|
ConstructionRisk.com Report
http://www.ConstructionRisk.com
Vol. 11, No. 7, July 09
______________
Inside
This Issue:
• New
OSHA Policy is Upheld – Rendering Prime
Contractors Responsible for Hazards Created by their Subcontractors;
• Faulty
Workmanship Arising from Subcontractor Work is Covered by a CGL Policy;
• Huge
Penalty for False Claim is Enforced , and Forfeiture of Entire
Contractor Claim is Affirmed;
• Architect
Failed to Prove Developer Infringed its Copyrighted Plans;
• Corporate
Veil Cannot be Pierced as Part of Supplementary Proceedings After
Judgment was Rendered Only Against Architectural Corporation .
======================================
_________
Article
1
__________
New OSHA Policy is Upheld – Rendering Prime Contractors
Responsible for Hazards Created by their Subcontractors
J. Kent Holland, Jr.
OSHA is permitted, under its new “controlling
employer citation policy,” to issue citations against employers for
safety violations even if their own employees are not exposed to any
hazards related to the violations. The
U.S. Court of Appeals for the Eighth Circuit held that the applicable
section of the Code of Federal Regulations does not prohibit application
of an employer’s safety responsibility to employees of other employers
such as its subcontractors. To
the extent that the regulation may have been ambiguous with regard to
whether it could be applied to allow OSHA to cite a prime contractor for
the failure of its subcontractors to protect the subcontractor
employees, the court stated it was required to defer the Agency’s
reasonable interpretation of its own regulation.
The key finding of the court was that the regulation, as
reasonably interpreted by OSHA, does not preclude imposing a duty on
employers to protect the place of employment, including others who work
at the place of employment, so long as the employer also has employees
at that place of employment.
In Solis v.
Summit Contractors, 558 F.3d 815 ( 8th Cir. 2009), the
issue on review was whether the Secretary of the Department of Labor’s
new multi-employer worksite policy for “controlling” employers
(“Controlling employer citation policy”) violated agency regulation
29 CFF 1910.12 (a). The new
policy provides that the Occupational Safety and Health Administration
(OSHA) may issue citations to general contractors at construction sites
who have the ability to prevent or abate hazardous conditions created by
subcontractors through the reasonable exercise of supervisory authority
regardless of whether the general contractor created the hazards or
whether the general contractor’s own employees were exposed to the
hazard. “
The OSH Act at 29 USC 654 (a) states that “Each
Employer (1) shall furnish to each of his employees employment and a
place of employment which are free from recognized hazard that are
causing or are likely to cause death or serious physical harm to his
employees.” Subparagraph
(2) of this section states that the Employer “shall comply with
occupational safety and health standards promulgated under this
chapter.”
According to the court, “Subsection (a)(1)
creates a duty running only to any employer’s own employees, while
subsection (a)(2) creates a specific duty to comply with standards for
the good of all employees on a multi-employer worksite.”
The original multi-employer worksite policy of OSHA provided that
OSHA could cite employers who exposed their own employees to hazardous
conditions or who created a hazardous condition “endangering
employees” whether or not those employees were his own or those of
another employer at the site.
OSHA initially applied a narrow interpretation of this policy.
With the adoption of the new multi-employer worksite policy,
however, OSHA is applying a much broader interpretation of the
regulation to permit it to cite employers who have the ability to
“control” the worksite even if they did not “create” the hazard
or “expose” the worker to the hazard.
The key regulation at issue in this dispute is 29
CFR 1910.12(a) which provides:
“The standards prescribed … shall apply … to every
employment and place of employment of every employee engaged in
construction work. Each
employer shall protect the employment and places of employment of each
of his employees engaged in construction work by complying with the
appropriate standards prescribed in this paragraph.”
The facts giving rise to this case are these.
Summit Contractors was the general contractor for the
construction of a college dormitory.
It subcontracted the entire project and had only four of its own
employees at the site as project superintendants.
On two or three occasions
Summit
observed the subcontractor’s employees operating without personal fall
protection on scaffolds that lacked guardrails. General contractor’s
superintendant advised the subcontractor to correct the problems.
But each time the subcontractor moved it scaffolding to another
location on the site, the employees would once again work without the
fall protection.
When the OSHA Compliance Officer saw the laborers
working without fall protection or guardrails he issued a citation not
only to the subcontractor, but also to the prime contractor (
Summit
) on the basis of the new policy for “controlling employer”
responsibility.
Summit
contested the citation, arguing that 29 CFR 1910.12(a) places a duty on
employers to protect only its own employees, not those of any
subcontractor. In evaluating
whether OSHA acted within its appropriate discretion in interpreting the
regulation as it did, the court concluded that there are two distinct
parts to the quoted regulation. The
first part of 1910.12(a) applies to an employer’s duty to protect its
own employees. The second
part of the paragraph, however, states that the employer is “to
protect the places of employment” where the employer actually has
employees. This is broad
enough, says the court, that “the plain language of part (2) does not
preclude an employer’s duty to protect the place of employment,
including others who work at the place of employment, so long as the
employer also has employees at that place of employment.”
For these reasons, the court held that OSHA may
continue to implement its new “controlling employer citation policy”
to issue citations against “controlling employers” such as prime
contractors that have neither created the hazard or exposed their own
employees to any hazard.
Comment:
Summit
, the prime contractor, was supported in this appeal by a number of
trade associations that believe this is an ill-conceived policy as well
as contrary to law. These
included Associated General Contractors of
America
, National Association of Home Builders, Associated Builders and
Contractors, National Federation of Independent Business Legal
Foundation, Contractor’s Association of Greater New York, Texas
Association of Builders, and Greater Houston Builders Association.
They argued that the controlling employer citation policy is
counterproductive to the goals of the OSH Act.
What potential benefits, they ask, can be gained in citing both a
subcontractor and the general contractor that had informed the
subcontractor of the violation on several prior occasions?
They argued that although the general contractor plays a role in
setting safety standards at worksites, “OSHA is an intricate and
function-specific regulatory regime such that each employer on a
worksite may be uniquely situated to know of the very specific
regulatory requirements affecting its particular trade.
The new policy places an enormous new responsibility on a general
contractor to monitor all employees and all aspects of a worksite (and
apparently take direct action to prevent unsafe conditions that it did
not itself create. The
court’s response to these philosophical arguments was to state
“These policy concerns should be addressed to Congress or to the
Secretary and not to the courts.”
Unfortunately, in the current political environment it would
appear unlikely that Congress would grant any relief or that the
Department of Labor would revise its regulation – regardless of how
sensible it might be to do so.
About the author: All articles
in this issue of the ConstructionRisk.Com Report are written by
J. Kent Holland, a construction lawyer located in Tysons Corner,
Virginia, with a national practice (formerly with Wickwire Gavin,
P.C. and now with Construction Risk Counsel, PLLC) representing design
professionals, contractors and project owners. He is also founder
and president of ConstructionRisk, LLC, a consulting firm providing
consulting services to owners, design professionals, contractors and
attorneys on construction projects. He is publisher of
ConstructionRisk.com Report and may be reached at Kent@ConstructionRisk.com
or by calling 703-623-1932. This article is published in
ConstructionRisk.com Report, Vol. 11 No. 7 (July 2009).
__________
Article
2
__________
Faulty
Workmanship Arising from Subcontractor Work is Covered by a CGL Policy
Claims of faulty workmanship against a builder were
held to be claims for “property damage” covered by a Commercial
General Liability (CGL) policy. The
“actual-injury” rule was applied by the court to find that since
actual physical damage to property occurred during the policy period,
the CGL policy during that period of time would cover the damage.
Several homeowners sued the contractor for construction defects
related to the Exterior Insulation and Finish System (EIFS) that they
alleged caused water damage to their homes.
An additional homeowner sued the contractor for alleged water
damage due to improper design and construction of columns and a balcony.
The contractor tendered defense of the claim to its insurance
carriers who denied any duty to defend.
An EIFS exclusion in the policy was the basis for one of the
carriers denial of any duty to defend and an intermediate appellate
court affirmed summary judgment in favor of that carrier. As
to the other carrier that did not have an EIFS exclusion, however, the
court found a duty to defend the contractor against the four homeowner
suits that alleged subcontractor installation defects caused their
alleged damage.
In Pine Oak
Builders v. Great American Lloyds Insurance, 279 S.W.3d 650 (Tex.
2009), the Supreme Court of Texas reviewed the CGL policies and the
allegations contained in the plaintiff’s complaint to determine
whether those allegations fell within the policy and required the
insurance company (Great American Insurance) to have a duty to defend
the contractor. Great
American argued that the faulty workmanship claims did not alleged
“property damage.” The
court held that pursuant to the case law established in Lamar
Homes v. Mid-Continent Casualty, 242 S.W.3d 1 (Tex. 2007), faulty
workmanship claims against contractors are claims for property damage
caused by an occurrence under a CGL policy.
Next the court considered the question of what
triggers coverage under a CGL policy.
The homes in question were built in 1996 and 1997.
The Great American policies were written to cover one year
consecutive periods from April, 1993 through April 2001.
Great American argued that the date the damages were manifested
is the date that triggers the policy.
Since that did not occur during the time that Great American
Insured the contractor, it argued it had no duty to the contractor.
The court disagreed and held that it would follow the “actual
injury rule” . . . “under which property damage occurs during the
policy period if ‘actual physical damage to the property occurred’
during the policy period.” The
key date, says the court, “is when injury happen, not when someone
happens upon it.” Quoting
from another case, the court says the key focus should be “when damage
comes to pass, not when damage comes to light.”
Applying that principal, the court found that property damage
occurred under the Great American policies “when a home that is the
subject of an underlying suit suffered wood rot or other physical
damage.”
How the “your work” exclusion applies to bar the claim for
defects in the balconies.
Four of the homeowner suits alleged on the face of
their complaints that the damages related to EIFS were caused by
subcontractors working for the prime contractor with whom they had their
contracts. These allegations
of subcontractor fault pulled the complaint out from under the “your
work” exclusion since there is an exception to that exclusion for work
that is performed by subcontractors in contrast to work that is
performed by the insured contractor itself.
The fifth lawsuit, however, did not allege subcontractor fault as
the basis of the claims against the contractor for defective columns and
balconies. On the face of
the complaint, the allegations alleged that the prime contractor itself
was at fault for the alleged defective work.
As stated by the court, that complaint did not accuse any
subcontractor of defective work or other legally actionable conduct, nor
allege that the prime contractor was liable under any theory for the
conduct or work of its subcontractor.
The complaint did not allege negligent supervision of a
subcontractor or any other third party.
It alleged only that the prime contractor was liable for its own
actionable conduct. As such,
the “your work” exclusion to coverage under the GCL policy must be
applied, concluded the court, to deny any duty to defend.
The contractor sought to present extrinsic evidence
(evidence outside the four corners of the plaintiff’s complaint) to
argue that it was the subcontractor’s work that caused the alleged
defects in the columns and balconies at issue.
In rejecting consideration of such extrinsic evidence, the court
explained: “The policy imposes no duty to defend a claim that might
have been alleged but was not, or a claim that more closely tracks the
true factual circumstances surrounding the third-party claimant’s
injuries but which, for whatever reason, has not been asserted.
To hold otherwise would impose a duty on the insurer that is not
found in the language of the policy.”
For these reasons, the court held the carrier had
no duty to defend the suit concerning the balconies that alleged on
prime contractor defects in workmanship, and it held the carrier hade a
duty to defend the four EIFS claims arising out of alleged subcontractor
defective workmanship.
_________
Article
3
__________
Huge
Penalty for False Claim is Enforced , and Forfeiture of Entire
Contractor Claim is Affirmed
Court of Fed Claims Affirmed decision in Daewoo
Engineering and Construction
v. U.S. holding that where contractor sued government for $64
million based on alleged defective specifications and impossibility of
performance, the lower court did not err in finding that $50 million of
the claim was fraudulent and that the government was entitled to assess
a $ a $50 million penalty
under the Contract Disputes Act plus a 10,000 penalty under the False
Claims Act. Since the
court upheld the penalty it also concluded that the lower court was
correct in finding under 28 U.S.C section 2514, that the contractor’s
entire claim, including any part of the claim that might not have been
fraudulent, is forfeited.
The court stated that unlike the antifraud provision of the
Contract Disputes Act, 41 USC, sec. 604, under which a contractor may
incur liability only for the unsupported part of a claim, the forfeiture
under 28 USC 2514 requires only part of the claim to be fraudulent in
order to find that the entirety of the contractor claim is forfeited.
In the case of Daewoo
Engineering and Construction Co., Ltd v.
United States
, 557 F.3d 1332 (Fed. Cir., 2009), the U.S. Court of Appeals for the
Federal Circuit, the matter concerned a certified claim by Daewoo in the
form of a request for equitable adjustment (REA) seeking adjustment of
the contract price and time to perform its contract to build a 53 mile
road. The REA alleged that
the contract used defective specifications, that the government breached
its duties to cooperate and to disclose superior knowledge, and that the
contract was impossible to perform within the originally specified time
period. When the contracting
officer denied Daewoo’s claim, Daewoo filed a complaint with the Court
of Federal Claims seeking an increase in monetary relief in the amount
of approximately $64 million.
The government counterclaimed for damages, seeking
$64 million under the Contract Disputes Act (CDA) and $10,000 under the
False Claims Act. The
government also entered a special plea in fraud and sought forfeiture of
Daewoo’s claims under 28 USC 2514.
The Court of Federal Claims found in favor of the government on
all the issues. In
affirming that decision, the court of appeals started with an
explanation of the antifraud provision of the Contract Disputes Act, 41
USC 604, “[i]f a contractor is unable to support any part of his claim
and it is determined that such inability is attributable to
misrepresentation of fact or fraud on the part of the contractor, he
shall be liable to the Government for an amount equal to such
unsupported part of the claim.”
Under 41 USC 601(9) A “misrepresentation of fact” is “a
false statement of substantive fact material to proper understanding of
the matter in hand, made with intent to deceive or mislead.”
The lower court held that Daewoo “filed at least
$50 million of the [$64 million certified] claim in bad faith”.
In challenging the lower court’s penalty assessment under the
CDA, Daewoo argued on appeal that its certified claim was neither a
claim for $64 million under the CDA nor was it fraudulent.
The contractor also argued that even if the claim was in part
fraudulent, it was not fraudulent to the full extent of $50.6 million.
What was fraudulent about the claim according to
the trail court was the project cost calculation used by the contractor.
The court did not find Daewoo’s theories of the government’s
breach of contract to be fraudulent – although it ultimately found
these theories to be without merit.
The problem with the calculation according to the court was that
it “assumed that the government was responsible for each day of
additional performance beyond the original 1080-day contract period,
without even considering whether there was any contractor-caused delay
or delay for which the government was not responsible.
The calculation then simply assumed that Daewoo’s current daily
expenditures represented costs for which the government was
responsible.”
Moreover, stated the appellate court, “Daewoo
apparently used no outside experts to make its certified claim
calculation, and at trial made no real effort to justify the accuracy of
the claim for future costs or even to explain how it was prepared.”
The court stated that, at the trial, Daewoo’s experts on
damages “treated the certified claim computation as essentially
worthless, did not utilize it, and did not even both to understand
it.” The trial court
consequently found that the certified claim was simply a “negotiating
ploy,” and that Daewoo “did not honestly believe the Government owed
it the various amounts stated when it certified the claim.”
The trial court found the entire $64 million calculation likely
was fraudulent, but it assessed only a $50.6 million penalty because it
thought the remaining $13 million incurred costs could have been
ultimately supported by alternative methodologies.
The appellate court understood Daewoo’s argument
to be that a claim can be fraudulent only if it rests upon false facts
rather than on a baseless calculation.
The court disagreed. It
explained that since the
claim by Daewoo was certified under 41 USC 605(c)(1) it was required to
be made in good faith and be supported by data that are accurate and
complete. The claim by
Daewoo was found to be baseless and therefore fraudulent.
For these reasons, the court sustained the $50.6 million penalty
under the CDA.
A certified claim may be a source of liability
under both the CDA and False Claims Act.
The trail court did not find that the government incurred actual
damages from Daewoo’s false claim.
It, therefore, assessed
only the statutory penalty of $10,000 under the False Claims Act
-- in addition to the much larger penalty under the CDA.
Finally, the appellate court affirmed the trial
court decision that the government “showed by clear and convincing
evidence that [Daewoo] knowingly presented a false claim with the
intention of being paid for it” and thus that Daewoo’s claims
against the government were forfeited under sec. 2514.”
Consequently, even if Daewoo could have documented and supported
the bases for the $13 million portion of its claim that might have had
merit, the court held that this claim was forfeited.
_________
Article
4
__________
Architect Failed
to Prove Developer Infringed its Copyrighted Plans
At a bench trial, a court considered evidence in a
complaint by an architect against a project developer alleging that the
developer had infringed the architect’s copyrighted drawings.
The court found that (1) although the architect discussed ideas
for the house plans with the developer and even provided the
developer’s attorneys with copies of his plans, the developer didn’t
have access to the architect’s plans; (2) the developer’s ultimate
plans were not strikingly
similar to those of the architect; (3) the developer had provided a
sketch of its conceptual ideas for the project to the architect as well
as to the ultimate architect – and it was this sketch that was the
common source for both firm’s copyrighted plans; (4) testimony by a
lay witness with no personal knowledge of the facts of the case was
excluded from evidence because it is the responsibility for the trier of
fact (judge in this case) to decide form himself whether the plans were
substantially similar and lay witness testimony attempting to give an
opinion on that is of no benefit to the court.
