Equitable Adjustment Allowed for Deductive Change Despite Contractor’s Unbalanced Bid

See article in the following topic indices:
,,,, 

Email this page to a friend:

By:  Philip R. White, Esq. Where a public owner issued a deductive change order, it was required to equitably adjust a contract despite the absence of an equitable adjustment clause in the contract, despite the absence of specifications or applicable public contracts law, and despite the fact that the contractor’s bid was unbalanced .  In [...]