Contractor Cannot Recover for Extra Work Performed without Change Order Approved by Authorized Officials
ConstructionRisk.com Report Vol. #14, Issue #2
See article in the following topic indices:
Apparent Authority,Change Orders,Contract - Notice Requirements,Design-Build,Estoppel,Implied Contract,Quantum Meruit,Unjust Enrichment
Email this page to a friend:
A design-build contractor that entered into a fixed-price contract to upgrade the heating, air conditioning and ventilation (HVAC) system in college dormitories satisfactorily performed all the work it was contracted to do, but also performed significant additional work to correct problems with the existing HVAC system that had not been identified at the outset of [...]
Email this page to a friend:


