by Kent Holland | Dec 19, 2016 | differing site conditions, Newsletter Article
After final payment was made under its contract, a utility construction contractor submitted a written request for additional payment to the project owner seeking payment for extra work it performed as well as increased costs due to delays and disruptions during the...
by Kent Holland | Dec 19, 2016 | Newsletter Article
A man who fell from a retaining wall at a streetscape project being built for a city filed suit against the city as well as the architect (BL Companies, Inc.) for the project. The legal theory against the architect was that he had created a public nuisance by failing...
by Kent Holland | Dec 19, 2016 | Newsletter Article
The “no-voluntary payments” condition of an insurance policy was violated by an insured subcontracting concrete company, when it entered into a settlement with its prime contractor and paid damages for contractual liability for construction delays as well as for an...
by Kent Holland | Dec 19, 2016 | economic loss doctrine, Newsletter Article
An error was made by a surveyor in setting the level for a foundation pad for a church building. A construction contractor then proceeded to excavate dirt from the foundation area, believing the resulting level would be higher than required by the base flood...
by Kent Holland | Dec 19, 2016 | Newsletter Article
Where a contractor sought a request for clarification to the project architect concerning whether rebar was to be tied from the floor slab to the pile caps, the architect responded with a clarification, that ultimately became a change order, directing the slab rebar...
by Kent Holland | Sep 6, 2016 | Newsletter Article
By: Terrence M. McShane, Esquire Lee & McShane, PC Among the critical clauses in design professional contracts are the Dispute Resolution Clauses. For over twenty years, we have advised our clients to opt for Litigation rather than Arbitration as a means of...
Connect