Ambiguity in Design-Build Contract Specs Interpreted in Favor of Contractor
Ambiguous Specifications,Contra proferentem,Design-Build,Specifications (Defective)
Email this page to a friend:
by Michael C. Loulakis Record Steel and Construction v. United States , 62 Fed. Cl. 508 (2004), provides an excellent example of the evolution of design-build caselaw. The dispute in this case involved whether a design-build contract required foundations to be over-excavated. The design-builder argued that the contract unambiguously made over-excavation a design recommendation – [...]