|
ConstructionRisk.com Report
http://www.ConstructionRisk.com
Vol. 10, No. 4, September 08
______________
Inside
This Issue:
• Contractor did not Owe Indemnity for Economic
Loss Incurred by Third Party Resulting from Contractor’s Excavation
Work;.
• Why
it Pays to Rely on Outside Counsel and Consultants When Requesting an
Equitable Adjustment
;
• Limitation
of Liability Clause Enforced in
North Carolina
Case While Similar Clause Rejected in a
Georgia
Decision
;
• Indemnity Clause
in Contract between GC and Subcontractor Enforced to Require Sub’s
Insurance Carrier to Defend and Indemnify GC in Wrongful Death Suit
Caused in part by Alleged Negligence of GC
======================================
_________
Article
1
__________
Contractor
did not Owe Indemnity for Economic Loss Incurred by Third Party
Resulting from Contractor’s Excavation Work.
Applying
the language from an American Institute of Architects (AIA) contract
form A201/CM (1980 ed.), an appellate court held that an excavator had
no responsibility to indemnify its client for economic
losses claimed by a neighboring property owner resulting from a
break in an underground electric cable from excavation activities on the
client’s property. When
the excavator struck and damaged the cable while digging a sewer line,
he provided the labor and material to repair it.
Electric service to the neighbor’s property was disrupted on
two occasions by damage to the cable resulting from performance of the
excavating. The neighbor
claimed against the project owner and that claim was settled with a
financial payment. The Owner
then sought indemnification or reimbursement of its settlement costs
from the excavator.
In reviewing whether the excavator was required to indemnify the
owner, the final appellate court affirmed the trial court holding that
indemnification was not required. This
is because Article 4.18.1 of the contract only mandated indemnification
for the negligent acts of the excavator.
There was no evidence of negligence.
A second article of the contract (Sections 10.2.1.3 and 10.2.5)
also came into play, however, and the intermediate appellate court and
final appellate court disagreed with each other over the application of
this clause.
Subparagraph 10.2.1.3 required the contractor to take all
reasonable precautions to prevent damage, injury or loss, including to
utilities. Subparagraph
10.2.5 required the contractor to remedy all damage or loss “to any
property referred to in Clause ….10.2.1.3 caused in whole or in part
by the Contractor….” This
clause was interpreted by the court to apply only to property damage on
the property itself. The
only property damage here was to the electric cable on the client’s
property. There was no
evidence of any property damage to the neighbor’s property.
The neighbor claimed only purely economic losses.
The court held these were not covered by this contract clause.
Watral & Sons v. OC
Riverbend (NY ap.)
Comment:
This case is instructive in explaining the differences between
the negligence based indemnity provisions of article 4 and the absolute
duty under article 10 for the contractor to remedy damage that it caused
“in whole or in part.” There
is no requirement in article 10 that there be negligence on the part of
the contractor in order for it to be found responsible for the damages.
As the court correctly states, however, this responsibility only
applies to actual property damages directly caused by the contractor and
not to economic losses incurred by someone on some other property.
If a different indemnity obligation is desired, the parties to a
contract should carefully tailor the clauses to allocate the risks more
narrowly or broadly.
__________
Article
2
__________
Why
it Pays to Rely on Outside Counsel and Consultants When Requesting an
Equitable Adjustment
By:
Brian P. Waagner
Over
the last several years, government contract lawyers have been sounding
the false claims alarm bell with great fervor.
The warnings may be justified.
The Justice Department has created a Procurement Fraud Task
Force, which is actively encouraging federal agencies to identify and
prosecute contractors that engage in fraudulent activity.
New regulations that would actually require contractors to
disclose potential fraud and false claims are under consideration.
The Court of Federal Claims has issued several remarkable
decisions penalizing contractors for the submission of false claims.
There have been a significant number of criminal fraud
investigations relating to contracts for services and supplies in
Iraq
.
Contractors
are well-advised to avoid even being accused of submitting a false claim
or a false statement. In
addition to the monetary penalties and other damages imposed by statute,
a false claim could mean suspension or debarment.
In extreme cases, it could mean jail time for those involved.
Given the high stakes, even an unproven false claims allegation
is a major disadvantage. Many
contractors would rather give up a legitimate claim than run the risk of
losing a false claims act case.
Government
contractors are certainly revisiting their compliance programs and
improving their policies and management protocols in order to prevent
the submission of a false claim. From
day to day, managers will all need to increase their awareness of false
claims issues.
One
area that will require special attention is the process if submitting
requests for equitable adjustment and claims for additional compensation
or extensions of time as a result of changes in contract requirements.
Because claims are such a significant source of false claims
issues, contractors will need to be more vigilant than ever in vetting
their requests for additional compensation.
Questions of entitlement and cost will need to be carefully
reviewed before a claim is
submitted.
Now
more than ever, contractors should consider involving outside counsel
and technical or cost consultants in the preparation of a request for
equitable adjustment. Involving
counsel and consultants early in the disputes process would not only
bolster a contractor's position on entitlement, cost, or schedule
impact, but it would minimize the risk of a false claims allegation.
If a false claims issue arises, the early involvement of counsel
and consultants could enhance the contractor's defense and facilitate
the negotiation of a more favorable settlement of both the false claims
issue and the underling contract modification.
While
there is a cost associated with using outside counsel and consultants,
the FAR cost principles offer some solace.
FAR 31.205-33 provides that costs of outside counsel and
consultants are allowable costs of contract administration.
This means that a contractor may recover attorney's fees and
consulting costs incurred in connection with the administration of the
contract as part of a request for equitable adjustment.
Although the total amount of fees paid must be
"reasonable" and "allocable," attorney's fees and
consulting costs reimbursed as costs of contract administration are not
subject to the limits imposed by the Equal Access to Justice Act.
Large business and small business alike can recover counsel and
consulting fees in excess of $125 per hour under this FAR cost
principle.
Federal
contractors regularly seek and obtain reimbursement of attorney fees and
consulting costs incurred on routine matters of contract
administration—subcontract negotiations, schedule adjustments, etc.
But the FAR provision that makes them allowable applies equally
to fees and costs incurred in connection with responding to a DCAA
audit, a contracting officer's request for information, preparing a
request for equitable adjustment, or negotiating a significant contract
modification. In light of
the potential false claims issues that sometimes appear in response to
an improperly supported request for equitable adjustment, it may be
smart to involve counsel and consultants on these tasks.
Since their fees and costs can be recovered from the government,
involving them is almost a necessity.
FAR
31.205-33 is not a blank check that allows contractors to recover all
counsel and consulting fees incurred in support of a government
contract. Perhaps the most
significant restriction on their allowability appears in FAR
31.205-47(f)(1). This FAR
provision prohibits recovery of professional or consulting costs
incurred in connection with prosecuting or defending claims asserted by
or against the federal government. FAR
31.205-47(f)(1).
The
government often cites this FAR provision in seeking to avoid liability
for contractor attorney's fees and consulting costs.
Certainly, attorney's fees or consulting costs incurred in
connection with drafting a certified claim letter or litigating a case
at the Court of Federal Claims or a Board of Contract Appeals are not
allowable costs of contract administration.
(There are other ways to recover attorney's fees in litigation,
but that question is for another day.)
Fortunately,
there are a number of decisions that help define whether counsel and
consultant fees will be treated as allowable costs of contract
administration or unallowable claim prosecution costs.
The Federal Circuit's decision in Bill
Strong Enterprises, Inc. v. Shannon, 49 F.3d 1541, 1550 (Fed. Cir.
1995), calls for an examination of the contractor's "objective
reason" for incurring the cost:
"If a contractor incurred the cost for the genuine
purpose of materially furthering the negotiation process, such cost
should normally be a contract administration cost allowable under FAR
31.205-33, even if negotiation eventually fails and a CDA claim is later
submitted. . . . On the
other hand, if a contractor’s underlying purpose for incurring a cost
is to promote the prosecution of a CDA claim against the Government,
then such cost is unallowable under FAR 31.205-33."
Significantly, the decision in Bill Strong recognizes the distinction between an informal request
for equitable adjustment and a formal Contract Disputes Act
"claim." Costs
incurred in connection with a claim are unallowable.
But costs incurred in connection with the preparation and
negotiation of a request for equitable adjustment and before the claim
is certified are "presumptively allowable."
While the government may be able to prove that the real purpose
for the fees was really to support a later claim, a contractor can
properly take the position that it can recover outside counsel and
consulting fees incurred before a CDA claim is certified.
