Failure to Request Change Order Bars Contractor Recovery for Excess Units
Change Orders,Notice Requirements,Unit Pricing,Unjust Enrichment
Email this page to a friend:
Contractor that performed significantly greater unit quantities of paving work than anticipated was barred from an equitable adjustment because although it adequately documented the increased quantities and costs, and the project owner was aware of the same, the contractor failed to submit a change order for approval by the owner in advance of incurring the [...]