some do not. A major cause of a
failed mediation is that the participants approach mediation as
informal, adversarial litigation. A party or
attorney acting in this manner will address his or her remarks solely to
the mediator, as if the mediator were a judge. Despite the mediator’s
efforts, the party refuses to have a dialogue with the opposing party
and does not make a good faith effort to engage in settlement
discussions. The mediation fails because the mediation process has never
actually begun.
Another reason why a settlement may not be reached is that
participation in mediation may reinforce a party’s assessment that it
has a very strong case and that a better result can be achieved in
litigation. A party who has come to this conclusion has benefited from
mediation without achieving a settlement. However, the party must
proceed in litigation and achieve an acceptable outcome in order to
validate its assessment.
Failure to achieve a settlement during mediation can also be
caused by the personalities of the participants. Some disputes have
their origin in or are sustained by personality conflicts that supersede
the issues in dispute. If the parties and their attorneys treat each
other disrespectfully before or during the mediation, this may cause
psychological damage that prevents them from focusing upon and resolving
the merits of the issues of the dispute.
A mediation may terminate without a settlement because of a
participant’s impatience. A party or its attorney may expect results
too quickly or may think that the process is simply not working.
Unrealistic deadlines or milestones for achieving results may be imposed
on the mediator and the other party. This attitude is non-productive and
self-defeating. A mediation
conducted under such an arbitrary time frame will terminate simply
because time has expired.
Finally, the parties may blame the mediator for the mediation’s
failure. There are good mediators and bad mediators, and the mediator
selected by the parties or the court may not possess adequate skills to
deal with the issues and personalities involved.
On the other hand, dissatisfaction with the mediator may also
result from the parties’ unrealistic expectations or their own failure
to commit to the process. The parties may fail to prepare for the
mediation properly and refuse to attempt a dialogue with each other, but
then demand that the mediator "do his magic." There is no
magic in mediation. If the parties are not willing to prepare and work
together toward a solution, it is difficult to achieve a settlement
solely from the mediator's efforts.
Allan H.
Goodman is an experienced mediator and arbitrator, a Judge on the
U.S. General Services Administration Board of Contract Appeals, and the
author of Basic Skills for the New Mediator and Basic
Skills for the New Arbitrator. He
is also an instructor for Redvector.com, where he offers online courses
on construction mediation and arbitration. For
a detailed description of his books and courses, visit www.solomonpublications.com
and www.redvector.com.
--------------------------------------------
New
Books on Alternative Dispute Resolution -
The revised second editions of Basic Skills for the New Mediator and
Basic Skills for the New Arbitrator by Allan H. Goodman
are now available! These best-selling titles are not just for new
mediators and arbitrators. They are valuable resources for
experienced ADR professionals, attorneys, and clients involved in
mediation and arbitration.
Visit
www.solomonpublications.com
for details.
__________
Article
# 3
___________
Pollution
Exclusion in D&O Policy Applied to
Exclude
Coverage for Alleged Business Torts
By:
J. Kent Holland,
Esq.
When a property purchaser discovered pollution on its newly
acquired property it filed suit against the seller and the seller agreed
to pay certain cleanup costs. But
the seller subsequently reorganized its corporate structure and asserted
the cleanup costs could not be paid out the reorganized company.
The seller then brought suit alleging the seller intentionally
and wrongfully reorganized its corporate structure to escape the
liabilities. The seller
asked its directors & officers insurance carrier to defend the suit
and the carrier refused to do so because it claimed a pollution
exclusion in the policy barred coverage.
The seller filed suit against it carrier and after much
litigation, the carrier’s position was ultimately found correct by an
appellate court which held that because there was a relationship between
the purchasers claims concerning wrongful reorganization and the
pollution on the property, the policy’s pollution must be applied to
deny coverage.
The
seller in this case was The Danis Companies
(“Danis” or “TDC”). The purchaser was
Waste Management, Inc. (“WM”) .
The insurance carrier was Great American Insurance Company
(“Great American”). Great
American refused to advance defense costs for Danis because it asserted
that a pollution exclusion in the D&O policy barred coverage on the
underlying claim against Danis by WM.
Waste
Management had acquired the landfill from Danis as part of a sale of all
outstanding shares of certain companies from Danis to Waste Management.
In connection with the stock purchase, Danis agreed to indemnify
WM against liabilities arising out of ownership of any landfill. The
indemnity covered environmental liabilities, but it was not limited to
just environmental liabilities.
As a result of pollution found after the transfer the landfill,
the Environmental Protection Agency (“EPA”) issued notices of
liability to Danis and WM as potentially responsible parties under
Superfund. WM demanded
indemnification from Danis, and Danis eventually entered into a
settlement agreement to indemnify WM for claims arising from
environmental pollution, remediation, failure to remediate, toxic torts,
bodily injury, and property damage.
At some point, just before the settlement agreement was
finalized, Danis underwent a major restructuring whereby Danis Building
Construction Company (“DBBC”) was separated from Danis Industries
Corporation (“DIC”) and The Danis Companies (“TDC”).
Waste Management alleged in its litigation against Danis that
DBBC had been a profitable subsidiary of TDC and was split off to
insulate DBBC from environmental liabilities to WM.
Waste Management also claims that the recapitalization/split-off
of DBBC stripped DIC and TDC of assets, leaving insufficient funds to
satisfy the indemnification obligations owed to WM under the settlement
agreement. WM’s complaint
further alleged breach of several agreements by Danis concerning
responsibility for the landfill remediation and liabilities.
Great American denied coverage for Danis and refused to advance
costs for the WM lawsuit, asserting that the pollution exclusion of the
policy barred coverage. The
policy language stated that the policy excludes claims “based upon,
arising out of, relating to, directly or indirectly resulting from or in
consequence of, or in any way involving actual or alleged…
pollution…;” provided, however, that this exclusion shall not apply
to any derivative suit by a security holder of the Company if the
security holder bringing such Claim is acting totally independent of any
without the solicitation, assistance, active participation or
intervention of any Director or Officer of the Company.”
Danis filed suit against Great American for breach of contract
and declaratory judgment. The
trial court agreed with Danis that coverage was not excluded by the
pollution exclusion. The
state appellate court reversed, however, because it concluded, “The
use of the modifying words “directly or indirectly” indicates that
an indirect causal relationship is sufficient for the exclusion to
apply. Consequently, even
though we have found that the federal claims are intertwined with the
pollution settlements, coverage for these claims would additionally be
excluded as matters ‘indirectly related to … pollution.”
The reason the trail court concluded the pollution exclusion
didn’t apply was that it found the underlying federal claims revolved
around allegations of corporate reorganization to escape liabilities.
What the court essentially decided was that the alleged actions
of the officers and directors in reorganizing and recapitalizing the
corporate entities was the immediate cause of the harm alleged by Waste
Management, and that these actions served as an intervening cause
between the pollution and the damages incurred by Waste Management.
Thus, as an “intervening cause,” the damages resulting from
that cause would be independent of the pollution and would not be
excluded by the pollution exclusion.
Great American argued that the trial court was wrong to apply an
“intervening cause” approach. Although
Great American admitted that the business torts create a separate cause
of action, it argued that they are not independent causes of loss,
because they could not have arisen in the absence of the underlying
environmental liabilities.
The appellate court agreed with Great American that only one loss
occurred—that being damage
caused by the polluted site. “The
acts of the Danis companies” concluded the court, “did not cause a
separate injury or loss; instead, the alleged wrongful acts were an
attempt to avoid paying for the loss.
This is not the typical situation in which one party commits a
tort, and the negligent or wrongful act of another party operates to
cause either sharing or a complete release of liability for the
injury.” To be an
intervening cause, explained the court, “the second negligent act must
be both ‘independent’ and ‘new….’ The second act must not have
occurred as a result of the first.”