See, e.g.,
SAB
Construction v. United States,
66 Fed. Cl. 77, 91 (2005) (consultant costs incurred in preparing REA
and negotiating with Government were allowable); Fru-Con Constr. Corp., ASBCA Nos. 53544, 53794, 2005-1 BCA ¶ 32,936
(allowing recovery of legal and consulting costs incurred to prepare and
negotiate REA); Lamb Engineering &
Constr. Co., EBCA No. C-9304172,
97-2 BCA ¶ 29,207 (allowing REA preparation costs because
“[n]egotiations based upon the REA were conducted and some issues
settled over an eight-month period”); Federal Insurance Co.,
IBCA No. 3236 et al., 96-2 BCA ¶ 28,414 (“costs incurred by a
contractor for a price adjustment due to a Government-caused delay are
allowable if they are reasonable and directed primarily toward
settlement negotiations”); Herman B. Taylor Constr. Co., GSBCA
No. 12,915, 96-2 BCA ¶ 28,547 (“if the contractor incurred the costs
for materially furthering the negotiation process, such costs should
normally be contract administration costs allowable under FAR 31.205-33
even when, as here, the negotiation fails and litigation eventually
follows.”)
The allowability of counsel and
consulting fees after a claim is certified is more questionable, even if
the fees were genuinely incurred in support of negotiations.
In
Plano
Builders Corp. v.
United States
, 40 Fed. Cl. 635 (1998), the Court of Federal Claims rejected
a demand for professional fees incurred to assist with settlement
negotiations after the claim had been certified. The court concluded
that concluded that settlement negotiations in this context are an
expected part of the CDA claims process and not an ordinary part of
contract administration.
The decision in Plano
Builders, however, has not been universally followed.
In the Armed Services Board of Contract Appeals, at least two
decisions have allowed contractors to recover post-claim attorney's fees
incurred in connection with negotiating settlements with the government.
See Propellex Corp.,
ASBCA No. 50203, 02-1 BCA ¶ 31,721; Grumman
Aerospace Corp., ASBCA No. 50090, 00-1 BCA ¶ 31,316.
There is no requirement
that a contractor submit a request for equitable adjustment or attempt
to negotiate a settlement before submitting a certified claim.
It may be wise in some cases to omit the REA altogether and move
forward with the disputes process as quickly as possible.
At a minimum, the submission of a certified claim begins the
period during which the contractor is entitled to recover interest on a
claim.
However, there is a downside to proceeding immediately with the
formal disputes process without first presenting an REA.
Because counsel and consulting fees incurred in connection with
the prosecution of a CDA claim cannot be recouped from the government,
contractors in this situation will be motivated to prepare and present
their CDA claims without the assistance of counsel and consultants.
While this is sometimes feasible, even careful contractors going
this route are vulnerable to false claims allegations.
In such a case, a simple error in the cost calculations or a
faulty analysis of a scheduling issue could undermine an otherwise
legitimate claim.
Seeking the assistance of counsel and consultants to prepare a
request for equitable adjustment and to assist in negotiations with the
government has several advantages. The
contractor will have the benefit of the lawyer's legal analysis or a
consultant's technical support early in the process.
This early involvement can assist the contractor in making
decisions about notifying the government of a differing site condition
or mitigating damages that might result from a defective specification.
Early involvement of counsel can be valuable in responding to a
DCAA audit, a stop work order, or a decision to terminate a contract for
default or convenience. It
can assist the contractor in identifying and quantifying damages or
compiling sufficient evidence to support a request for additional
compensation or an extension of time.
At a minimum, early involvement of counsel and consultants can
help contractors avoid the submission of false claims or defend false
claims allegations when they do appear.
Given the value counsel and
consultants add to the resolution of contract modifications and the
potential downside of going it alone, it would be smart to use counsel
and consultants even if their fees could not be recouped from the
government. But with the FAR
cost principles and the cases supporting the recovery of attorney's fees
and consulting costs incurred to assist a contractor in preparing an REA
and negotiating a settlement, the decision about whether to use counsel
and consultants is that much easier.
About the Author:
Brian Waagner is a shareholder in the Tysons Corner office of
Akerman Senterfitt Wickwire Gavin, where his practice focuses on the
resolution of claims and contract disputes on public and private
projects. Mr. Waagner regularly advises contractors and subcontractors
on the preparation of requests for equitable adjustment and Contract
Disputes Act claims. In addition to representing clients in litigation
before the Boards of Contract Appeals, Mr. Waagner is active in
alternative forms of dispute resolution, including arbitration and
mediation. Contact
information: Akerman
Senterfitt Wickwire Gavin;
8100 Boone Blvd, Suite 700
;
Vienna
,
VA
22182
; 703-790-8750; brian.waagner@akermnan.com.
_________
Article
3
__________
Limitation
of Liability Clause Enforced in
North Carolina
Case While Similar Clause Rejected in a
Georgia
Decision
By: J.
Kent Holland
A limitation of liability (LoL) clause limiting a land
surveyor’s liability to $50,000 was enforced in
North Carolina
. A similar clause was held
unenforceable in an important
Georgia
case. The only apparent
difference in the clauses two is that the contract in
North Carolina
applied the LoL only to damages arising out of claims asserted by the
client. The contract in the
Georgia
suggested that the LoL applied to all possible claims – including
those by third parties. This
third party claim language, according to the
Georgia
court, turned the clause into a type of indemnity agreement rather than
just a limitation of liability agreement.
In Blaylock Grading Company
v. Neal
Everett
Smith, (N.C. Ct. of Appeals, 06 CVS 70, April 2008), the clause was
entitled “Risk Allocation.” It
provided the following: “[Defendants’ liability to plaintiff] for
any and all injuries, claims, losses, expenses, damages or claim
expenses arising out of this agreement, from any cause or causes, shall
not exceed the total amount of $50,000, the amount of [defendants’]
fee (whichever is greater) or other amount agreed upon when added under
Special Conditions. Such
causes include, but are not limited to, [defendants’] negligence,
errors, omissions, strict liability, breach of contract or breach of
warranty.”
In performing land surveying for the plaintiff, the defendants
apparently mistakenly set benchmarks higher than specified in the design
plan, and this required plaintiff to incur the expenses of importing
fill to raise the elevation of the site.
The Plaintiff filed suit and defendants moved for partial summary
judgment to enforce the $50,000 liability limitation.
The trial court denied the motion and the matter went to trial
with a jury finding in favor of the plaintiff in the amount of $574,714.
In response to the defendants’ motion for judgment
notwithstanding the verdict, the trial court held that the Risk
Allocation provision was void as against public policy and entered
judgment on the jury verdict.
On appeal, the defendants argued that the trial court erred in
finding the clause void and unenforceable.
They argued that their partial summary judgment motion should
have been granted. The
appellate court agreed, and held that (1)
North Carolina
law allows a professional engineer/land surveyor to limit its liability
and that (2) the Risk Allocation limitation of liability clause did not
violate the state anti-indemnity statute.
The court cited several North Carolina Supreme Court decisions
previously holding that limitation of liability clauses are not contrary
to public policy. One such
case precedent decision was quoted as follows:
“People should be entitled to contract on their
own terms without the indulgence of paternalism by courts in the
alleviation of one side or another from the effects of a bad bargain.
Also, they should be permitted to enter into contracts that
actually may be unreasonable or which may lead to hardship on one side.
It is only where it turns out that one side or the other is to be
penalized by the enforcement of the terms of a contract so
unconscionable that no decent, fair-minded person would view the ensuing
result without being possessed of a profound sense of injustice, that
equity will deny the use of its good offices in the enforcement of such
unconscionability.”
The court stated that (1) there were no irregularities in
formation of the contract, and (2) the plaintiff and defendants were
“sophisticated, professional parties that conducted business at
arms’ length.”
The appellate court also reversed the trial court’s conclusion
that land surveying services fall within the “public service
exception” that bars enforcing LoL clauses because the services are
“extensively regulated” industries.
The appellate court held that merely because engineers and
surveyors are regulated and licensed does not convert their profession
into a public service. Moreover,
the court stated that because the claim involved only economic loss, the
health and safety of the public are not implicated.
