|
ConstructionRisk.com Report
http://www.ConstructionRisk.com
Vol. 10, No. 3, July 08
______________
Inside
This Issue:
• Limitation
of Liability Clause Enforced in A/E Agreement;.
• Indemnification
Provisions of AIA Contract Did Not Require Contractor to Indemnify
Client for Economic Losses Claimed by Adjacent Property Owner;
• Contractor
Could Not Recover From Engineer for Interference
======================================
_________
Article
1
__________
Limitation
of Liability Clause Enforced in A/E Agreement
A
North Carolina
court has ruled that a limitation of liability clause in an engineering
services agreement did not violate the laws of
North Carolina
or
Georgia
. Additionally, the clause applied to direct contract damages,
consequential damages and claims for professional malpractice.
In this case, Mosteller Mansion LLC hired Mactec
Engineering and Consulting of Georgia Inc. to assess the subsurface
conditions of a 16-acre tract of land in
Buncombe County
,
N.C.
, where Mosteller intended to develop an apartment complex. The
engineering services agreement, which stipulated that it would be
governed by the laws of the state of
Georgia
, where Mactec was headquartered, called for Mactec to recommend
foundation designs and site preparation procedures. The contract also
contained two clauses entitled “Indirect Damages” and “Limitation
of Liability.” Unlike the rest of the agreement, these two clauses
were printed entirely in capital letters.
The Indirect Damages clause said neither party
would be responsible “for any economic, consequential or indirect
damages (including, but not limited to, loss of use, income, profits,
financing or reputation) arising out of or relating to this
Agreement.” The Limitation of Liability clause read in part as
follows:
“To the maximum extent
permitted by applicable law and for additional compensation of $10.00
from [Mactec], [Mosteller] hereby expressly agrees that the liability of
[Mactec] … for any cause of action based upon breach of contract,
strict liability, negligent professional acts, errors or omissions, or
negligent misrepresentation arising out of or in connection with this
Agreement and/or services provided or work product developed pursuant to
this Agreement, shall be limited to the aggregate sum … of $50,000 or
the total fees paid to [Mactec] by [Mosteller] under this Agreement,
whichever is greater.”
Mactec drilled 19 soil test borings at the site,
presented its findings, recommended foundation designs, and billed
$8,900 for its services. Three years later, Mosteller sued Mactec for
more than $3 million in damages allegedly incurred because of unsuitable
soils. The damages included not only the cost of removing and replacing
the soil, but also testing and engineering services, loss of business,
insurance premiums, and interest on borrowed funds. The suit alleged
breach of contract and professional negligence.
Mactec moved for summary judgment, relying on the
Indirect Damages and Limitation of Liability clauses. A
North Carolina
trial court, applying
Georgia
law, ruled in favor of Mactec. Mosteller appealed, arguing that the law
of
North Carolina
, where the project was located, should govern and that the contract
clauses in question were unenforceable because they violated the public
policy of the state of
North Carolina
.
The Court of Appeals of
North Carolina
said the choice of law provision in the contract was clear and
enforceable—
Georgia
law would govern all claims under the contract. The court agreed with
Mosteller that the law of
North Carolina
, where the project took place, should govern all negligence claims
outside the contract.
The court went on to rule that the Limitation of
Liability clause, an express allocation of financial risk between two
business entities, negotiated at arm’s length, did not violate the
public policy of Georgia. The limitation was enforceable against
Mosteller.
The Indirect Damages disclaimer was also
enforceable. Mactec did not attempt to exculpate itself from
responsibility for personal injury, public safety or property damage.
Like the Limitation of Liability clause, this was a contractual
allocation of financial risk between two business entities. It did not
offend public policy.
The court also addressed the professional
malpractice claims, governed by the law of
North Carolina
. Both clauses expressly applied to negligence claims. The court ruled
that the clauses should be enforced accordingly.
“People should be entitled to contract on their
own terms without the indulgence or paternalism by courts in the
alleviation of one side or another from the effects of a bad bargain.…
The parties were sophisticated professionals and the result of their
bargain does not elicit a profound sense of injustice. Moreover,
Mosteller’s assertion to the contrary, all of Mosteller’s damages
were economic, indirect and consequential and the health and safety of
the public are not implicated.”
The facts of this case illustrate the rationale
behind the allocation of risk established in these clauses. The engineer
provided $8,900 in services. The owner was attempting, in effect, to
hold the engineer responsible for the overall viability of the entire
project, seeking recovery of more than $3 million in alleged damages.
Mosteller
Mansion LLC v. Mactec Engineering and Consulting of Georgia Inc.,
May 20, 2008, COA07-664. This
is an unpublished opinion of the North Carolina Court of Appeals and
does not constitute controlling legal authority. Citation is disfavored,
but may be permitted in accordance with the provisions of Rule 30(e)(3)
of the North Carolina Rules of Appellate Procedure.
About the
Author: This case note was originally published in
Construction Claims Advisor, and is republished here in
ConstructionRisk.com Report (Vol. 10, No. 3, July 2008) with permission.
__________
Article
2
__________
Indemnification
Provisions of AIA Contract Did Not Require Contractor to Indemnify
Client for Economic Losses Claimed by Adjacent Property Owner
The issue is in this case was whether a contractor
was required to indemnify its client (project owner) for damages claimed
by a third party (neighboring landowner) when the contractor’s backhoe
struck an underground power cable that supplied electricity to the
neighbor’s property. The
ultimate appellate court decision held that indemnification was not
required by the AIA A201/CM contract
because there was no evidence that contractor was negligent, plus the
damages claimed were purely economic.
In the case of Watral
& Sons, Inc. v. OC
Riverbend 58, Inc. (NY,
2008), the court interpreted the indemnification clause of the 1980
edition of AIA Document A201/CM . Watral
& Sons (Contractor) executed this contract form with OC Riverbend
(Owner) to provide excavation, drainage and sanitary work necessary to
build an Applebee’s Restaurant on the Owner’s property.
While excavating for the sewer line, Contractor struck an
underground power cable that serviced a neighbor’s adjacent property.
Before doing the excavation, Contractor called
“New York One Call” to request marking the electric line.
This was done. Subsequently,
however, an unidentified electrician relocated the cable.
Contractor had no knowledge of the relocation and was working 10
to 15 feet from the flags that marked the supposed location of the cable
when its backhoe struck it.
This was repaired immediately, with Contractor paying for the
material costs of the repair and the electrician providing the labor.
This might have been the end of the story but for the fact that
two weeks later the cable was again broken when a Contractor employee
was excavating in the same area and the ground near the cable collapsed.
The collapsing ground dragged the cable and damaged it in the
sample place it had been previously repaired.
Contractor again paid for the materials to fix the damage to the
cable.
Owner paid the contractor only half of the total
contract price and withheld the balance due to a claim against the owner
by the neighbor for damages arising out of the power interruption.
The owner paid the neighbor almost $70,000 to resolve that claim
and withheld the same amount from the contractor.
The contractor then filed a mechanic’s lien against the
property to recover the balance of the contract price.
Contractor subsequently filed suit to foreclose on its lien.
In its answer and defense, the owner asserted that the contractor
was required to indemnify the owner for the third party claim pursuant
to the indemnification clause of the contract and the “Safety of
Persons and Property” clause.
The trial court found in favor of the contractor on
the basis that the contract required indemnification by the contractor
only for its own negligent acts. There
was no evidence here of contractor negligence.
That decision was reversed by the intermediate appellate court.
The court agreed that the contractor was not required by the
indemnification clause (Article 4.18) to indemnify the owner since there
was no contractor negligence. However, applying the “Safety of Persons
and Property” clause of paragraph 10, the court held the contractor
had a broader indemnity obligation under that clause to indemnify the
owner even if the contractor was not negligent.
Subparagraph 10.2.1.3 of the contract provides:
“the Contractor shall take all reasonable precautions for the safety
of, and shall provide all reasonable protection to prevent damage,
injury or loss to: . . . property at the site or adjacent thereto,
including trees, shrubs, lawns, walks, pavements, roadways, structures
and utilities not designed for removal, relocation or replacement in the
course of construction; ….”
Subparagraph 10.2.5 provides further:
“The Contractor shall promptly remedy all damages or loss . . .
to any property referred to in Clause … 10.2.1.3 caused in whole or in
part by the Contractor . . . for which the Contractor is responsible
under Clause . . . 10..2.1.3, except damage or loss attributable to the
acts or omissions of the Owner, the Architect, the Construction Manager
or anyone directly or indirectly employed by any of them, or by anyone
for whose acts any of them may be liable, and not attributable to the
fault or negligence of the Contractor.
The foregoing obligations of the Contractor are in addition to
the Contractor’s obligations under Paragraph 4.18.”
These clauses from Article 10 were held to require
indemnification by the contractor without regard to negligence.
This decision, however, was reversed by the court of appeals.
As reason for the reversal, the court held that Article 10 only
applied to “property” damage, and that the only property damage
involved in this case was the property damage to the electric cable.
There was no evidence of any damage to the neighbor’s property.
Instead, the neighbor sustained only purely economic injury.
