Contractor Suit Dismissed for Failure to Follow Claim Procedures of Contract

See article in the following topic indices:
,,,, 

Email this page to a friend:

A homebuilder’s lawsuit against a city and its architectural firm for refusing to grant change orders for additional costs was rejected by a court because the contractor failed to comply with a contractual requirement that it give written notice to the architect of its breach of contract claims against the city before initiating litigation. In [...]