A state court in California declined to enforce a “no-damage-for-delay” clause that would have deprived a construction contractor of equitable adjustment for time delays and expenses caused by the project owner, City of Los Angeles. The city had superior knowledge concerning site conditions which it withheld from the bidders. The city also impeded access to [...]