Subcontractor forfeits right to arbitration by filing demand untimely

See article in the following topic indices:
,,,, 

Email this page to a friend:

Where a subcontract required subcontractor to commence arbitration proceedings no later than 30 days following receipt of an adverse decision by the contractor, the failure of the subcontractor to contest a decision within 30 days was fatal to later seeking arbitration. Holt, a drywall subcontractor, entered into a contract with Choate, the general contractor, to [...]

Email this page to a friend:

Using Negotiation, Mediation and Arbitration to Resolve Construction Disputes

See article in the following topic indices:
, 

Email this page to a friend:

By Allan H. Goodman If a dispute arises during construction of your project, do not proceed immediately to court! Your contract may require you to use alternative dispute resolution (ADR) techniques such as negotiation, mediation or arbitration to resolve your disputes. You should therefore be familiar with these techniques. Negotiation is the most informal method [...]

Email this page to a friend:

Arbitration Consolidation was Inappropriate

See article in the following topic indices:
, 

Email this page to a friend:

Where a subcontractor submitted a claim against the general contractor for  payment, it submitted the matter to arbitration and the general contractor replied with a counterclaim in that arbitration and also initiated a third-party arbitration claim against a related subcontractor.  When the arbitrator ordered consolidation and permitted an indemnity claim between subcontractors the impleaded subcontractor [...]

Email this page to a friend:

Architect’s Decision Final where Contractor Failed to Satisfy Arbitration Filing Requirements

See article in the following topic indices:
,,, 

Email this page to a friend:

Where a contractor failed to comply with arbitration notice and filing requirements, the architect’s decision became final and binding, and the contractor had no further recourse to arbitrate or litigate its dispute with a homeowner. The AIA form contract that was at issue in the case of Martel v. Bulotti, 65 P.3d 192 (2003), provided [...]

Email this page to a friend:

Contractor Not Bound By Architect’s Decision on Claim

See article in the following topic indices:
,,, 

Email this page to a friend:

Contracts between owners and contractors often state that the contractor must submit any claim to the architect for final determination. Most contracts state that this must be done as a condition precedent to further review by a dispute resolution board or a court. But some contracts purport to eliminate any right of the contractor to [...]

Email this page to a friend:

$26.9 Million in Liquidated Damages Not a Windfall to Power Plant Owner

See article in Construction Risk Newsletter:
ConstructionRisk.com Report Vol. #12, Issue #3

See article in the following topic indices:
,,,,, 

Email this page to a friend:

On October 30, 2009, the DC Superior Court confirmed an August 17, 2009 arbitration award issued by a three-member arbitration panel in New Athens Generating Co. et al. v. Bechtel Power Corp. et al. The Panel awarded $26,950,000 in liquidated damages against the construction giant Bechtel Power Corporation, EPC contractor of a $533 million power [...]

Email this page to a friend: