|
ConstructionRisk.com Report
http://www.ConstructionRisk.com
Vol. 11, No. 6, June 09
______________
Inside
This Issue:
• Quantum
Meruit Recovery for Architect that Worked without a License;
• Limitation
of Liability Clause Unenforceable to protect Individual Professional;
• ADA
and FHA Bar Indemnification of Building Owner by Design Professional ;
• Economic
Waste Doctrine Prevents Owner from Recovering Excessive Damages from
Contractor;
• Time
Limit for Filing Suit Shortened by Contract Condition;
• Acceptance
Doctrine Bars Subsequent Claim against Contractor for Negligence
======================================
_________
Article
1
__________
Quantum
Meruit Recovery for Architect that Worked without a License
J. Kent Holland, Jr.
Where an Architect performed services for a project
in a state where it did not obtain a license until part way through the
time it was providing its services, the project developer asserted that
it didn’t have to pay for
the services because the architect lacked the required license.
It was held that the architect was entitled to paid on a quantum
meruit basis for the value of its services rendered after it
obtained its license, and that it was entitled to be paid on an unjust
enrichment basis for services it performed prior to obtaining its
license.
Since the original contract was signed before the
architect had the appropriate state license it was void.
The court found that once the architect obtained its license, the
services performed after that date were chronologically separable from
the illegal services and an “implied-in-fact” contract must be
recognized for services performed after that date, requiring payment to
the architect on a quantum meruit basis.
Quantum meruit permits recovery of the reasonable value of the
services rendered or the materials provided, regardless of whether a
party such as the developer was enriched by those services.
In contrast, the theory of “unjust enrichment” allows
recovery where a party such as the developer has received a benefit from
another that would be inequitable for that party to retain without
compensating the other for the value of the benefit.
In this case the court held that the architect may be entitled to
both types of relief.
In the case of Farrell
v. Whiteman, 200 P.3d 1153 (Idaho 2009), an architect licensed in
Michigan and one of his long-time friends (also from Michigan) decided
to join together in an undertaking to build a condominium project in
Idaho. The architect
understood that he and his friend the developer would be partners in the
project in exchange for his professional services to design the
building, secure the site plan approval, and oversee the construction.
No formal agreement or contract was ever reached.
At some point, the developer terminated the
architect from the project and refused to pay him anything for his
services even though the project was eventually completed and condo
units were successfully sold. The
developer claimed he owed the architect nothing because the architect
violated the state licensing law by performing without a license at
least at the outset of the services.
As explained above, the appellate court held that
the architect was entitled to be paid.
But the court disagreed with the reasoning of the trail court in
a couple key issues. First,
the court stated that the trial court went too far in interpreting the
state statute as only requiring architects to be licensed at “critical
times” during their performance. Instead,
the court concluded that architects must be licensed at “all times.”
Any services performed prior to the date of licensure would have
been performed pursuant to an illegal contract.
Consequently, there could be no quasi
contract or implied-in-fact contract for those services that would
entitle the architect to quantum meruit compensation for services
rendered before he was licensed. This
did not mean, however, that the architect should not be compensated for
those services, but instead that the trial court needed to evaluate a
different reason and method for determining the compensation –
specifically to consider the “unjust enrichment” theory.
The explanation of the court is as follows:
This case is one in which awarding
some damages is necessary to protect the public interest.
Although Farrell had an obligation to ensure that he was properly
licensed while he practiced architecture in
Idaho
, it would be contrary to the public interest to allow a developer to
avoid any payment for architectural services when the work performed was
sub-standard, the building was actually constructed, and several units
were sold. The architect
licensing statutes aim to protect buyers and the public-who lack
knowledge and expertise about architecture-from shoddy work and
untrained individuals posing as architects.
In this case, although Farrell was not licensed in
Idaho
for the entirety of his performance, he was a licensed architect in
another state. The district
court found that Farrell did not breach his duty of care, and that no
defects existed in the building Farrell designed.
Therefore, to leave the parties as the Court finds them would
result in a windfall to Whiteman [the developer], who obtained the
benefit of a trained and capable architect at zero cost.”
For these reasons, the appellate court remanded the
case back to the trial court to determine the amount to be awarded to
the architect.
About the author: All articles
in this issue of the ConstructionRisk.Com Report are written by
J. Kent Holland, a construction lawyer located in Tysons Corner,
Virginia, with a national practice (formerly with Wickwire Gavin,
P.C. and now with Construction Risk Counsel, PLLC) representing design
professionals, contractors and project owners. He is also founder
and president of ConstructionRisk, LLC, a consulting firm providing
consulting services to owners, design professionals, contractors and
attorneys on construction projects. He is publisher of
ConstructionRisk.com Report and may be reached at Kent@ConstructionRisk.com
or by calling 703-623-1932. This article is published in
ConstructionRisk.com Report, Vol. 11 No. 6 (June 2009).
__________
Article
2
__________
Limitation
of Liability Clause Unenforceable to protect Individual Professional
J. Kent Holland, Jr.
A
Florida
appellate court has found that the limitation of liability clause in a
contract between a design firm and its client cannot be applied to limit
the liability of an individual professional that is an employee of the
firm. “A cause of action
in negligence against an individual professional exists irrespective,
and essentially independent of a professional services agreement,”
says the court. A judgment
in excess of $4 million against an individual engineer was allowed to
stand because the court held the LoL in the design firm agreement did
not apply to actions directly against individual employees, and that
even if the clause were applicable to individual employees it would be
unenforceable as contrary to law.
In the case of Witt
v. La Gorce Country Club, Inc., 34 Fla.L. Weekly D1161a, the case
involved a law suit by a country club against G.M. Witt and Associates
(“GMWA”). The county
club entered into contracts involving the design and construction of a
reverse osmosis water treatment process for its golf course.
A design-build contract with ITT Industries was for the design
and construction of the treatment system.
The club entered into separate contracts with GMWA was for
hydrogeologic consulting services and overall project coordination.
The system suffered many problems and ultimately failed
completely.
The club filed suit against GMWA and its principal
employee, Mr. Witt, alleging malpractice, breach of contract, and fraud.
The trial judge determined that Witt and GMWA were liable for
professional malpractice – with the limitation of liability (LoL)
provision of the contract applying only to GMWA and not the employee.
In finding Witt personally liable but not protected by the LoL,
the trial court concluded:
This damage limitation is not
applicable to Witt’s liability for malpractice.
I find it is not applicable both because he was not a party to
the agreements and, therefore, not entitled to the benefit of any
limitation, and because [Moransais
v. Heathman, 744 So. 2d 973 (Fla. 1999)] … suggests that, ‘it is
questionable whether a professional, such as a lawyer, could legally or
ethically limit a client’s remedies by contract in the same way that a
manufacturer could do with a purchaser in a purely commercial
setting.”
The LoL clause in question provided as follows:
“In recognition of the relative
risks and benefits of the project to both La Gorce and [GMWA], the risks
have been allocated such that La Gorce agrees, to the fullest extent
permitted by law, to limit the liability of [GMWA] and its
subconsultants to the total dollar amount of the approved portions of
the scope of the project for any and all claims, losses, costs, damages
of any nature whatsoever or claims expenses from any cause or causes, so
that the total aggregate liability of [GMWA] and its subconsultants to
all those named shall not exceed the total dollar amount of the approved
portions of the Scope or [GMWA’s] total fee for services rendered on
this project, whichever is greater.
Such claims and causes include, but are not limited to,
negligence, professional errors or omissions, strict liability, breach
of contract or warranty.”
In refusing to apply the LoL clause to the action
against the individual, the court concluded that although there are no
Florida cases specifically addressing whether an LoL provision extends
to an individual professional, the Moransais
decision of the Florida Supreme Court would provide useful guidance to
suggest the clause would not apply because (1) the cause of action was
deemed by the court to be “extra contractual” in nature and (2) it
concluded that individual professional services by individuals such as
attorneys cannot limit their liability. (The court essentially equates
professional legal services and professional design services in this
regard). By finding the
plaintiff’s “cause of action in negligence against the individual
professional to exist irrespective, and essentially independent of a
professional services agreement,” the appellate court found the
“limitation of liability provision was, as a matter of law, invalid
and unenforceable as to Witt.”
Comment:
This is an unfortunate, and poorly reasoned decision.
As an initial matter, it should be noted that the court wrongly
applied the Moransais logic to the facts of this case.
Contrary to the court’s suggestion, lawyers and design
professionals are not treated the same when it comes to enforcing
limitation of liability provisions in contracts.
Attorneys are often prohibited by their Codes of Ethics and state
licensing laws from limiting their liability to their clients by way of
a limitation of liability provision.
Yet design professionals in many of those same states are
permitted to limit their liability.
It is also illogical to suggest that in the absence
of the contract that created a duty of the firm to the client, the
individual design professional would have owed any independent duty to a
client of the engineering firm for whom he was employed.
The engineering firm does not exist in a vacuum.
It exits only because it contains a number of individual licensed
design professionals working for it and on its behalf.
A firm cannot provide professional services without
individual licensed professionals. In this case the licensed
professionals worked within the scope of their employment for the
engineering corporation. They
were not acting ultra vires
– outside or contrary to their employment.
Their employer was fully responsible for their actions.
Any professional liability policy this employer had
would have not only insured the corporation, it would also insure each
employee acting within the scope of its employment.
The fact that insurance policy (contract) treats the corporation
and its employees as all part of the same “insured” further
demonstrates flaws in the court’s reasoning in which the court created
an artificial wall between the corporation and the individual.
If the LoL provision is enforceable to protect the
corporation, it must also be enforceable to protect the individuals
working for the firm. (Note:
An improvement to the LoL clause would have been to specifically
state that it applies to all principals, directors, officers, employees,
agents and servants of the firm. The absence of that language in this
case, however, was not an issue in the court’s reasoning, and does not
change the obvious intent of the clause).
By this terrible decision, the
Florida
court has once again demonstrated the extraordinary risk design
professionals assume when working in the state of
Florida
. This should strike
additional fear into the hearts of insurance underwriters considering
providing insurance for design professionals in
Florida
. For those underwriters
brave enough to try to help design professionals survive in such an
inhospitable environment by providing them coverage, it may be necessary
to raise premiums even higher than the heights to which
Florida
is already used to seeing. There
are unfortunate consequences to bad law.
_________
Article
3
__________
ADA
and FHA Bar Indemnification of
Building Owner by Design Professional
J. Kent Holland, Jr.
In litigation against a property owner alleging
violations of the Fair Housing Act (FHA) and Americans with Disabilities
Act (ADA), the owner settled litigation with the plaintiff, a non-profit
group that files suits to enforce the FHA and
ADA
. By settlement it agreed to
pay $1.4 million in damages, plus attorneys fees, costs and other
expenses. It also agreed to
survey and retrofit 71 properties to bring them into compliance with the
FHA and
ADA
. The owner then sought to
recover its damages from the architect pursuant to an indemnification
clause in the architect’s contracts.
The court held that the federal statutes prevented the owner
seeking indemnification under the theories of breach of contract and
professional malpractice -- alleging the firm specified incorrect
dimensions or other details in its construction documents.
The court granted the design firm’s motion for summary judgment
on the basis that under the FHA and
ADA
, the owner is barred from seeking indemnification or contribution
against the design firm.
In
Equal
Rights
Center
v. Archstone Smith Trust, 603
F.Supp. 814 (D.C. Md. 2009), the court cited a U.S. Supreme Court
decision of Northwest Airlines,
Inc. v. Transport Workers Union of America, for the proposition that
there can be no right to indemnification under the FHA or the ADA
because there is no expressed right under the statutes and there is no
evidence that Congress intended to create a private remedy.
Numerous federal court decisions are cited by the court as having
held that no claim for indemnity or contribution exists in connection
with liability under the two laws.
Since no federal law afforded Archstone the right
to indemnity or contribution against the design professional, Archstone
argued it was entitled to such remedy under state law.
