|
ConstructionRisk.com Report
http://www.ConstructionRisk.com
Vol. 7, No. 8, December 05
______________
Inside
This Issue:
• Book
Review: Design-Build Lessons Learned (2004 Edition)
• Ambiguity
in Design-Build Contract Specs Interpreted in Favor of Contractor;
• Contractual
Jury Waivers Held Invalid by
California
Supreme Court;
• Contract & Risk
Management Guide;
• Accord and Satisfaction Barred
Contractor Claim for Additional Compensation
======================================
Contract & Risk Management
Guide – by
J. Kent Holland
If you have $39.95 remaining in your 2005 budget for books and education
materials, here is a good place to spend it.
This approximately 300 page guide provides detailed examples of
over 30 contract clauses. The discussions include risk management ideas
and suggestions for negotiating contracts with reasonable allocation of
risk between the contracting parties. Much attention is given to
explaining how contract language may affect the availability of
insurance coverage for claims against design professionals. This book is
for (1) Attorneys and insurance brokers that advise design professionals
on the insurability of contract language and the risks assumed by
contract; (2) design professionals who desire to more information and
reasoning to use during their contract negotiations with project owners;
(3) project owners who desire to understand what and why design
professionals are seeking certain
language in their contracts and rejecting language proposed by owners,
and (4) anyone concerned with design professional contracts.
http://www.constructionrisk.com/ContractGuideProNet/index.htm
=====================================
_______________
ARTICLE 1
_______________
Book
Review: Design-Build
Lessons Learned (2004 Edition)
Those of you who are interested in design-build have undoubtedly
come across Design-Build Lessons
Learned, an annual publication authored by Mike Loulakis, the
president of the law firm of Wickwire Gavin and one of the country’s
foremost authorities on design-build.
Mike first started publishing Design-Build
Lessons Learned in 1995 as a newsletter designed to give his clients
an opportunity to understand the nuances of this new area of law.
The first edition of the publication only covered ten cases,
which represented the universe of 1995 court decisions addressing
design-build disputes. Ten
years later, after unprecedented growth in both public and private
sector use of the design-build process, Mike has now reported on a total
of 304 cases, almost half of which have come during the 2002-2004 time
period. Design-Build
Lessons Learned has also become much more substantial in appearance,
as it moved from newsletter format to paperback book format in 2001.(240
pages, US$60.00).
As an avid reader of this publication, I strongly believe that
the industry needs caselaw to help explain design-build legal theories
and precedent. Over the past
few years, Design-Build Lessons Learned has regularly highlighted 20-30
important design-build cases around the country.
While this gives design-build practitioners insight into the
mistakes of others, it also affords them the opportunity to fashion best
practices from these cases.
The 2004 edition of Design-Build
Lessons Learned is a 240-page paperback book that contains an array
of significant design-build cases among its 58 reported decisions.
Although it is very difficult to identify the “best of the
best,” special attention should be paid to the following seven cases:
§
Lockheed Martin
Idaho Technologies Co. v. EG&G Idaho Inc., where an
Idaho
federal court rejected a turnkey contractor’s excuses for failing to
meet the contract’s performance guarantees.
Particularly noteworthy was the court’s conclusion that
millions of dollars of cost overruns were not sufficient to establish a
“commercial impracticability” defense to performance.
§
Record Steel and
Construction v.
United States
, where the United States Court of Federal Claims concluded that the
design-builder was entitled to a change order when the government
required it to use a “recommended” geotechnical approach instead of
what the design-builder wanted to use.
§
PDC-El Paso Meriden,
LLC v. Alstom Power, Inc., where a Massachusetts state court
concluded that an owner and an EPC contractor needed much more than a
Letter of Intent to create a binding commitment to construct a power
plant.
§
Siemens Westinghouse
Power Corp. v. Dick Corp., where a
New York
federal court refused to find that one member of a design-build
consortium could claim that it was “duped” by its partner.
