The GSA issued a solicitation for a Request for Proposals on a project. The Request for Qualifications specifiedthat GSA was using a design-build bridging project delivery method and that the bridging documents wereapproximately 30% complete. GSA awarded the contract...
by Kent Holland | Feb 26, 2018 | Newsletter Article
On a design-build project involving MCAS Camp Pendleton, a subcontractor filed suit against Balfour Beatty Construction (“BBC”), the design-build contractor. This was under the Miller Act and alleged breach of contract and breach of implied warranty of specifications...