by Kent Holland | Jan 12, 2012 | Newsletter Article
Where a design-builder (“contractor”) was assessed liquidated damages by the Contracting Officer under a U.S. Coast Guard contract for the design and construction of prefabricated metal buildings, the contractor filed suit against the Government seeking remission of...
by Kent Holland | Jan 12, 2012 | Newsletter Article
A design-build contractor that entered into a fixed-price contract to upgrade the heating, air conditioning and ventilation (HVAC) system in college dormitories satisfactorily performed all the work it was contracted to do, but also performed significant additional...
by Kent Holland | Jan 3, 2012 | indemnification clause, Newsletter Article
Where a firm (Parsons Infrastructure) entered into a contract to design and construct a soda ash processing plant for Kerr-McGee Chemical Corp (KM) and agreed to provide KM with a defense and indemnity against losses arising out of negligent performance of its work, ...
by Kent Holland | Jan 3, 2012 | Newsletter Article
Where a design-builder filed suit against the project owner (animal fee manufacturing plant) to collect the balance of fee that was being withheld, the owner countersued for almost $2 million alleging that contractor breached the contract’s requirements for concrete...
by Kent Holland | Jan 3, 2012 | Newsletter Article
Where a contractor entered into a design-build contract with the U.S. Navy to build four buildings at the Pensacola Naval Air Station, and included a liquidated damages (LD) provision in the subcontract with its subcontractor, that LD provision was enforceable despite...