Applying these legal concepts, the appellate court found that the
claims involved in the litigation by WM against Danis were not
independent of the original pollution settlements but instead that the
underlying settlements were part of the necessary predicate for
liability of Danis is the federal case.
The original pollution settlements and the alleged illegal
transfers of assets are so intertwined and directly connected that
pollution exclusion is applicable to all the claims asserted.
For these reasons, the court held in favor of Great American and
reversed the trail court decision.
Danis
v. Great American Insurance Co., 2004-Ohio-6222 (November 19, 2004).
________
Article
# 4
_________
Rapid Result Drug Testing
By William F. Current
ã
2005 William F. Current
Would
you be surprised to learn that nearly a quarter of your workers were
illegal drug users? It could happen. Consider what a California-based
contractor discovered several years ago when it decided to prove that
its workers were not druggies.
On
a given day following 30 days advance notice employees were asked to
volunteer for a drug test. Of
the 179 people on the payroll, 80 volunteered. The urine samples were
collected by an independent laboratory, tested and reported directly to
the contractor. No names were used in either the collection or the
reporting of the results. Three different construction sites were chosen
to represent a cross section of employees from northern, central and
southern
California
.
The
results speak for themselves: the
percentage of tests that were positive for one or more drugs was 24
percent, a quarter of the employee population. From that group 15
percent tested positive for marijuana and 10 percent tested positive for
cocaine.[i]
Wow! And that was from a
group of volunteers.
The Drug Problem Today
America
has made progress in addressing its drug problem over the past 10 years,
but unfortunately the problem has not gone away. The federal
government’s annual report on substance abuse indicates just how
serious the issue is.
For
example, there are approximately 19 million current (use in the last 30
days) illicit drug users 18
and older. Further, there
are about 35 million prescription
drug abusers. There are nearly 16 million adults 21 and older who admit
to being “heavy” drinkers (5 or more drinks on at least 5 or more
occasions every month); and there are 2.3 million Americans younger than
21 who admit to being heavy drinkers.[ii]
Several
national reports on teen substance abuse do not paint a promising
picture of the near future outlook.
And, of course, today’s teen drug user is tomorrow’s job
applicant.
Drugs in the
Construction Workplace
The federal
government estimates that 77 percent of all illicit drug users 18 and
older are employed.[iii]
And the industry that is often identified for having the highest rate of
illicit drug users is the construction industry.
A 1996
federal government survey, the last such survey conducted by the
government, showed how serious the problem is for construction
companies. Among full-time construction workers between the ages of 18
and 49 more than 12 percent reported illicit drug use in the month
before the survey was conducted; almost 21 percent reported illicit drug
use during the past year. Additionally, approximately 13 percent
admitted to being “heavy” alcohol users.[iv]
Rates of
substance abuse among different occupations in the construction industry
included:
|
Position
|
Current
Illicit Drug Use (%)
|
Past
Year Illicit Drug Use (%)
|
Current
Heavy Alcohol Use (%)
|
|
Construction
Laborers
|
12.8
|
25.4
|
19.9
|
|
Construction
Supervisors
|
17.2
|
25.9
|
12.7
|
|
Other
Construction Workers
|
17.3
|
23.4
|
20.6
|
How Drug
Abuse Affects the Construction Industry
Generally
speaking, we know that substance abusing workers are less productive,
tend be unreliable, are more likely to be involved in workplace
confrontations and acts of violence, and steal from their employers and
others at a higher rate than their non-using co-workers.
A
compelling study by the U.S. Postal Service found that substance
abusers, again when compared to their non-substance abusing co-workers,
are involved in 55 percent more accidents, and sustain 85 percent more
on-the-job injuries.[v]
Further, the National Safety Council reported that 80 percent of
those injured in “serious” drug-related accidents at work are not
the drug abusing employees but innocent co-workers and others.[vi]
It also
stands to reason that if the construction industry employs more drug
users than other industries, then the impact of drug abuse would be
significant at construction sites. And, given the safety sensitive
nature of the construction industry, that impact is most significant in
the area of safety.
A study
conducted by a
Cornell
University
graduate student found that construction laborers between 25 and 34
years of age who have been treated for substance abuse have a time-loss
injury rate of 23.6 per 100 full-time equivalent workers (FTEs).
That’s nearly double the rate of non-substance abusers, who had a rate
of 12.2 FTEs.
The
majority of the cases, 85 percent, involved treatment for alcohol abuse.
The study concluded that the difference between the known
substance abusers and the non-substance abusers is “likely
understated.” The study observed that:
“Injuries
were counted as related to substance abuse only after substance abuse
was diagnosed, yet 1/3 of the substance abusers’ work-related injuries
occurred before diagnosis.”[vii]
The study only tracked workers on union jobs and only substance abusers
treated in programs paid for by union health insurance.
Drug Testing
As a Solution
The
construction industry is especially affected by drug abuse given that it
tends to hire a higher proportion of substance abusers. As a result,
employers in the construction industry tend to be very concerned about
the issue and are probably more likely to have a comprehensive drug-free
workplace program in place. And among the components of such a program
is drug and alcohol testing.
Drug and alcohol testing have proven to be highly effective ways of
deterring substance abuse and identifying those who need help.
It is legal in every state, though a handful of states regulate
it, and commonly accepted as way of life in American industry.
For many years construction companies that drug test have utilized the
services of a laboratory certified by the federal government’s
Substance Abuse and Mental Health Services Administration (SAMHSA) to
analyze all drug screens. And
for many years this was the best testing method available.
However, while drug testing makes a lot of sense for many
construction companies waiting 2-4 days to get a result from a lab is
highly impractical. When a drug test result is the only thing stopping a
crew of 20 or 30 new workers from starting a job, an immediate, accurate
result is really what is needed.
Rapid
result, on-site testing has become a popular alternative to traditional
lab-based testing, especially in safety-sensitive industries such as the
construction industry. Often a construction company can significantly
reduce the time it takes to conduct a test by utilizing rapid result
testing. The results are available within minutes and, depending on the
product being used, can be as accurate as the screening technologies
used in laboratories.
When
accidents or some other unacceptable behavior occurs, construction
companies rarely have the luxury of waiting for a lab result to come in
24-48 hours later. Rapid result testing is a viable option for
post-accident and reasonable suspicion drug testing.
Rapid
Drug Testing Is Union Friendly
Union
members are typically in favor of drug testing. A
Gallup
survey found that 71 percent of full-time union workers favor
employers’ right to conduct pre-employment testing.
Further, when asked, “would you favor or oppose your
company adopting or maintaining a drug testing policy,” 66 percent of
union respondents said they would favor such a policy compared to 26
percent who said they would not.
Union
workers are just like any other workers, the vast majority are not drug
users, yet they know who the drug users at work are and they don’t
like working side by side with them, especially in safety-sensitive
worksites.
The general
concerns that some union may have about drug testing are addressed with
rapid drug testing. Rapid
drug testing delivers fast results making it possible for workers who
test negative to get back on the job quickly.
Unions are
interested in the integrity of the testing process. A rapid drug test
can be witnessed throughout every phase of the testing process.
Workers actually get to see the entire test take place.
There is never a question about chain of custody.
And because the analysis can be witnessed there is rarely any
confrontation between the tested worker and the test administrator over
a result.
Unions are
interested in preserving the clean records of their members.
Again, because the majority of all drug screens are negative,
tested workers are not only back on the job faster, but there’s no
lingering question about the result as management, the union, and
workers wait a couple of days for a lab-tested result to come back.
Oral Fluid
Testing
Construction
employers also now have options available in terms of what specimen to
test. No longer is urine the only specimen recognized as an accurate
medium for detecting drugs. Oral fluid and hair samples have proven to
be effective in detecting drugs of abuse. Oral fluid testing, in
particular, is an attractive option to the construction industry because
it can be conducted either with a rapid result device or through a
laboratory.
Oral fluid
testing eliminates the inconvenience of securing a restroom in the
middle of a construction site. It makes it possible for every collection
to be observed, and eliminates concerns about mixed gender collections.
Studies
show that oral fluid testing is an accurate indicator of the presence of
drugs in a person’s system.
When Choosing
a Rapid Result Testing Device
A word of
caution about rapid result testing: Not all of these testing devices are
created equal. While the prices of these products have come down
significantly in the last few years, the old adage “you get what you
pay for” often comes into play. When considering instant testing, be
it with urine or oral fluid, consider the following:
-
Make sure your state
allows it. Most states have no restrictions on instant testing or
oral fluid testing, some do.
-
Look for urine devices
that are approved by the U.S. Food & Drug Administration (FDA).
This is quickly becoming the gold standard for instant urine
testing. Instant oral fluid testing has not passed FDA muster yet,
though are there several reliable products available.
-
Limit your considerations
to devices that come with independent scientific data to back up all
accuracy claims. It’s not enough to see it in writing; make sure
the source is an independent, objective one.
-
Try all devices under
consideration in real work situations. Devices differ in how they
are administered, how results are read, how long it takes to get a
result, etc. Make sure the device you’re considering will work for
you.
-
Deal with a provider who
has been in the business more than a few months (and maybe even
years). You’re going to need support, both technical and perhaps
legal. Not all providers have staffs of experts on hand to answer
your questions.
About
the Author: Mr. Current is a principal with the firm WFC &
Associates,
Substance
Abuse Prevention Consultants
8627
N.W. 50 Drive
Coral Springs
,
FL
33067
Ph:
954-255-8650 / Fax: 954-344-0707
bcurrent2@aol.com
[i]
California
Associated General Contractors, 2005.
[ii]
National Survey of Drug Use and Health. Substance Abuse and Mental
Health Services Administration.
Washington
,
D.C.
2003.
[iv]
U.S.
Department of Labor. Substance Abuse Information Database (SAID)
website.
[v]
Current, William F. Why Drug Testing?
Coral Springs
, FL. 1999.
[vii]
Meyers, Linda. “Construction Company Drug Testing Reduces Work
Injuries, Study Finds.”
Cornell
University
. 2000.
=====================================
RED
VECTOR.COM --- ON-LINE COURSES by KENT HOLLAND
Currently available risk management courses written by Kent Holland for
RedVector, (http://www.redvector.com/instructors/view_related_courses.asp?id=195)
include the following:; Contract Guide for the Design Professional,
Design Build Professional Liability Risk Management and Insurance; Site
Safety Risk and Liability; Risk Management for the Design Professional;
Managing Communication, Documentation and Reports; Insurance for
Design-Build and Complex Projects; Construction Contract Law; Contract
Claims against Design Professionals; Insurance Coverage Disputes; and
Environmental Claims. This is an efficient, easy and cost-effective to
get your continuing education credits.
=====================================
ABOUT
THIS NEWSLETTER & A DISCLAIMER
This newsletter Report is published and edited by J. Kent Holland,
Jr., J.D., is a construction lawyer and risk management consultant for the Environmental and
Design Professional Liability. The
Report is independent of any insurance company, law firm, or other
entity, and is distributed with the understanding that
ConstructionRisk.com, LLC, and the editor and writers, are not hereby
engaged in rendering legal services or the practice of law. Further,
the content and comments in this newsletter are provided for educational
purposes and for general distribution only, and cannot apply to any
single set of specific circumstances. If you have a legal issue to which
you believe this newsletter relates, we urge you to consult your own
legal counsel. ConstructionRisk.com, LLC, and its writers and editors,
expressly disclaim any responsibility for damages arising from the use,
application, or reliance upon the information contained herein.
=====================================
Copyright 2005, ConstructionRisk.com, LLC
Publisher & Editor: J. Kent Holland, Jr., Esq.
8596 Coral
Gables Lane
Vienna, VA
22182
703-623-1932
Kent@ConstructionRisk.com
_____________________________________________
_____________________________________________
|