Termination of Subcontractor was Improper

Subcontractor was 95 percent complete with its work when the general contractor (GC) made changes to the scope of work, failed to timely respond to change order requests, and failed to make payment of amounts then due under the subcontract. Without providing...

Economic Loss Rule Barred Claim against Contractor’s President

An error was made by a surveyor in setting the level for a foundation pad for a church building.   A construction contractor then proceeded to excavate dirt from the foundation area, believing the resulting level would be higher than required by the base flood...