§
Metropolitan Steel
Industries, Inc. v. Perini Corp., where a
New York
state court considered a series of claims arising from construction of a
New York City Transit Authority bus terminal.
Particularly noteworthy about this case is the guidance it
provides relative to the potential liability of a subconsultant engineer
to the prime design-builder, reaching a different result than what we
have seen from other cases around the country.
§
O’Brien & Gere
Technical Services, Inc. v. Fru-Con Construction Corp./Fluor Daniel,
Inc., where the 8th Circuit Court of Appeals concluded that a
design-build contract was abandoned because of, among other things, poor
change order management and a failure of the parties to ever reach
agreement on a design baseline.
§
American Family
Mutual Insurance Company v. American Girl, Inc., where the Wisconsin
Supreme Court finally ended a multi-year piece of litigation by
concluding that a design-builder’s CGL insurance policy covered the
damages incurred when a building failed because of negligence by the
design-builder’s geotechnical contractor.
For an
extensive excerpt of one of the cases taken directly from the
publication, see the next article in this issue of the
ConstructionRisk.com Report.
=====================================
Ambiguity
in Design-Build Contract Specs Interpreted in Favor of Contractor,
by Michael C. Loulakis
Record Steel and
Construction v.
United States
, 62 Fed. Cl. 508 (2004), provides an excellent example of the
evolution of design-build caselaw. The
dispute in this case involved whether a design-build contract required
foundations to be over-excavated. The
design-builder argued that the contract unambiguously made
over-excavation a design recommendation – not a design requirement.
In the alternative, it argued that if the contract was ambiguous,
then the ambiguity was latent and should be construed against the
government. The government
argued that the contract expressly and unambiguously required the
design-builder to over-excavate the foundation.
After carefully examining the relevant contract provisions, the
United States Court of Federal Claims (“Court of Federal Claims”)
found the contract to be latently ambiguous, and saddled the government
with the financial responsibility of the over-excavation. [Editor’s
Note: This casenote
discussion is excerpted from Design-Build
Lessons Learned (2004) - See
book review above for more details].
The Corps of Engineers (“Corps”) awarded Record Steel and
Construction, Inc. (“Record Steel”) an $8.8 million design-build
contract for a dormitory at Offutt Air Force Base in
Bellevue
,
Nebraska
. Part of the RFP contained
a foundation analysis report, with a section entitled “Subsurface
Recommendations.” Included
in the recommendations was the following language:
Due
to the anticipated column loads for a multi-story building, it is
believed that improving the site is more viable than reducing the
bearing pressure to a very low value …. The recommended improvement
program is outlined below.
The
recommended program contained statements that materials be undercut and
“should be excavated” from below the bottom elevation of all
building footings.
In response to the RFP, Record Steel submitted a price proposal
informing the Corps that it did not believe over-excavation for the
foundations would be required but, if site conditions ultimately
required over-excavation, Record Steel committed to perform this work at
no additional cost. The need
for over-excavation was discussed during several design meetings both
prior to and after contract award. The
parties agreed that Record Steel’s geotechnical firm was to conduct
field investigations and tests and provide such information to both
Record Steel and the Corps. If
the resulting data was satisfactory, then Record Steel could proceed
with its design without conducting over-excavation.
The geotechnical firm concluded that the native soils were
adequate to support the building’s footings without over-excavation.
However, the Corps apparently re-evaluated its position and
refused to issue a notice to proceed for the footings unless Record
Steel agreed to conform to “the requirements of the subsurface
recommendations of the Foundation Analysis Report” and over-excavate
the site. Record Steel
complied with this order and submitted a claim for approximately
$188,000 for the costs associated with the over-excavation effort.
The Court first looked at the reasonableness of each party’s
contract interpretations. In
finding that Record Steel’s interpretation was reasonable, it first
noted that Record Steel, as the designer-of-record, was expected to
exercise its professional judgment in designing the dormitory and had to
defer only to specific requirements contained in the RFP, not to
recommendations. The Court
then examined how the “requirements” in the RFP were expressed in
terms of words like “shall,” “may,” and “should.”