Such economic injury is not covered as property damage under
Subparagraph 10.2.5 quoted above. For
that reason, the court stated it did not need to reach or express an
opinion as to whether subparagraph 10.2.5 imposed a negligence or
fault-type liability standard. Since
the clause in no event applied to economic losses, it would make no
difference whether the contractor was at fault.
For these reasons, the court ordered that the trial court
decision be reinstated in favor of the contractor.
Comment: The
distinction recognized here by the court between the genuine
“property” damage that is intended by the contract clause and
economic loss of the type at issue in this case is an important one.
This same principle comes into play when making claims under
various insurance policies to recover property damage.
This has been discussed in numerous case notes and articles
previously presented in this newsletter.
About the author:
J. Kent Holland is a construction lawyer located in Tysons Corner
, Virginia , with a national practice (formerly with Wickwire Gavin,
P.C. and now with Construction Risk Counsel, PLLC) representing design
professionals, contractors and project owners. He is founder and
president of a consulting firm, ConstructionRisk, LLC, providing
consulting services to owners, design professionals, contractors and
attorneys on construction projects. He is publisher
of ConstructionRisk.com Report and may be reached at Kent@ConstructionRisk.com
or by calling 703-623-1932. This article is published in
ConstructionRisk.com Report, Vol. 10, No. 3 (July 2008).
_________
Article
3
__________
Contractor
Could Not Recover From Engineer for Interference
The Idaho Supreme Court has ruled that a contractor
could not recover from the project owner’s consulting engineer for
alleged interference with the performance of the construction contract.
The engineer was an agent of the owner and was protecting the owner’s
interests when monitoring and testing the work.
The Pocatello Development Authority retained J-U-B
Engineers Inc. to provide design and construction monitoring services
for a utility, street and sidewalk reconstruction project. The Authority
subsequently awarded the construction contract to BECO Construction Co.
Inc.
The construction contract contained a number of
provisions defining the role of the engineer, which included routing all
owner communications to the contractor through the engineer. The
engineer served as the owner’s representative throughout the project
and had authority to monitor the progress and quality of the work. The
engineer also had authority to test the contractor’s work product.
BECO Construction later complained that J-U-B
Engineers unreasonably stopped work on the project and delayed BECO’s
performance. BECO claimed that J-U-B had tested asphalt and aggregate
compaction in an incompetent manner, resulting in improper rejection of
street improvements. BECO sued J-U-B for tortious and intentional
interference with the performance of the construction contract.
J-U-B moved for summary judgment, arguing that it
had only been performing its responsibilities to the project owner, as
defined in the engineering services agreement and the construction
contract. A trial court granted summary judgment in favor of J-U-B
Engineers. BECO appealed.
The Supreme Court of Idaho said a claimant could
recover from another for interference with a contract only if the
defendant was a stranger to the contract. One cannot “interfere”
with a contract to which one is a party. J-U-B Engineers was not a party
to the construction contract in the traditional sense; it was not a
signatory to the contract. But, J-U-B was not a stranger to the
contract, either.
The court noted that the construction contract
spelled out in considerable detail the role and responsibilities of the
engineer during construction. BECO was fully aware of this role. J-U-B
was the agent of the project owner and was responsible for protecting
the owner’s interests. The monitoring and testing performed by J-U-B
were in keeping with its contractual responsibilities. Consequently,
J-U-B Engineering could not be liable to BECO Construction for tortious
or intentional interference with the performance of the construction
contract.
“These [contract] provisions, along with a number
of others, clearly provide J-U-B with broad discretionary authority to
monitor BECO’s progress, and encompass those actions BECO complains of
here. Although J-U-B was not a party to the construction contract in the
traditional sense, it acted as the City’s agent by the very terms of
the contract between BECO and the City.… Since J-U-B was an agent of a
party to the contract and was acting for the benefit of such party, it
is not a stranger to the contract and therefore cannot be liable for
tortious interference with such contract.”
Contractors have had better luck pursuing construction
monitors based on theories of professional malpractice or negligent
misrepresentation. As explained by the court in this opinion, there is
an inherent flaw in an interference claim.
BECO Construction Co., Inc.
v. J-U-B Engineers, Inc., Supreme Court of Idaho, Case no.: 33378,
Date filed: May 2, 2008.
About
the author: This case note was originally published in Construction
Claims Advisor, and is republished here in ConstructionRisk.com Report
(Vol. 10, No. 3, July 2008) with permission.
