Risk of Differing Site Condition Not Shifted to Contractor

See article in the following topic indices:
,, 

Email this page to a friend:

Contract provisions requiring contractors to perform site investigation and inspection prior to bidding did not impose the risk of subsurface conditions on the contractor, and therefore, did not preclude a claim for equitable adjustment.  When the contractor began work it discovered a deep scour hole in the river bottom that prevented it from building cofferdams [...]