|
ConstructionRisk.com Report
http://www.ConstructionRisk.com
Vol. 11, No. 1, January 09
______________
Inside
This Issue:
• How Building Information
Modeling (BIM) Impacts Insurance Availability by Changing the Roles,
Responsibilities, and Risks of Project Participants.
• Subcontract Installation
of Unattractive Wrong Shingles not Property Damage Covered by CGL Policy.
• Mechanic’s Lien Waiver
Found Unenforceable because Violation of Public Policy.
• Plan Drafter Penalized
for Practicing Architecture without a License.
• No Coverage in
Homeowner’s Policy for Mold Damage from Water Pipe leak
======================================
_________
Article
1
__________
How Building Information Modeling (BIM) Impacts
Insurance Availability by Changing the Roles, Responsibilities, and
Risks of Project Participants.
J. Kent Holland, Jr. –
(with attribution to Rod Taylor – AON) (Short excerpt from ABA
Presentation to ABA Forum on the Construction Industry – Winter
Conference (January 15-16, 2009 – Bonita Springs, FL)
What are the key risk allocation issues that may be impacted
by the use of Building Information Modeling (BIM) on a specific
construction project? According
to some attorneys and commentators, the risks unique to BIM are minimal
and more than offset by its many benefits.
For example, my friend, attorney Rick Lowe, writes: “When all
of these issues are analyzed, the perceived legal risks in using 3D
modeling melt away and are outweighed by the obvious benefits of clash
detection and greater project collaboration. It should only be a matter
of time before insurers offer discounts to encourage clients to wear the
clash-detection ‘safety belts’ of 3D modeling.
Ultimately, the question will morph into whether team leaders
actually increase risks by not using 3D modeling, much like not using seat belts.”(1)
While underwriters may agree that there are benefits of early
conflict detection and resolution through 3D modeling, they are less
likely to see how they can underwrite their single insured, who has a
minor participation in the BIM model, and who may pick up full
responsibility and liability for claims arising out of mistakes caused
by use of or reliance on that model.
The challenge for the insurer is that this scenario resembles
insuring someone “for all damages caused in whole or in part by their
acts, errors or omissions.”
The courts interpret language of this type to mean the
responsible party is liable for all damages arising out of the acts of
all parties involved in a transaction, so long as the assuming party was
responsible to any degree for the resulting loss or damage.
The collaboration of contractors and subcontractors in the design
has the potential to create uninsurable professional liability risks for
themselves, as well as the design professionals, where BIM is used for
design and construction of a project.
Similarly, the collaboration of the design professionals in the
means, methods and procedures of construction has the potential to
create uninsured general liability risks for the design professionals.
In fact, both professional liability and general liability risks
may be difficult to insure in projects where BIM is utilized.
Risks as Viewed by a
Professional Liability and Environment Insurance Broker
Many serious risk allocation and insurance concerns have been
raised by the managing director of Aon Environmental Insurance Services
Group, Rodney J. Taylor, in a white paper entitled: “Professional
Liability Risks in BIM Applications:
If BIM is Here to Stay, How Can We Insure Errors and
Omissions?” (2) Because
of the major role he plays in one of the most significant insurance
brokers for construction industry, we should consider carefully his view
of the impact of BIM risks. Rather
than paraphrase or edit his comments, I will quote him directly:
Reliance on the
information developed and maintained in a BIM system raises questions
concerning the role of the architect in performing professional services
associated with the construction process.
With systems that are capable of generating beam sizes and
concrete thickness from three-dimensional models, who is responsible for
the specification of the final elements incorporated into a structure
designed and built with BIM technology?
Is the answer the same if the architect’s data is supplemented
by data from the contractors, vendors and the owner that result in the
selection of different elements from those originally specified by the
architect and/or the BIM system?
Over-reliance on BIM
technology presents a chance for heightened liability on the part of
design professional if the information being input into a BIM system is
incorrect or the software processes it incorrectly. (3)
Some architects and structural experts fear that this will result
in catastrophic failures where no human judgment is applied after the
fundamental construction components have been selected by computer
programs based on the architect’s design parameters.
There is also fear that the new breed of architects that
interface with the BIM systems may lack field experience and
“street-sense”. This
could lead to construction using materials and systems that experienced
personnel would intuitively understand to be unworkable.
Legal issues will
also arise in determining responsibility for design errors where greater
collaboration among the construction team spreads decision-making for
design elements beyond the traditional set of design professionals.
Liability may depend on what information is included in the database;
who has the ability to add or change data and how much reliance
contractors place on the output from the BIM system.