======================================
Green
Building Best Practices 2008:
Four
Sessions
Sponsored
by Construction Claims Advisor
Construction
Project Controls &
Green
Building Insider
Session 1* - Design Considerations - It's
More Than Just About LEED Certification
Wednesday, July 9, 2008 1:00 - 2:30 pm Eastern Time*
TO
REGISTER: Click on the following link:
https://www.magnetmail.net/events?8d4b8cd76e534b9d8f4fc944bc84eebaa
The
burden to achieve certification, whether for new or existing buildings,
starts with design. Energy efficiency, renewable resources, acoustics,
air quality, conservation, recycling and waste minimization all have a
part in the big picture. Complete project life cycle design is the key
to successful green building projects.
Whether
dealing with LEED, Energy Star or local certification guidelines, you
want to make green design and construction a standard practice. Best
practices in building performance design is the topic of our first
session: Green
Building Best Practices 2008: Session 1 - Design Considerations - It's
More Than Just About LEED Certification
#1
– July 9, 2008
Design Considerations - It's More Than Just About LEED Certification What
is it, who benefits, where’s the ROI for the Designer? Contractor?
Occupant? Building owner? Using design best practices to find the most
economical alternatives to achieve the highest possible certifications.
#2
– July 23, 2008
The Construction Phase - Tips, Techniques and Concerns
CMs, contractors and subcontractors play a crucial role in executing the
green design intent. Learn how to plan and manage construction to
maintain or improve certification ratings. Josh R. Greenfield, PE, LEED®
AP, of Primera Engineers, Ltd. and Jim Day, LEED-AP, VP Clark
Construction Group, LLC, discuss lessons learned including
preconstruction issues, management tools, documentation methods,
subcontractor training and contract close-out.
#3
– August 6, 2008
Commissioning - Where the Rubber Meets the Road
Long before green building hit the radar, savvy owners insisted on
formal commissioning programs to assure design goals are met. Now LEED
for New Construction (LEED-NC) requires it. Commissioning planning
should start during the design process; find out how to implement
commissioning best practices, how it's done, who should perform it and
why it often improves the opportunity to achieve on-time and on-schedule
project delivery. Hear experienced experts including commissioning
expert Amir Yazdi, PE, LEED-AP, of CTG Energetics, provide insight
gained on 35 projects of all sizes and types.
#4
– August 20, 2008
Legal and Risk Considerations
Construction attorneys Bryan Jackson and Mike Cathcart from Allen
Matkins Leck Gamble Mallory & Natsis LLP along with William Broz, PE
of CTG Forensics, LLP., discuss the major risks associated with green
building -- capital (design/build cost & schedule), operational
(operation costs) and reputational (failure to achieve certification) --
as well as emerging risks such as ownership, regulatory and casualty.
Much is at stake, including loss of financial incentives, occupancy
delays, future marketability and reputation, for starters. Risks affect
all parties - owner, designer, contractor and CM - and are best dealt
with at contract formation.
TO
REGISTER: Click on the following link:
https://www.magnetmail.net/events?8d4b8cd76e534b9d8f4fc944bc84eebaa
======================================
RED
VECTOR.COM --- ON-LINE COURSES by KENT HOLLAND
Currently available risk management courses written by Kent Holland for
RedVector, (http://www.redvector.com/instructors/view_related_courses.asp?id=195)
include the following:; Contract Guide for the Design Professional,
Design Build Professional Liability Risk Management and Insurance; Site
Safety Risk and Liability; Risk Management for the Design Professional;
Managing Communication, Documentation and Reports; Insurance for
Design-Build and Complex Projects; Construction Contract Law; Contract
Claims against Design Professionals; Insurance Coverage Disputes; and
Environmental Claims. This is an efficient, easy and cost-effective to
get your continuing education credits.
=====================================
ABOUT THIS NEWSLETTER & A DISCLAIMER
This newsletter Report is published and edited by J. Kent Holland,
Jr., J.D. The Report is independent of any insurance company,
law firm, or other entity, and is distributed with the understanding
that ConstructionRisk.com, LLC, and the editor and writers, are not
hereby engaged in rendering legal services or the practice of law.
Further, the content and comments in this newsletter are provided for
educational purposes and for general distribution only, and cannot apply
to any single set of specific circumstances. If you have a legal issue
to which you believe this newsletter relates, we urge you to consult
your own legal counsel. ConstructionRisk.com, LLC, and its writers and
editors, expressly disclaim any responsibility for damages arising from
the use, application, or reliance upon the information contained herein.
Copyright 2008, ConstructionRisk, LLC
Publisher & Editor:
J. Kent Holland,
Jr., Esq.
8596 Coral Gables Lane
Vienna
,
VA
22182
703-623-1932
Kent@ConstructionRisk.com
_____________________________________________
|