Archstone argued that in addition to a statutory duty owed to the
plaintiffs, the designer had contractual and professional duties to the
defendant to design consistent with the FHA and
ADA
. In the face of breach of
those duties, Archstone argued that the designer should be liable to it
under state law for negligence and for breach of contract. In addition,
Archstone argued that under the express indemnification provisions of
its contracts with the design firm, indemnity was available as a
contractual duty. The
court rejected both of these arguments.
The court states that both the design firm and the
owner had non-delegable duties to design ADA/FHA compliant dwellings,
and that the design firm’s failure to fulfill its independent
obligation under the federal statutes subjects it to liability directly
to the plaintiffs on first-party claims under the FHA and
ADA
if claims were properly asserted. Nothing
in the federal law, however, would make the designer liable to Archstone
on a derivative indemnification claim based on the FHA or the
ADA
. As a
matter of law, the court also concluded that the state law claims for
breach of contract and professional negligence “are wholly derivative
of Archstone’s primary liability and are therefore what federal law
regards as de facto claims for indemnification. “Accordingly, those
state law claims are barred because any recovery by Archstone would
frustrate the achievement of Congress’ purposes in the FHA and
ADA
.”
In further explaining why the express
indemnification obligations in the design professional contract would be
unavailing to Archstone in this case, the court stated that the goal of
the statutes is to make each responsible party meet the purposes of the
laws. The court believed
those goals would be undermined if parties could “contract around’
their non-delegable duties imposed by statute by using indemnification
provisions of contracts with others.
Based on the court’s reasoning, it found that the
express indemnity claim based on the contract language “is barred by
federal law every bit as much as its implied indemnity claim is
barred.”
Risk
Management Note: This
decision should be carefully studied by design professionals and their
counsel to determine what it means to the enforceability of certain
contract terms and conditions.
Assuming the logic of this decision is adopted by other courts it
appears to mean that the design professional’s liability for ADA and
FHA violations is limited to the persons intended to be protected by the
laws, and that the design professional’s client cannot be indemnified
by the design professional for its share of damages for ADA and FHA
violations, regardless of what language is contained in the professional
services agreement.
In the
indemnity provisions of design professional contracts, attorney and
insurance professionals typically advise that indemnification by the
design professional be limited to damages actually caused by negligent
performance of services by the design professional. In
the “compliance with law” provision of design professional
contracts, design professionals are generally advised to agree only to
exercise the generally accepted standard of care to comply with laws,
codes, regulations, etc. (hereinafter “laws”).
The reasoning is that it is inappropriate and uninsurable for a
design professional to warrant or guarantee that its services will meet
the requirements of all laws.
Laws, ordinances, and regulations may be ambiguous,
or subject to more than one reasonable interpretation, or just so arcane
that not every reasonable person even knows that they apply, or how they
apply, to a situation. Instead
of assuring compliance with all laws, the design professional should
exercise reasonable care to comply.
Not every error or mistake is a negligent one.
It is important to remember, that professional liability
insurance only covers “negligent” acts, errors and omissions.
If liability is imposed and damages sustained by the design
professional to the third-party plaintiff due to its negligent failure
to comply with the ADA, FHA or other laws, there might be coverage for
some of the damages under the policy (although fines and
penalties will probably be excluded).
On the other hand, if the design firm was not negligent -- since
it met the standard of care in endeavoring (but yet failing) to comply
with the laws -- it would have no insurance coverage to cover losses
that its client might try to recover from it based on the design
firm’s broad-form (non-negligence based) indemnification or
unconditional promise/guarantee to comply with all laws.
_________
Article
4
__________
Economic
Waste Doctrine Prevents Owner from Recovering Excessive Damages from
Contractor
J. Kent Holland, Jr.
Where contractor built a house at 7.5 feet
elevation instead of the specified 8.5 feet, the home owner claimed he
was entitled to damages of almost $1 million to tear down the house and
rebuild it. The contractor
argued that the cost to cure the elevation defect was unreasonable and
that under the economic waste doctrine the proper measure of damages was
the diminution in the value of the home as a result of the lower
elevation. The trial court
and appellate court both agreed with the contractor that there was only
a “nuisance” diminution in value of $25,000 to which the homeowner
was entitled.
The court cited the Restatement of Contracts in
support of its decision, citing a comment in the Restatement as follows:
“The purpose of money damages is to put the injured party in as good a
position as that in which full performance would have put him; but this
does not mean that he is to be put in the same specific physical
position”…”Sometimes defects in a completed structure cannot be
physically remedied without tearing down and rebuilding, at a cost that
would be imprudent and unreasonable.” … “The law does not require
damages to be measured by a method requiring economic waste.”
Restatement (first) of Contracts, Sec. 346(1)(a), comment b.
The court rejected the homeowner’s argument that
the language in the contract barred application of the economic waste
doctrine. As explained by
the court, a standard form contract was used by the parties.
That contract provided that [t]he Contractor shall promptly
correct Work…failing to conform to the requirements of the Contract
Documents, whether observed before or after Substantial Completion, and
whether or not fabricated, installed or completed” and that [t]he
Contractor shall bear costs of correcting such rejected Work….”
The court rejected
the homeowner’s argument that this language constituted an
agreement to measure damages based upon a “cost to repair”, thereby
precluding the application of the economic waste doctrine.
The court explained its reasoning as follows: “This court must
employ a reasonable interpretation of the contract and the contract
language. Certainly, a more
explicit and specific provision would be required for this court to
conclude that the parties intended to contract away application of the
well-recognized economic waste doctrine.”
Heine v. Parent
Construction Company, 4 So.3d 790 (
Fla.
2009).
_________
Article
5
__________
Time
Limit for Filing Suit Shortened by Contract Condition
J. Kent Holland, Jr.
Motion to dismiss complaint against design
professional was correctly granted because, pursuant to the AIA form
contract, the applicable four year statute of
limitations period began, to run on the date of substantial
completion of project construction regardless of the fact that the
plaintiff may not have discovered its alleged injuries until later and
the limitations period would have otherwise run longer. Article 9.3 of
the AIA contract form was held to control the accrual date of the
applicable statute of limitations and precluded application of the
discovery rule that would have otherwise have permitted the plaintiff to
file its complaint four years after having discovered its injuries.
In Federal
Insurance Company v. Konstant Architecture Planning, Inc., 902 N.E.
2d 1213, 388
Ill
, Appl3d 122 (2009), the plaintiff sued for breach of contract with
respect to the design and building of a residence.
The contract contained the following provision concerning the
time limits on filing suit: “Causes
of action between the parties to this Agreement pertaining to acts or
failures to act shall be deemed to have accrued and the applicable
statutes of limitation shall commence to run not later than either the
date of Substantial Completion, or the date of issuance of the final
Certificate for Payment for acts or failures to act occurring after
Substantial Completion.”
The home was built and substantially complete in
1997. Water damage and
mold infestation resulting from water intrusion were discovered by the
homeowner in 2002, resulting in repair costs in excess of $300,000.
The homeowner’s insurance policy covered the cost. The
insurance company then sued the design professional to recover the
costs.
In order to avoid the applicability of the contract
language and the four year statute of limitations applicable to design
and construction, the plaintiff insurance company made two curious
arguments that were rejected by the court.
First the plaintiff argued that a 10 year statute of limitations
applied instead of the four year statute cited by the design
professional. It also tried
to argue that another section of the code established a 10 year statute
of repose actually worked to lengthen the time by which to file suit
against the design firm. The
court quickly disposed of that second argument concerning the statute of
repose as essentially nonsensical (although the court didn’t put it in
those succinct terms), since the statute was clearly intended to
establish an final end point by which suits against design firms must be
filed.
With regard to the 10 year statue of limitations,
the court said it is a general statute that applies,
to “actions on bonds, promissory notes, bills of exchange,
written leases, written contracts, or other evidences of indebtedness in
writing.”