With the lines of responsibility blurred, professional liability
risks may spread from the traditional design professionals to include
contractors, subcontractors and even building owners that alter the data
in the BIM databases.
***
Another question that
has been asked with respect to the use of BIM systems is whether they
alter the standard of care applied to design professionals for their
work in developing building concepts and specifications.
It is important to understand that BIM does not promise
“perfect” drawings. The
work of the architects and engineers is still subject to errors that can
result in change orders during construction or future structural
problems. The owner still
needs to set aside a contingency fund for construction coordination
issues that arise during construction * * *.
In his White Paper, Mr. Taylor also makes several suggestions for
design professionals that, if followed, may facilitate the availability
of insurance to cover the risks arising out of BIM.
If a design professional’s current policy does not provide
affirmative coverage for BIM, it should, at a minimum, not contain an
exclusion expressly excluding claims arising out of BIM.
An astute underwriter will want to inquire as to the following:
(1) Is the design professional obtaining risk allocation clauses
in its contracts stating that the use of BIM is not intended to alter
the normal standard of care applicable to the design professional’s
services?
(2) Who can input data into the BIM model and can that affect the
data or the results of the data provided by the design professional?
(3) If the design professional’s BIM content can be altered by
future decisions of the Owner or contractors, is there a contractual
indemnity provision to protect the design professional against liability
resulting from those changes?
(4) Does the design professional’s contract with its
owner/client include a third-party beneficiary clause stating that use
of the BIM model is not intended to create any contractual relationship
with third parties (e.g., contractors and suppliers) that may also be
using the model?
(5) Does the design
professional contract include a waiver of consequential (and even
direct) damages resulting from flaws or failure of a BIM system for
which it was not responsible? (4)
Footnotes:
1) Richard H. Lowe, Constructor Magazine,
January/February 2007 (McGraw-Hill Co.).
2) Rodney J. Taylor, J.D, P.E., CPCU,
CLU
,
ARM
– Director , Professional
Liability Risks in BIM Applications,
AON Risk Services, unpublished white paper (December 14, 2007),
pages 7-9.
3) Gary
Prather, Building Information
Modeling: The Wave of the
Future?, INSIGHT,
September 18, 2007
.
4) See
Taylor, Professional Liability
Risks in BIM Applications, supra, pages 8-10 for additional risk
management suggestions from the insurance professional’s perspective.
__________
Article
2
__________
Subcontract
Installation of Unattractive Wrong Shingles not Property Damage Covered
by CGL Policy
Where a subcontractor, without knowledge or
permission of the prime contractor, purchased and installed shingles on
the roof of a new garage that were a different color and an inferior
grade than specified by the contract, the homeowner sued the prime
contractor for damages for breach of contract, negligence and consumer
fraud. The prime
contractor’s general liability (CGL) carrier defended the case.
Before the case was given to the jury for deliberations, the
plaintiff withdrew the negligence count of the complaint.
The jury returned a verdict for the plaintiff on the remaining
counts of breach of contract and consumer fraud.
The CGL carrier then withdrew its defense and refused to
indemnify the prime for the damages awarded by the jury – stating that
the award was not covered by the terms of the policy.
Both the trial court and appellate court found that the CGL
carrier correctly denied coverage because there had been no “property
damage” as defined under the policy.
In a declaratory judgment action by the prime
contractor against its CGL carrier, the trial court ruled in favor of
the insurance carrier on a summary judgment motion – holding that the
jury award was excluded from coverage under the policy.
On appeal, the appellate court affirmed the decision, and
explained that the basis of its holding was that neither “physical
injury” nor “loss of use” of property occurred in this case.
The key to the court’s decision was the term
“property damage” which was defined by the policy (CGL Form
23-3) to be “physical injury to tangible property” or the “loss of
use of tangible property that is not physically injured.”
The court decided that although the shingles were
inferior in quality and different in color from those specified in the
contract, “Nothing in the record, however, suggests that any physical
defect existed in the shingle material used or in the manner in which
the shingles were installed, or that the [homeowner] was unable to use
their new garage as a result of the inferior shingles.”
For this reason, the court stated “We decline to find coverage
for aesthetic damage under a CGL policy that does not explicitly provide
for it.” Down
Under Masonry, Inc. v. Peerless Insurance Co., 950 A.2d 1213 (
Vt.
2008).
Comment:
Where the only item asserted to be damaged is the work
itself, many cases have held that the “your work” exclusion in the
policy bars coverage. In
this case, the court did not address that issue.
It limited its review to the more basic question of whether an
inferior quality product that was aesthetically unpleasing to the
homeowner could be considered to be “property damage” under the
policy. There was no
allegation that the shingles leaked or that they otherwise permitted
damage to occur to other parts of the building or to equipment stored
inside the building. Had
there been such allegations, there are a number of court decisions in
various jurisdictions holding that the damages to these areas or items
(other than the shingles themselves) could potentially be covered as
“property damage” under the policy.
An interesting aspect of the fact pattern in this
case, not discussed by the court, was that the jury found the prime
contractor liable for fraud. Fraud
is not covered by insurance. In
a case where a plaintiff drops the negligence count from its complaint
but prevails on its fraud count, it seems a reasonable argument could be
made that all losses, costs, and damages arising out of the fraud
(including breach of contract caused by the fraud) would be excluded.
_________
Article
3
__________
Mechanic’s
Lien Waiver Found Unenforceable because Violation of Public Policy
Where a lien waiver provision incorporated by
reference into a subcontract applies to prohibit all liens regardless of
whether the subcontractor received any payment, the court concluded that
such a provision violates public policy.
Enforceability of a lien waiver clause must be resolved on a
case-by-case basis to determine, whether public policy is violated.
Likewise, a pay-if-paid clause was found to be a violation of
public policy as a violation of public policy to secure payment for
contractors.
In Lehrer
McGovern Bovis, Inc. v. Bullock Insulation, 185 P.3d 1055 (Nev.
2008), the Nevada Supreme
Court affirmed the decision of the trial court that both the mechanics
lien waiver provision and the pay-if-paid provision of a subcontract
violated public policy and could not be enforced to bar the
subcontractor’s claim. The
critical facts giving rise to the underlying dispute between the
subcontractor (Bullock Insulation), prime contractor (Bovis), and
project owner (Venetian Resort), involve a dispute over subcontractor
entitlement to be paid for certain services and certain re-work that
Bullock asserted was additional work beyond its original scope of
services.
Bovis was the construction management firm for the
project. Bullock Insulation
was under subcontract to Bovis to provide firestopping work on the
project. This included installation of “firestop putty pads” around
the electrical boxes in the separation walls of the hotel rooms.
Due to reasons that are not completed fleshed out in the
decision, Bullock did not install putty pads in all the walls in which
such pads were ultimately required by the county building department.
Bovis directed Bullock to retrofit all of the guest room walls by
installing the omitted putty pads. After
completing this retrofit work, Bullock recorded a mechanic’s lien on
the project and filed a complaint in the local court to foreclose on the
mechanic’s lien and pursue other claims.
In response to the Bullock complaint, Bovis
counterclaimed for breach of contract.
At the conclusion of the trial, a jury found that the subcontract
required Bullock to install the putty pads in all the rooms, but
nevertheless found that Bullock was entitled to be paid for the retrofit
work. Although this jury
verdict appeared internally inconsistent, Bovis and Venetian Resort did
not object to the verdict before the jury was discharged.
On appeal, the court found that because the jury verdict and the
jury interrogatory answers had internal inconsistencies, the trial court
abused its discretion by entering the judgment as to the extra
compensation for the retrofit work.
The court then focused its analysis on the lien as
to the other issues and amounts claimed by Bullock, and whether the lien
waiver and/or the “pay-if-paid” clause of the subcontract barred
Bullock from recovery.
Bovis argued that the pay-if-paid clause precluded
Bullock from recording a valid lien.
The trial court rejected that argument by finding that the
pay-if-paid clause was unenforceable as a matter of public policy
because “[i]t deprives people who work on construction projects of a
statutory right” to a mechanic’s lien.”
At a subsequent hearing on Bullock’s request to enforce its
lien, Bovis argued the lien waiver provision of the contract
nevertheless precluded Bullock from filing a lien.
The trial court refused to enforce the lien waiver provision,
however, because it found that public policy prohibited lien waiver
clauses.
In reviewing the question of whether contractors
may be required by contract to waive their statutory rights to a
mechanic’s lien, the court had to decide whether to follow it previous
precedent in the case of Dayside
v. District Court. In
that case, the court had held that absent a prohibitive legislative
proclamation, a waiver of mechanic’s lien rights is not contrary to
public policy and will be enforced if it is clear and unambiguous.
In overruling that previous precedent, the Bovis
decision states: “Because Nevada’s public policy favors
contractors’ rights to secure payment, [and] because Dayside removes
public policy from the analysis of the enforceability of particular lien
waiver provisions, we now overrule Dayside and conclude that it is
appropriate for the district court to engage in a public policy analysis
particular to each lien waiver provision that the court is asked to
enforce.” In this
case, because the lien waiver applied regardless of whether Bullock
Insulation received any payment, the court held that the waiver
provision violates public policy. The
court then turned to the pay-if-paid clause (which predated state
legislation that currently declares such clauses unenforceable), and
found that even without the current legislative prohibition, the clauses
violated public policy and could not be enforced against Bullock.
