Liquidated Damages in Design-Build subcontract Are Enforceable Even Where Far Exceeding Actual Damages

See article in Construction Risk Newsletter:
ConstructionRisk.com Report Vol. #14, Issue #1

See article in the following topic indices:
,,,,,, 

Email this page to a friend:

Where a contractor entered into a design-build contract with the U.S. Navy to build four buildings at the Pensacola Naval Air Station, and included a liquidated damages (LD) provision in the subcontract with its subcontractor, that LD provision was enforceable despite evidence that the actual damages incurred by the contractor as a result of alleged [...]

Email this page to a friend:

Subcontractor Had Rights as Third Party Beneficiary Under Federal Government Contract

See article in Construction Risk Newsletter:
ConstructionRisk.com Report Vol. #13, Issue #8

See article in the following topic indices:
,,, 

Email this page to a friend:

Where the federal government contracting officer issued a contract modification to the prime contract to require the government to issue a two-party check jointly to the prime and a subcontractor that had complained about not being paid, the subcontractor had rights against the government as a third party beneficiary when the government failed to issue [...]

Email this page to a friend:

Accord and Satisfaction Barred Contractor Claim for Additional Compensation

See article in the following topic indices:
,,, 

Email this page to a friend:

Where a contractor timely completed a construction contract for the U.S. Army Corps of Engineers and accepted payment which included changes required by the Corps, the contractor was barred from later filing a claim for additional compensation.  The claim was barred by accord and satisfaction because when signing change orders the contractor did not reserve [...]

Email this page to a friend:

Proving Constructive Acceleration Claims Can be Difficult for Contractors

See article in the following topic indices:
,,, 

Email this page to a friend:

By: Katz & Stone When claiming entitlement to cost for constructive acceleration, contractors must prove that any time extensions received were inadequate to remedy their excusable delays.  Time extensions do not have to be granted immediately, and the mere failure to grant extensions does not, by itself, constitute constructive acceleration so long as the procedures [...]

Email this page to a friend:

Hurricane Katrina’s Impact on Existing U.S. Government Contracts

See article in the following topic indices:
,, 

Email this page to a friend:

For contractors performing work on existing federal contracts in affected areas, assessing the impact of the hurricane on their contracts raises a number of issues and concerns.  Federal construction and supply contracts typically provide for a non-compensable time extension for unusually severe weather or Acts of God.  See, e.g., The Rice Co., AGBCA No. 2003-188-1, [...]

Email this page to a friend:

De Facto Takeover: Are a Surety’s Rights Protected?

See article in the following topic indices:
,,, 

Email this page to a friend:

By Michael J. Carrato, Esq. A Miller Act surety needs to be aware of certain notice requirements if it decides to take over performance for its principal on a federal construction contract.  Informal or “constructive” notice that a surety intends to take over management of a project may not be enough to protect the surety’s [...]

Email this page to a friend:

Contractor Entitled to Rely Upon Government’s Implied Warranty of Specifications

See article in the following topic indices:
,,,, 

Email this page to a friend:

Where a contractor had to revise the government’s design and expend additional time and expense to construct a door for a helicopter hangar, the government argued unsuccessfully that the contractor was barred by a general disclaimer from claiming entitlement to a change order for its extra costs. The specifications contained a general disclaimer advising prospective [...]

Email this page to a friend:

Written Notice of Deviations from Specifications Is Required With Shop Drawing Submittals

See article in the following topic indices:
,, 

Email this page to a friend:

The Owner’s approval of a shop drawing submittal that deviates from specification requirements does not relieve the contractor where the contractor failed to notify the owner in writing of the variations from the specifications and obtain approval from the owner. The U.S. Navy issued specifications for the construction of a facility in Greece. One of [...]

Email this page to a friend:

Bid Bonds on Federal Contracts – Just the Fax

See article in the following topic indices:
,,, 

Email this page to a friend:

Bidders on most sealed-bid federal contracts are required to furnish a bid guarantee along with their bids. The bid guarantee is usually provided in the form of a bid bond issued by a Treasury-listed surety company. The purpose of the bid bond is to guarantee the payment of liquidated damages to the government in the [...]

Email this page to a friend:

Government Warranty of Performance-Type Specifications

See article in the following topic indices:
,,, 

Email this page to a friend:

Two recent Board of Contract Appeals decisions addressed the conflict between the Government’s implied warranty of its design and its attempt to disclaim that warranty through the use of performance specifications.  In both cases, the Boards allowed the contractors to recover damages. In Edsall Construction, Inc., ASBCA No. 51,787, 01-1 BCA 31,425, the Government awarded [...]

Email this page to a friend: