Substantial completion not granted until fire alarm system is successfully tested

See article in the following topic indices:
,, 

Email this page to a friend:

Where the government took beneficial occupancy of a building after the scheduled completion date, it assessed liquidated damages against the contractor for late completion.  This was on the basis that until the contractor successfully tested the fire alarm system it had installed, the work was not substantially complete.  The contractor argued that the project was [...]