________
Article
4
__________
Plan Drafter
Penalized for Practicing Architecture without a License
An individual that drafted plans and specifications
for a strip shopping center was fined by a stated board of architect
examiners for practicing architecture without a license.
The individual appealed the Board decision to court, arguing that
since the building for which he prepared design plans was never built,
he did not practice architecture within the meaning of the state statute
definition of the term. The
court affirmed the penalty and held that it did not matter whether or
not the building was built since it was the intent of the statute of
safeguard public safety and prevent waste “by prohibiting activities
that are undertaken in contemplation of erecting buildings.”
The court held that “the state logically need not wait until
the erection actually occurs” before making a determination that an
individual has practiced without a license.
In Davis v.
Board of Architect Examiners, 193, P.3d 1019 (Oregon, 2008), the
court of appeals affirmed a decision by the Oregon Board of Architect
Examiners that imposed a civil penalty of an individual that was doing
business under the name of “Coast Drafting and Design.”
Although no employee of Coast was licensed as an architect, the
firm advertised itself as available to produce designs.
In response to an advertisement, a builder/developer company
contracted with Coast to create preliminary plans for a strip shopping
center it was planning to build. Preliminary
plans were defined by contract as being sufficient to create “a final
floor plan and elevations.”
According to the court, Coast Drafting and Design
provided three proposals with completed drawings, one set which was
selected by the builder which then entered into another contract with
Coast by which Coast would provide the following services:
“1. Provide
permit ready drawings for a two (2) story, wood frame retail strip
center …
2. Incorporate
civil and structural drawings, done by others, into the work drawings.
3. Periodic
site visits and reports to Client during course of construction.
4. Provide
reproductions of drawings as follows, 20 sets Preliminary Drawings for
Site Plan Review, and 12 Sets Final Working Drawings.”
Coast thereafter produced floor plan drawings
showing two levels of building units with square footage.
The court states these drawings were “stamped by petitioner.”
Coast and the builder then
submitted additional drawings to the city planning director who approved
them. Subsequently, Coast
drafted more detailed plans that included framing plans and section
details. These were stamped
by Coast and an “engineering firm with which [it] had
subcontracted.” The court
does not specifically say so, but this appears to be the first instance
in which plans drafted by Coast were stamped by a licensed professional
– and it appears that the stamp is as to engineering aspects of the
documents only.
Coast did not deny that it had produced plans and
designs for the building. Instead,
it argued that the statutory definition of architect services does not
encompass planning and designing buildings that are never erected.
In rejecting that argument, the court found that Coast’s
proposed definition could not be reconciled with the plain text of the
statute that provides that the practice of architecture includes
“planning” or “designing” the “erection” of “any
building.” As explained by the court, “One plans the erection of a
building or executes designs for it regardless of whether the plans or
designs ever come to fruition.”
________
Article
5
__________
No Coverage
in Homeowner’s Policy for Mold Damage from Water Pipe leak
Where a homeowner sought to recover under its
homeowner’s policy for mold damage that occurred from water from a
burst pipe, the insurance carrier denied the claim on the basis of a
mold exclusion in the policy. The homeowner filed suit against the
carrier seeking a declaratory judgment that the policy covered mold.
The trial court found that the mold damage was subject to an
clearly worded, and broad exclusion that specifically addressed mold.
Mold was excluded from coverage even if it resulted from an
otherwise covered event such as a water line break.
In DeVore v.
American Family Mutual Insurance, 891 N.E.2d 505 (Ill. App. 2008),
the homeowner appealed from the trial court’s judgment.
The appellate court affirmed that there was no coverage based
upon a careful review and analysis of the policy exclusion that included
a discussion of decisions by other state jurisdictions that have found
coverage for homeowners under similar language.
Quoting from the policy, the court stated: “The
policy does not cover ‘a loss to the property *** resulting directly
or indirectly or caused by *** mold.’ “ In addition, the policy
provided: that “[s]such loss is excluded regardless of any other cause
or event contributing concurrently or in any sequence to the loss.’”
The court stated: “We do not understand how much clearer
American Family could have been in excluding coverage relating to an
event such as this one, wherein water caused damage to a home and
created mold in the home.”
The homeowner argued that the trial court should
have recognized a distinction between mold that results from an
otherwise covered event and mold that results from some other source or
event. Courts in some
jurisdictions have recognized such a distinction.
According to the homeowner, the mold damage was not a loss
excluded under the policy since it was damage caused by a covered loss.
A case cited by the homeowner in support of that proposition is
an
Arizona
case of Liristis v. American
Family Mutual Insurance Co., a case which interestingly enough
addressed the exact same exclusionary language from the same insurance
company’s policy.
In Liristis,
the homeowner sought coverage for mold that grew after a house fire was
extinguished with water. The
Arizona
court held that “mold damage caused by a covered event is covered
under the American Family policy… On the other hand, losses caused by
mold may be excluded.” The
court reasoned that the exclusion language:
“[D]oes not exclude all mold. Rather, it excludes loss
‘resulting directly or indirectly from or caused by’ mold. If
American Family had intended to exclude not only losses caused by mold
but also mold itself, it could have easily expressed that intention. * *
* If American Family had added the words ‘either consisting of, or
...’ to its exclusionary language, then loss ‘consisting of’ mold
as well as loss caused by mold would be subject to this restrictive
language.”
The
Illinois
appellate court in the DeVore
case stated: “We respectfully reject this reasoning.”
The court went on to explain that it found the language of the
exclusion is ‘clear and unambiguously indicates that a loss from mold
from any cause at any time is excluded.”
“The losses in this case were twofold:
(1) water damage; and (2) mold damage.
Under the plain terms of the policy, the former was covered and
the latter expressly was not.” For
these reasons, the court held in favor of the insurance company to
exclude coverage for mold.
Comment:
The issue of whether the otherwise clearly stated
mold exclusion is ambiguous when it comes to addressing mold that arises
from an otherwise covered event is a question that continues to be
litigated in various jurisdictions – with surprisingly different
results as seen here between Arizona and Illinois.
In the view of this author, the reasoning of the
Illinois
court excluding coverage provides the more reasonable interpretation of
the policy language. As
suggested by the
Illinois
court, the
Arizona
decision is not “well-reasoned.”
The
Arizona
court did linguistic gymnastics to create a convoluted interpretation of
the policy to hold that “only losses caused by mold” are excluded,
but that the actual “mold” in and of itself is not excluded. To
reach that conclusion, the court must have affirmatively chosen to
ignore what the Illinois court calls the “plain, ordinary, popular
meaning” of the policy language, in perhaps a subconscious effort to
rewrite the contract to make it read the way it would prefer to have it
applied to help out the homeowner. The
Illinois
court, in contrast, chose to honor the obvious intent of a contract
(insurance policy).
Litigation abounds, and is increasing, in large
part due to the failure of judges to apply the written contracts and
established statutory law and case precedent to the cases brought before
them. Because
plaintiffs realize they may find a court friendly to their own tortured
reasoning, they are encouraged to bring suits based on ever more
creative theories. Society as a whole loses as result of this.
_________________
About the author: All articles
in this issue of the ConstructionRisk.Com
Report, unless specially stated others, are written by J. Kent Holland is a construction lawyer
located in Tysons Corner, Virginia,
with a national practice (formerly with Wickwire Gavin, P.C. and
now with Construction Risk Counsel, PLLC) representing design
professionals, contractors and project owners. He is founder and
president of a consulting firm, ConstructionRisk, LLC, providing
consulting services to owners, design professionals, contractors and
attorneys on construction projects. He is publisher of
ConstructionRisk.com Report and may be reached at Kent@ConstructionRisk.com
or by calling 703-623-1932. This article is published in
ConstructionRisk.com Report, Vol. 11, No. 6 (January 2009).
=====================================
ABOUT THIS NEWSLETTER & A DISCLAIMER
This newsletter Report is published and edited by J. Kent Holland,
Jr., J.D. The Report is independent of any insurance company,
law firm, or other entity, and is distributed with the understanding
that ConstructionRisk.com, LLC, and the editor and writers, are not
hereby engaged in rendering legal services or the practice of law.
Further, the content and comments in this newsletter are provided for
educational purposes and for general distribution only, and cannot apply
to any single set of specific circumstances. If you have a legal issue
to which you believe this newsletter relates, we urge you to consult
your own legal counsel. ConstructionRisk.com, LLC, and its writers and
editors, expressly disclaim any responsibility for damages arising from
the use, application, or reliance upon the information contained herein.
Copyright 2009, ConstructionRisk, LLC
Publisher & Editor:
J. Kent Holland,
Jr., Esq.
1950
Old Gallows Rd
Suite 750.
Vienna
,
VA
22182
703-623-1932
Kent@ConstructionRisk.com
_____________________________________________
|