Differing Site Conditions and Lost Productivity Entitle Contractor to Additional Compensation
Change Orders,Damages,Differing Site Conditions,Lost Productivity,Reliance,site information reliance
Email this page to a friend:
A construction contractor was entitled to change orders where it encountered differing site conditions that required the use of form footings instead of trench footings as has been planned. The plans and specifications incorporated into the contract contained affirmative indications that the subsurface conditions would be consistent with the use of trench footings. The owner [...]