This was affirmed on appeal to the U.S. Court of Appeals, 10th
Circuit.
In La
Resolona Architects v. Reno, Inc., 555 F.3d 1171 (10th
Cir., 2009), the court of appeals explained
that there are two elements to
a copyright infringement claim: (1) proof of ownership of a valid
copyright and (2) proof that the defendant copied constituent elements
of the work that are original. The
plaintiff would thus have to prove that portions of its work were copied
and that those elements of the work that were copied were “protected
expression and of such importance to the copied work that the
appropriation is actionable.”
In this case, although the architect couldn’t directly prove
the defendant had access to its drawings, it might nevertheless
indirectly prove access if it could demonstrate that the copyrighted
work and the alleged infringing work are “strikingly similar.”
Courts have endorsed the legal principle under which a plaintiff
may establish factual copying without any proof of access to the
drawings when the similarity of the works is sufficiently striking such
that copying can be inferred solely on that basis.
The trial court concluded
that the plans were not strikingly similar to each other.
The appellate court saw no reason to find err in that decision
wherein the trial court found “major differences in the kitchen area,
living area, master bath and roof slope, placement of doors, placement
of plumbing, [and] placement of door openings, all of which affect
traffic-flow and articulation of space.”
The trial court also reasoned that “these differences so
outweigh any similarities that the similarities are inconsequential
within the total context of the work.”
Moreover, the court found that the similarities between the plans
were explained by the fact that both sets of plans were derived from one
common source – the defendant/developer who had provided both
architects with a sketch showing what he had in mind for the houses.
_________
Article
5
__________
Corporate Veil
Cannot be Pierced as Part of Supplementary Proceedings After Judgment
was Rendered Only Against Architectural Corporation
After a plaintiff obtained judgment against an
architectural firm for breach of contract, it learned during
post-judgment, supplementary proceedings, that the firm had no assets
from which to collect the judgment.
It also obtained evidence that arguably could serve as a basis to
pierce the corporate veil and hold the sole shareholder of the firm
individually liable on the basis that the corporation was merely the
architect’s alter ego. The
plaintiff then filed a motion with the trial court to pierce the
corporate veil and impose personal liability on the individual
architect. The trial court
granted the motion. In
reversing that decision, the appellate court held that post-judgment
supplementary proceedings cannot be used to reopen a matter and hold a
third party liable under a corporate veil piercing theory.
In Green v.
Ziegelman, 282 Mich. App. 292 (2009), the court focused on the
misuse of the supplementary proceedings as the basis for its reversal,
but it also noted that the architect argued that plaintiffs failed to
satisfy the compulsory joinder rule by not joining a claim for breach of
the architectural agreement, predicated on piercing the corporate veil,
against the individual architect. The
architect also argued that res
judicata barred entry of the judgment against the individual
architect. Both of these
arguments seem solid, but
the court did not specifically rely on them or even address them since
it based its reversal entirely on the manner in which supplemental
proceedings are intended to be used.
Comment:
An interesting aspect of this case is that there was
apparently no professional liability insurance available to satisfy the
judgment that had been granted against the architectural firm.
This may have been because of the nature of the claim – being
for breach of an operating agreement between the architect and the
developer of which the architect had a co-interest in the developer and
the project. The issue in
dispute did not appear to be based on allegations of negligent
performance of professional services.
=====================================
ABOUT THIS NEWSLETTER & A DISCLAIMER
This newsletter Report is published and edited by J. Kent Holland,
Jr., J.D. The Report is independent of any insurance company,
law firm, or other entity, and is distributed with the understanding
that ConstructionRisk.com, LLC, and the editor and writers, are not
hereby engaged in rendering legal services or the practice of law.
Further, the content and comments in this newsletter are provided for
educational purposes and for general distribution only, and cannot apply
to any single set of specific circumstances. If you have a legal issue
to which you believe this newsletter relates, we urge you to consult
your own legal counsel. ConstructionRisk.com, LLC, and its writers and
editors, expressly disclaim any responsibility for damages arising from
the use, application, or reliance upon the information contained herein.
Copyright 2009, ConstructionRisk, LLC
Publisher & Editor:
J. Kent Holland,
Jr., Esq.
1950
Old Gallows Rd
Suite 750.
Vienna
,
VA
22182
703-623-1932
Kent@ConstructionRisk.com
_____________________________________________
|