This ten year statue did not apply to design and
construction, however, because as explained by the court, a separate
section of the state statute specifically prescribes a four year time
limit applicable to such suits. It
reads as follows: “Actions based upon tort, contract or otherwise
against any person for an act or omission of such person in the design,
planning, supervision, observation or management of construction, or
construction of an improvement to real property shall be commenced
within 4 years from the time the person bringing an action … know or
reasonably should have known of such act or omission.”
Plaintiff tried to argue that the state statute
should be read as “an organic whole” to make the 10 year statute
apply. In rejecting that
argument, the court followed the time-honored principle that the more
specific provision governs over the generalized provision.
Since a section was specific to design and construction, that
section of the law clearly applied to establish a 4 year time period for
filing suit.
With regard to cutting off the discovery period
that would have otherwise existed under the 4 year statute to extend the
time for filing suit, the court enforced the accrual date established by
the AIA contract document and explained, “When construing the language
of a contract, this court’s primary objective is to give effect to the
intent possessed by the parties at the time they entered the
agreement.” Because the
appellate court found there was nothing ambiguous about the contract
language, and nothing prohibited enforcing the language, it held that
the trial court correctly dismissed the complaint against the design
professional as untimely.
Risk
Management Note:
This case demonstrates the great value in including a clause in
the contract to establish a date certain (such as substantial
completion) for the statute of limitations to begin to run.
This eliminates the possibility of a plaintiff arguing that it
didn’t “discover” its injuries until many years after the building
was complete. It limits or
eliminates the discovery period that would otherwise exist under the
state statute. In the
absence of the contract clause in this case, the plaintiff could have
filed suit up until 10 years after substantial completion since the
state statute of repose had a 10 year time period.
________
Article
6
_________
Acceptance
Doctrine Bars Subsequent Claim against Contractor for Negligence
J. Kent Holland, Jr.
A construction company was sued by victims of a
serious car accident for alleged negligent construction of the road
where the accident occurred. Summary
judgment was granted, and affirmed, for the contractor on the basis of
the “acceptance doctrine” whereby if a contractor performs its
construction work consistent with someone else’s design and without
negligence, and the work is accepted by the owner,
the contractor is not subject to liabilities resulting from the
defective design of the work.
In the case of Bragg v. Oxford Construction Company, 674 S.E.2d 268, (GA 2009), a
county government contracted with the contractor to repave and overlay
asphalt patches on a road owned and maintained by the county.
An engineer who was employed by the County directed the
contractor to place a “spot overlay patch” on the area of the road
where the accident occurred. The
contractor followed the specific instructions and had no responsibility
for the design of the road. Nor did the contractor hold itself out as an
expert on road design. The
contractor did just what it was instructed to do by the County.
It was not negligent, and the County accepted the work when it
was completed. The
Georgia
“acceptance doctrine” was, therefore, found applicable to the
situation. In a dissenting
opinion, three of the justices stated that they believe the
underpinnings of the acceptance doctrine have been eroded and should be
abandoned. The majority opinion, however, re-affirmed the acceptance
doctrine generally as applicable in
Georgia
as proper common law that had been judicially created and never
rescinded or addressed by the legislature.
=====================================
ABOUT THIS NEWSLETTER & A DISCLAIMER
This newsletter Report is published and edited by J. Kent Holland,
Jr., J.D. The Report is independent of any insurance company,
law firm, or other entity, and is distributed with the understanding
that ConstructionRisk.com, LLC, and the editor and writers, are not
hereby engaged in rendering legal services or the practice of law.
Further, the content and comments in this newsletter are provided for
educational purposes and for general distribution only, and cannot apply
to any single set of specific circumstances. If you have a legal issue
to which you believe this newsletter relates, we urge you to consult
your own legal counsel. ConstructionRisk.com, LLC, and its writers and
editors, expressly disclaim any responsibility for damages arising from
the use, application, or reliance upon the information contained herein.
Copyright 2009, ConstructionRisk, LLC
Publisher & Editor:
J. Kent Holland,
Jr., Esq.
1950
Old Gallows Rd
Suite 750.
Vienna
,
VA
22182
703-623-1932
Kent@ConstructionRisk.com
_____________________________________________
|