It found that the most critical aspects of the foundation report
used the word “should” instead of “shall” – and that this
expressed a desire for action, but not a binding requirement.
It looked to the fact that the foundation report stated that the
Corps “believed” that over-excavation was “more viable” to
improve the site, and couched its report in terms of a
“recommendation” rather than as a requirement.
The Court also found Record Steel’s interpretation to be
reasonable based on the fact that the Corps’ initial borings were not
conducted within the actual footprint of the dormitory’s location.
The Court ruled, however, that the Corps’ contract
interpretation fell “within the zone of reasonableness.”
It looked to the fact that the RFP used the verb “shall” in
connection with incorporating the foundation report’s recommendations
into the contract, and that, by referring to the terms
“over-excavation and compaction requirements,” there was an argument
that the RFP expressly converted the foundation report’s
recommendations into requirements.
Faced with two reasonable contract interpretations, the Court
then looked to the rule of contra
proferentem for guidance on who should bear the risk of these
ambiguities. The four-part
test associated with this rule places the risk of the ambiguities on the
government when: (1) the contract specifications were drawn by the
government; (2) the language used therein was susceptible of more than
one interpretation; (3) the intention of the parties does not otherwise
appear; and (4) the contractor actually and reasonably construed the
specifications in accordance with one of the meanings of which the
language was susceptible. The
Court found that all of these conditions were satisfied.
The court also refused to apply the exception to the general rule
of contra proferentem (i.e., the patent ambiguity doctrine), which
resolves ambiguities against the contractor where the ambiguities are
“‘so ‘patent and glaring’ that it is unreasonable for a
contractor not to discover and inquire about them.’”
The court did not find this ambiguity obvious, particularly since
the Corps had not indicated its view of the mandatory nature of these
so-called “requirements” until many predesign meetings between the
parties had taken place.
There are several “take-aways” from the Record
Steel case. Owners who
use competitive procurement processes, like the Corps of Engineers and
other public agencies, must remember that proposers get the benefit of
the doubt if there is something wrong with or unclear about the
owner-furnished RFP documents. The
fact that the over-excavation concept was expressed in terms of a
“recommended” process started the potential for ambiguity, and the
“should,” “may,” and “shall” verbs contained in the
foundation report sealed the deal for the conclusion that there was an
ambiguity. If the Corps
wanted to mandate over-excavation, it should have said so explicitly.
Equally important, however, is that Record Steel did the right
thing by advising the Corps during the proposal phase that it did not
intend to undercut unless soil conditions required it to do so.
These actions demonstrated that Record Steel actually relied upon
its interpretation of the ambiguity, which is one of the predicates to
recovery under the contra
proferentem rule. The
result of this case might have been different if Record Steel recognized
the ambiguity but never informed the Corps of its interpretation during
the proposal process.
=====================================
Contractual
Jury Waivers Held Invalid by
California
Supreme Court
By Daven
G. Lowhurst
Thelen Reid & Priest LLP
October 3, 2005
The Issue
The California Supreme Court has single-handedly altered the contractual
expectations of parties to thousands of contracts governed by
California
law. For many years, parties to a wide variety of contracts – such as
leases and construction contracts – have knowingly agreed to give up
their right to have their disputes resolved by jury trial. Indeed, these
contracting parties likely continue to assume that any dispute that
arises in the future will be subject to the jury waiver clause in their
contracts. Confidence in the enforceability of contractual jury waivers
could only have been increased beginning in 1991 when a
California
appellate court expressly validated such jury waivers.
That confidence was been shattered by the California Supreme Court
recently in Grafton Partners L.P. v. Superior Court, 36 Cal.4th
944 (2005). The court ruled that contractual pre-dispute waivers of the
right to trial by jury are unenforceable. Further, the Court elected to
treat its ruling as retroactive, meaning that jury waivers are
invalidated in existing contracts.
A brief trek through the Court’s analysis is helpful to understanding
how the Court reached its decision and what alternatives remain
available to parties who wish to avoid the expense and uncertainty of
entrusting their contractual disputes to juries.
The Decision
In Grafton, a partnership hired PriceWaterhouseCoopers (PWC) to
audit accounts. Under the retention agreement, the parties agreed not to
demand a trial by jury in any action arising out of PWC’s services.
The partnership sued PWC for negligence and misrepresentation arising
out of the audit and demanded a jury trial. PWC, after unsuccessfully
asking the trial court to strike the jury demand, obtained relief from
the Court of Appeal. The Supreme Court reversed.
The court ruled that under
California
law, jury trials can be waived only when one of the six situations set
out in Code of Civil Procedure §631 had occurred. Section 631 allows
jury waivers when, for example, a party consents to waive jury in open
court, fails to timely demand a jury trial or fails to pay jury fees. A
contractual pre-dispute jury waiver is not one of those situations.
Thus, the court found that such waivers violate the California
Constitution’s right to trial by jury.
In so ruling, the Court disapproved of the Court of Appeal decision in Trizec
Properties, Inc. v. Superior Court, 229 Cal.App.3d 1616 (1991),
which had validated pre-dispute contractual jury waivers by analogizing
them to arbitration clauses. Trizec reasoned that if parties
can contractually do away with trials altogether, they certainly can do
away with trials by jury.
The Supreme Court found that analogy unpersuasive. First, the court
explained that unlike jury waivers, arbitration clauses are expressly
authorized by statute and advance a strong public policy in favor of
arbitration. Second, arbitrations conserve judicial resources to a much
greater extent than court trials by avoiding the judicial forum
altogether. By contrast, court trials unquestionably tax the court
system, even if to a lesser degree than jury trials.
The Supreme Court then ruled that its decision applies retroactively, i.e.,
to pre-existing contracts. PWC argued that pre-dispute jury waivers are
commonplace and that retroactive application of the court’s decision
would upset long-established contractual expectations. The court was not
persuaded that an exception to the normal rule of retroactive
application should be found because Trizec did not constitute a
uniform body of law that could reasonably have been relied on in forming
expectations.
A concurring opinion pleaded for the California Legislature to authorize
pre-dispute jury waivers because they offer an “attractive middle
ground” between jury trials and arbitration. Specifically, court
trials calm contracting parties’ fears of runaway jury awards while
providing greater procedural and evidentiary safeguards than
arbitration. Court trials also provide the additional safeguard of a
full right to appeal rather than the very limited right to seek to
vacate arbitration awards. Finally, court trials reduce the expense and
delay associated with jury trials.
The Impact
Grafton broadly invalidates pre-dispute contractual jury
waivers. What’s more, it invalidates jury-waiver clauses in existing
contracts, thereby shattering the contractual expectations of thousands
of parties who have entered into contracts governed by
California
law.
Unless and until the California Legislature authorizes pre-dispute jury
waivers, contracting parties seeking to avoid the expense and risk
associated with jury trials may be limited to having their disputes
resolved by arbitrators or by referees (usually retired trial court
judges). The pros and cons of arbitration versus reference
versus jury trial should be examined with legal counsel.
Likewise, given that Grafton is retroactive, parties to existing
contracts with jury waivers should consult legal counsel to determine
whether to attempt to modify the contract to provide for arbitration or
reference or whether to leave the invalid jury waiver as it is.
Whether in an existing contract or in a contract to be negotiated, if
arbitration is preferred to having the dispute resolved by a referee,
care must be taken to ensure that the arbitration clause satisfies
California law, as different rules of arbitral enforceability govern
different types of contracts. Further, when arbitration or reference is
sought to resolve contractual disputes, care must be taken to ensure
that the clause is not later invalidated as unconscionable. A pro-active
approach to reviewing existing contracts with an eye toward dispute
resolution will help ensure that any dispute is resolved in a manner
consistent with the parties’ expectations.