Finally, the court rejected the plaintiff’s argument that the
state’s anti-indemnity statute made the LoL clause void and
unenforceable. That statute provides that a clause “purporting to
indemnify or hold harmless the promisee … or indemnitees against
liability for damages arising out of bodily injury to person or damage
to property proximately caused by or resulting from the negligence, in
whole or in part, of the promise … is against public policy and is
void and unenforceable.” Because
the contract at issue in the case only involved a clause limiting a
party’s liability for damages to its client and did not purport to
provide any indemnity relating to bodily injury or property damages to
third parties, the court held the anti-indemnity statute to be
inapplicable. For these
reasons, the trial court’s decision was reversed and the case remanded
for entry of judgment consistent with the limitation of liability
clause.
In the
Georgia
decision of Lanier v. PEC (
Georgia Supreme Ct.
, S07G1424), the
Georgia
court considered a similar clause to the one discussed above but reached
the opposite conclusion. Because
the limitation of liability clause in the contract stated that it would
be applied to “any and all claims” not just from the client but also
by “third parties”, the court held that this was contrary to the
Georgia anti-indemnity statute that, similar to that of North Carolina,
prohibits a person from being indemnified for its own negligence to
third parties.
Comment:
The appellate court in
North Carolina
got it right on each and every point of its well reasoned decision.
It is enough to restore one’s faith in the judicial system when
we see a court enforce the law as established through the common law
decisions or by the statutes of the state.
It is unfortunate that the find a trial court judge so willing to
ignore both the common law (including state Supreme Court decisions) as
well as the state statutes. Such
disregard for precedent and legislative intent makes litigation
frustrating and unpredictable – and ultimately quite expensive as
multiple appeals must be filed to get to a correct decision.
The
Georgia
decision was wrongly decided initially and it stayed wrong even after
appeal. The Court seemed to
find a problem in the limitation of liability clause of its own making
and imagination. Perhaps if
the damages at issue had something to do with bodily injury or property
damage claims by third parties, there might have been some logic to the
decision. But this was just
a simple dispute between parties to a contract.
There was no third party claim at issue.
The legal reasoning of the
North Carolina
court is directly applicable to the situation.
Unfortunately the
Georgia
court decided to the contrary.
This does not mean, however, that LoL clauses are no longer
enforceable in
Georgia
. As best I can tell, it
simply means that when drafting these clauses, it will be important to
strictly limit them to claims by the client.
I just completed a case defending a professional consulting firm
that was sued for $2.4 million, but as a result of a $50,000 limitation
of liability clause in the contract (plus good facts and state law on
our side) we case ultimately settled for far, far less than the LoL
amount. In a different case
I defended last year involving an $8 million claim, a court enforced a
$50,000 LoL on our motion for summary judgment.
The plaintiff eventually opted to settle with us paying one
thousand dollars ($1,000), rather than going through an expensive trial
where their potential recovery had been so severely limited by the
applicability of the LoL clause.
My consistent message to professional consultants in this
increasingly litigious environment is that they get an appropriate, well
written limitation of liability clause in their contract.
Keep that clause separate and apart from any indemnity clause.
Make the clause apply to claims only by the client for damages
incurred by the client. Avoid
putting any language in the LoL clause that might suggest it applies to
third party claims. Make the
amount of the limitation significant enough that the court will deem it
reasonable. I like the
language quoted from the
North Carolina
case where the limitation amount was $50,000 or the fee WHICHEVER IS
GREATER. I prefer this use
of the “greater” instead of the “lesser” of the fee and the
dollar amount as I have noted in some contracts.
If the fee was very small, it is possible that a court might be
less inclined to enforce the provision. As seen in courts (but not all
courts) around the country, LoL clauses enjoy wide support and serve a
legitimate need and purpose. The
fact that contract negotiated at arms length between sophisticated
parties contains an obvious and well worded LoL clause goes a long way
in discouraging law suits from being filed, and that certainly help
tremendously to narrow down the case through successful filing of
motions.
About the author: J. Kent Holland is a construction
lawyer located in Tysons Corner, Virginia,
with a national practice (formerly with Wickwire Gavin, P.C. and
now with Construction Risk Counsel, PLLC) representing design
professionals, contractors and project owners. He is founder and
president of a consulting firm, ConstructionRisk, LLC, providing
consulting services to owners, design professionals, contractors and
attorneys on construction projects. He is publisher of
ConstructionRisk.com Report and may be reached at Kent@ConstructionRisk.com
or by calling 703-623-1932. This article is published in
ConstructionRisk.com Report, Vol. 10, No. 4 (September 2008).
________
Article
4
__________
Indemnity
Clause in Contract between GC and Subcontractor Enforced to Require
Sub’s Insurance Carrier to Defend and Indemnify GC in Wrongful Death
Suit Caused in part by Alleged Negligence of GC
By: J. Kent Holland, Esq.
Where XL Specialty Insurance Company insured a subcontractor that
had contractually agreed to indemnify the general contractor (Kiewit
Offshore Services, LTD or “GC”) for all suits or liabilities on
account of acts or omissions of the subcontractor whether or not caused
in part by the negligence of the GC, the trail court granted declaratory
judgment ruling that XL Specialty had a duty to defend and indemnify the
GC in an underlying wrongful death suit.
The primary issue on appeal was whether the indemnity clause
clearly and unambiguously stated the intent that the Subcontractor must
indemnify the GC for all liability caused by GCs own negligence.
The appellate court agreed with the trial court that the clause
satisfied the
Texas
law requiring that where express negligence of another party is to be
indemnified, it must be unambiguously stated.
In XL Specialty Insurance
Company v. Kiewit Offshore Services, Ltd. and
RBT Welders (
U.S.
5th Cir., No. 06-41785, January 2008), the basic facts were
as follows: Kiewit Offshore
Services (Kiewit) was a GC on the Skyway Bridge San Francisco Bay
Project. Kiewit entered into
a subcontract with RBT Welders (RBT), for RBT to provide welders to
Kiewit to work at Kiewit’s facility in
Ingleside
,
Texas
for materials to be used on the bay project.
While welding in a confined space, an employee of RBT was killed
as a result of an explosion. The
explosion also killed an employee of Kiewit who had been standing on the
roof above space where the welding occurred.
The families of both individuals filed a suit against Kiewit and
RBT in
Texas
state court alleging negligence by both companies.
Kiewit demanded that XL, the excess liability insurance carrier
of RBT, defend and indemnify Kiewit as an additional insured.
XLSpecialty refused.
RBT and Kiewit both settled the wrongful death suit.
XL Specialty filed a declaratory judgment action in federal
district court, seeking a judgment that it had no duty to defend or
indemnify Kiewit for Kiewit’s settlement because Kiewit was not an
additional insured under the XL Specialty policy.
Kiewit filed a third party claim against RBT and a cross-claim
against XL Specialty, asserting that RBT had a duty to defend and
indemnify Kiewit under the indemnification provision in the contract,
and that the XL policy provided coverage for RBT’s liability under the
indemnification provision.
The district court granted summary judgment for Kiewit, holding
that (1) the indemnity clause of the subcontract required RBT to
indemnity Kiewit of all claims and damages, (2) expressly including
those resulting from Kiewit’s own negligence, and (3) that the XL
Specialty policy provided coverage for RBT’s contractual duty to
indemnify Kiewit.
This summary judgment decision was affirmed on appeal, with the
U.S. Fifth Circuit Court finding that the indemnity clause was
unambiguous and satisfied the express negligence rule of
Texas
. The clause in question
(entirely in capital letters) provided as follows:
“(b) To
defend and indemnify them against and save them harmless from any and
all claims, suits or liability for damages to property, including death,
and from any other claims, suits or liability on account of acts or
omissions of subcontractor, or any of its subcontractors, suppliers,
officers, agents, employees or servants, whether or not caused in part
by the active or passive negligence or other fault of a contractor
indemnified party; provided however subcontractor’s duty hereunder
shall not arise if such claims, suits or liability, injuries or death or
other claims or suits are caused by the sole negligence of contractor,
unless otherwise provided in the prime contract.
Subcontractor’s obligation hereunder shall not be limited by
the provisions of any worker’s compensation act or similar statute.”
XL Specialty and the subcontractor argued that this clause was
unlike those that had been previously found to unambiguously apply to
the indemnitee’s own negligence in that the phrase “liability on
account of acts” was used instead of “liability arising out of
acts”. The court
concluded that this was a distinction without a difference.
The two phrases are have the identical legal meaning according to
the court.
Next, the court held that the “inclusionary language”
providing for indemnity “whether or not caused in part by the active
or passive negligence or other fault of a contractor” was sufficient
to demonstrate the parties’ intent that the subcontractor will
indemnify the contractor regardless of whether the contractor is
partially responsible.
Comment:
The outcome of this decision requiring the insurance carrier to
cover the liability of the subcontractor arising out of the indemnity
provision of the subcontract demonstrates how important it is that both
the language of the subcontract as well as the language of the insurance
policy be carefully reviewed and understood.
A different result might have occurred if the indemnity provision
in the contract had restricted the indemnity to apply only “to the
extent” of damages caused by the performance of the subcontractor.
Indemnity obligations may be even further restricted to apply
only to the extent of damages caused by the negligence of the
subcontractor. The
insurance policy, itself, can be crafted to avoid contractual liability
coverage for damages that are not directly caused by the insured entity.
Even more restrictive policy language limiting the contractual
liability coverage to only those damages caused by the Insured’s own
negligence may also be used.
It should be noted in this case that Kiewit argued it was an
additional insured under the XL Specialty policy.
That did not seem to be the case.
The court did not make its decision on whether or not Kiewit was
an additional insured. It
was the contractual liability coverage that subjected XL Specialty to
liability. The same points
above concerning the possible different terms that may be used in the
contractual liability coverage or exclusions apply to additional insured
endorsements. Not all
additional insured provisions or endorsements are alike.
If a carrier desires to do so, it may provide language in the
additional insured endorsement limiting insurance coverage to the
additional insured so that only liability arising out of the Named
Insured’s acts are covered, instead of also picking up liability for
the additional insured’s acts – and even negligence.
Another issue that arises in some of these cases is that the
subcontract may contain a specific provision requiring the subcontractor
to obtain insurance to cover the indemnity and other contractual
obligations of the contract. The
subcontractor and its insurance professionals should be aware of such
clauses so the subcontractor does not over commit to what it can
reasonably obtain from its insurance carrier.
Just because the subcontractor signs a contract stating that its
insurance will cover the contractual liability provisions does not make
it so. The carrier is only
required to cover what is expressly stated in its own contract
(insurance policy) with the subcontractor.
Be careful not to assume that all contractual liability and
additional insured provisions are the same or equal.
About the author: J. Kent
Holland is a construction lawyer located in Tysons Corner, Virginia,
with a national practice (formerly with Wickwire Gavin, P.C. and
now with Construction Risk Counsel, PLLC) representing design
professionals, contractors and project owners. He is founder and
president of a consulting firm, ConstructionRisk, LLC, providing
consulting services to owners, design professionals, contractors and
attorneys on construction projects. He is publisher of
ConstructionRisk.com Report and may be reached at Kent@ConstructionRisk.com
or by calling 703-623-1932. This article is published in
ConstructionRisk.com Report, Vol. 10, No. 4 (September 2008).
=====================================
Construction SuperConference 08
December 10-12, 2008 - The Palace Hotel, San Francisco;
Earn up to 20 MCLE Credits;
To Receive Special Early Pricing You Must
Register by September 17, 2008
The Construction SuperConference, now in its 23rd year, is recognized as the
preeminent legal construction conference. With the guidance of the Advisory
Board and the expertise and feedback from past participants and long-time
supporters of the conference, the program will provide insight into some of
the most complex legal and business issues facing the construction industry.
To register:
http://www.constructionsuperconference.com/ME2/Default.asp
=====================================
ABOUT THIS NEWSLETTER & A DISCLAIMER
This newsletter Report is published and edited by J. Kent Holland,
Jr., J.D. The Report is independent of any insurance company,
law firm, or other entity, and is distributed with the understanding
that ConstructionRisk.com, LLC, and the editor and writers, are not
hereby engaged in rendering legal services or the practice of law.
Further, the content and comments in this newsletter are provided for
educational purposes and for general distribution only, and cannot apply
to any single set of specific circumstances. If you have a legal issue
to which you believe this newsletter relates, we urge you to consult
your own legal counsel. ConstructionRisk.com, LLC, and its writers and
editors, expressly disclaim any responsibility for damages arising from
the use, application, or reliance upon the information contained herein.
Copyright 2008, ConstructionRisk, LLC
Publisher & Editor:
J. Kent Holland,
Jr., Esq.
8596 Coral Gables Lane
Vienna
,
VA
22182
703-623-1932
Kent@ConstructionRisk.com
_____________________________________________
|