About the Author: This
article is written by Daven G. Lowhurst, an attorney in the
San Francisco
office of Thelen Reid & Priest, LLP.
The article was originally published in the firm’s newsletter
and on the website: ConstructionWebLinks.com.
Mr. Lowhurst may be contacted at 415-369-7270 or at dglowhurst@thelenreid.com.
=====================================
RED VECTOR.COM --- ON-LINE COURSES by KENT
HOLLAND
Do you need year end continuing education courses?
Currently available on-line risk management courses written by
Kent Holland for RedVector, (http://www.redvector.com/instructors/view_related_courses.asp?id=195)
include the following:; Contract Guide for the Design Professional,
Design Build Professional Liability Risk Management and Insurance; Site
Safety Risk and Liability; Risk Management for the Design Professional;
Managing Communication, Documentation and Reports; Insurance for
Design-Build and Complex Projects; Construction Contract Law; Contract
Claims against Design Professionals; Insurance Coverage Disputes; and
Environmental Claims. This is an efficient, easy and
cost-effective to get your continuing education credits.
=====================================
Accord and
Satisfaction Barred Contractor Claim for Additional Compensation
-- By J. Kent Holland
Where a contractor timely completed a construction contract for the U.S.
Army Corps of Engineers and accepted payment which included changes
required by the Corps, the contractor was barred from later filing a
claim for additional compensation. The
claim was barred by accord and satisfaction because when signing change
orders the contractor did not reserve its rights to assert any
additional delay or impact. Moreover,
the contractor had signed releases in certain bilateral modifications
that barred its claims.
The contractor was paid the lump sum contract price plus over $600,000 in
additional compensation for changes to the work that were agreed upon
and authorized by bilateral modifications.
After completing the work and being paid, the contractor, Jackson
Construction Company (Jackson), sought to recover additional
compensation under two separate claims.
One claim was for early completion delay.
The other was an impact claim to recover additional overhead and
general administrative costs.
Jackson
asserted that the project was delayed by the Corps of Engineers at the
start of the project causing the contractor to have to overcome a 120
day delay. This was
allegedly due to the having to redesign and relocate a waterline that
ran through the footprint of the building.
Jackson
argued the applicability of what is known as the Eichleay formula for
calculating additional home office overhead.
The other claim was for additional damages allegedly incurred due
to cumulative impact of numerous changes required by the Corps during
performance.
The U.S. Claims Court found in favor of the Corps and denied the claims
due to (1) accord and satisfaction and (2) on the merits, the contractor
failed to prove its case. As
explained by the court, “The doctrine of accord and satisfaction is an
absolute defense that terminates any previous right that a party may
have had to assert a claim of the same subject matter.”
Further explaining this, the court stated: “An ‘accord’ is
a contract under which both parties agree that one party will render
additional or alternative performance in order to settle an existing
claim made by the other party, and ‘satisfaction’ is the actual
performance of the accord. A
party asserting an accord and satisfaction defense must establish four
elements: (1) proper subject matter; (2) competent parties; (3) a
meeting of the minds; and (4) consideration.”
The issue concerning the delay was that the contractor asserted that
although it completed the contract exactly on time, it could have
completed its work much earlier if it had not been for delays due to the
waterline location that were allegedly caused by the Corps.
In reviewing these issues, the court pointed out that
Jackson
chose to move the waterline and that the Corps approved
Jackson
’s plan with the work to “be performed at no additional cost to the
Government.” Eventually,
the Corps paid
Jackson
on a claim for the waterline relocation in the amount of $15,212 on a
total claim of $18,212. The
modification, along with all the other bilateral modifications executed
by the parties included the following stipulation regarding schedule
delays and impact changes: “The
contract period of performance remains the same.
It is further understood and agreed that this adjustment
constitutes compensation in full on behalf of the contractor and his
subcontractors and suppliers for all costs and markup directly or
indirectly, including extended overhead, attributable to the change
order, for all delays related thereto, and for performance of the change
within the time frame stated.”
The Corps agued that
Jackson
was barred by this release language from obtaining any further damages.
The court agreed that
Jackson
did not make a timely reservation of rights to assert additional damages
for the problems associated with the work, either in its original claim
or at any time prior to the execution of the bilateral modification.
It was not until after the contract was completed that
Jackson
first attempted to make an additional delay claim.
The same was true of
Jackson
’s cumulative impact for the changes required by the Corps.
The court found that “
Jackson
never attempted to reserve its rights to assert a cumulative impact
claim at any time during the work.”
Jackson argued that there had been no accord and satisfaction because the
release language was in effective for the following reasons: (1) Jackson
says it made a written reservation of rights to assert an impact claim
at a later date; (2) the modifications were ambiguous; (3) the
modifications were the result of misrepresentations by the Corps; and
(4) the modifications were executed under duress.
The court found none of these arguments were supported by the
evidence presented at trial. The
court found
Jackson
did not explicitly reserve its rights to assert a delay or impact claim
at a later date. Even
if
Jackson
did attempt to reserve its rights, however, the court found it did not
do so in a timely manner. In
fact, the court stated that the delay and impact claim appeared to be an
after thought. According to
the court, “It does not appear that
Jackson
had even considered submitting a delay claim at that time.
Jackson
did not request any delay damages when it submitted its [original] claim
for the waterline location….”
Much later, when executing two contract modification completely unrelated
to the claims at issue in this particular matter,
Jackson
attempted to make two after-the-fact reservations of rights pertaining
to the earlier matters. “The
Court views
Jackson
’s actions as an invalid attempt to revive claims that had already
been extinguished by its execution of bilateral modifications.”
Moreover, said the court, “
Jackson
did not reserve its rights to assert future claims arising from any of
the other specific performance problems that it presented at trial.”
In reviewing the language of the release, the court found that it was
neither ambiguous nor obtained by misrepresentation.
And, finally, the court found that
Jackson
had been under no duress when it agreed to the release language.
For these reasons, the court found in favor of the Government and
against the contractor.
Jackson Construction Co., Inc v.
The
United States
,
62 Fed.Cl. 84.
Comment:
This case points out how important it is for contractors to
exercise extreme caution when executing change orders—if they intend
to reserve any potential claims for delay and impact.
It is sometimes difficult when agreeing to a change order to know
the full impact of the change in the event that the project owner issues
multiple additional changes impacting the project and the contractor’s
work. If there is a chance
that additional damages may arise out of a change, the contractor should
strive to include some language explicitly reserving its rights.
Otherwise, it may find itself in the situation described in this
case.
About the author: Kent
Holland is a construction lawyer in Tysons Corner, Virginia, and is a
risk management consultant for the environmental and design professional
liability. He also publisher of ConstructionRisk.com Report.
=====================================
ABOUT
THIS NEWSLETTER & A DISCLAIMER
This newsletter Report is published and edited by J. Kent Holland,
Jr., J.D., a construction lawyer and risk management consultant for Environmental and
Design Professional Liability. The
Report is independent of any insurance company, law firm, or other
entity, and is distributed with the understanding that
ConstructionRisk.com, LLC, and the editor and writers, are not hereby
engaged in rendering legal services or the practice of law. Further,
the content and comments in this newsletter are provided for educational
purposes and for general distribution only, and cannot apply to any
single set of specific circumstances. If you have a legal issue to which
you believe this newsletter relates, we urge you to consult your own
legal counsel. ConstructionRisk.com, LLC, and its writers and editors,
expressly disclaim any responsibility for damages arising from the use,
application, or reliance upon the information contained herein.
=====================================
Copyright 2005, ConstructionRisk.com, LLC
Publisher & Editor: J. Kent Holland, Jr., Esq.
8596 Coral
Gables Lane
Vienna, VA
22182
703-623-1932
Kent@ConstructionRisk.com
_____________________________________________
|